In Ontario, a generator or storage facility connected to a transmitter's system goes through the IESO's connection assessment and approval. The IESO carries out a system impact assessment (SIA) and the transmitter a customer impact assessment (CIA). The result is a Notification of Conditional Approval or a Notification of Disapproval with Reasons. The IESO describes six stages, from preparing the application to commissioning, and restructured its connection deposit in September 2026.
Short answer: what the IESO connection assessment is
The IESO connection assessment is the Independent Electricity System Operator’s review of a new or modified connection to Ontario’s transmission system. It has two parts. The IESO carries out the System Impact Assessment (SIA), which tests the effect on power-system reliability. The transmitter, often Hydro One, carries out the Customer Impact Assessment (CIA), which tests the effect on its facilities and on other customers. Together they form the connection assessment and approval process. For plants on a distribution line, the first step is the distributor; see Ontario generation connection through distributors. The province-by-province context is in distributed generation interconnection in Canada, and the wider code framework in electrical codes and grid connection in Canada.
Who goes through it
The IESO’s connection pages separate two cases.
- Transmitter-connected projects. New or modified connections face the IESO’s SIA and the transmitter’s CIA.
- Distributor-connected projects. They go through the distributor’s connection assessment. A distributor may have to take part in the IESO and transmitter process on the project’s behalf.
The IESO’s pages say transmitter-connected projects generally go through all six stages, while distributor-connected projects may need only the first three.
The six stages
The IESO gives typical durations for each stage. They are its planning figures, not commitments.
| Stage | What happens | Typical duration given by the IESO |
|---|---|---|
| 1 | Prepare the application with the transmitter or distributor | not stated |
| 2 | Obtain conditional approval to connect | about one year |
| 3 | Design and build to the approval’s requirements | 18 to 36 months |
| 4 | Authorize market and program participation | about one month |
| 5 | Register equipment, telemetry and metering | at least three months |
| 6 | Commission equipment and validate performance | at least three months |
Stages 4 to 6 apply to projects that will take part in IESO-administered markets or that connect a new facility to a transmitter’s system.
Inside stage 2
The IESO recommends a face-to-face meeting before any filing, with the applicant’s consultants, the IESO and the transmitter. Then the stage runs in order.
- Application and deposit. The applicant files the application for its facility type. The IESO decides whether it qualifies for an SIA or an expedited SIA, and assigns an identifier.
- SIA agreement. The IESO prepares an agreement under Chapter 4 of the Market Rules for the applicant to sign.
- Draft SIA report. The IESO sends it to the applicant and the transmitter.
- CIA. The transmitter generally starts after the draft SIA report. A separate CIA agreement between the applicant and the transmitter is required.
- Final SIA report. It carries either a Notification of Conditional Approval or a Notification of Disapproval with Reasons.
Final reports are published in the IESO’s application status table at the end of the month in which they are finalized. Later changes issue as addenda. The detailed process sits in the IESO’s market manual on connection assessment and approval, so cite its current version in project files.
What Hydro One adds for transmission generators
Hydro One lays out the transmitter’s side as a sequence.
- Preliminary inquiry and a meeting with planning staff.
- The connection application, filed with both Hydro One and the IESO.
- A study agreement for the CIA.
- The SIA and CIA, with the IESO publishing a final draft SIA before Hydro One finalizes the CIA.
- A connection cost estimate agreement, then a connection and cost recovery agreement.
- Design, build, and execution of a transmission connection agreement before service begins.
The commissioning plan is due 45 days before the in-service date, and final as-built documents follow commissioning. Hydro One states that an average connection takes from 18 months to over three years. It also publishes generation interconnection requirements for its extra-high-voltage and high-voltage networks.
What changed in 2026
The IESO restructured its connection process deposit. It is now tiered by project size in megawatts, and the IESO invoices ad hoc when costs exceed the deposit. The change took effect on 1 September 2026. The IESO also offers two early, voluntary options: the Major Projects Identification Committees process and a technical feasibility study. Unlike Alberta’s cluster assessment, the IESO’s pages describe assessment project by project, with no cluster stage. For that contrast, see AESO connection and technical requirements.
Worked example: a planning timeline
The numbers use the IESO’s typical durations and are illustrative. A transmitter-connected plant that must complete stages 2 to 6 back to back needs:
- Lowest case: 12 + 18 + 1 + 3 + 3 = 37 months.
- Highest case: 12 + 36 + 1 + 3 + 3 = 55 months.
Stage 1 is not included. Some stages can overlap in practice, so the sum is a planning bound, not a forecast. A developer with a commercial operation date in 40 months can see that the lowest case already uses most of the time. The decision is to start the application early and fix the design basis before filing.
Checklist for the engineer
- Confirm whether the project is transmitter-connected or distributor-connected.
- Request the pre-application meeting with the IESO and the transmitter.
- Download the current market manual on connection assessment and approval and record its version.
- Check the deposit under the September 2026 structure for the project size.
- Assemble the facility data the application form asks for.
- Plan the CIA agreement with the transmitter in parallel with the SIA.
- Build the schedule from the IESO’s stage durations, not from a desired date.
- Keep the package ready for your professional engineer to review and stamp.
Related guides
For comparison, see FERC Order 2023 cluster studies in the United States, how ERCOT handles generator interconnection and Grid Code compliance processes in the United Kingdom. The cross-market view is in which interconnection study each market requires. Cybersecurity obligations for bulk-system plants are in NERC CIP requirements. Reliability standard adoption in Ontario is covered in NERC reliability standards in Canada.
From the rules to studies your P.Eng. can stamp
An IESO application moves faster when the facility data and the system model are complete at filing. We prepare the power-system studies and data that feed an application: short-circuit, load-flow and protection inputs and equipment data. The package is ready for your professional engineer (P.Eng.), licensed by Professional Engineers Ontario, to review and stamp. Tiza does not stamp, sign or certify studies in Ontario. Contact us with the connection voltage and plant size.
Frequently asked questions
What is the difference between the SIA and the CIA in Ontario?
The SIA is the IESO's assessment of the effect on the reliability of the power system. The CIA is the transmitter's assessment of the effect on its own facilities and on other customers. They run in sequence and need separate agreements.
Does every Ontario generator need an IESO assessment?
Transmitter-connected projects do. Distributor-connected projects go through the distributor's assessment first, and the distributor takes part in the IESO and transmitter process when the project needs it.
Is conditional approval permission to energize?
No. It tells the applicant what to build to. The IESO describes further stages for market registration, equipment registration and commissioning tests before final approval.