Ontario Generation Connection Requirements for Distributors

Ontario connection requirements for generation: how the OEB Distribution System Code, Hydro One and local utilities shape a project, with a worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

1 Screen with the capacity map2 Application and study agreement3 Connection impact assessment4 Cost and connection agreements5 Single-line and protection checklist6 ESA inspection, commissioning reportAbove 10 MW:IESO assessmentaddedProcess flow4.8 MW AC on a 27.6 kV feederI = 4,800,000 / (1.732 x 27,600)fault: 1.2 x 100.4 = 120.5 A120.5 / 6,000 = 2.0 % of the feederrated current 100.4 Ainverter fault current 120.5 A (1.2 x rated)feeder fault current 6,000 A (own scale)plant adds 2.0 %illustrative; the data sheet gives the real valueStepScreeningApplicationImpact assessmentAgreementsInspection© tizagrp.com1 Screen with the capacity map2 Application and study agreement3 Connection impact assessment4 Cost and connection agreements5 Single-line and protection checklist6 ESA inspection, commissioning reportAbove 10 MW:IESO assessmentaddedProcess flow4.8 MW AC on a 27.6 kV feederI = 4,800,000 / (1.732 x 27,600)fault: 1.2 x 100.4 = 120.5 A120.5 / 6,000 = 2.0 % of the feederrated current 100.4 Ainverter fault current 120.5 A (1.2 x rated)feeder fault current 6,000 A (own scale)plant adds 2.0 %illustrative; the data sheet gives the real valueStepScreeningApplicationImpact assessmentAgreementsInspection© tizagrp.com
Ontario connection steps for a distribution-connected generator: screening with the capacity map, application and study agreement, connection impact assessment, cost and connection agreements, single-line and protection checklist, and Electrical Safety Authority inspection with the commissioning report, with the 4.8 MW plant at 27.6 kV drawing 100.4 A, adding 120.5 A in a fault, 2.0 percent of a 6,000 A feeder fault. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

In Ontario, a generator connected to a distribution network applies to the local distribution company or to Hydro One. The Ontario Energy Board's Distribution System Code and its DER Connection Procedures set the common steps, and each distributor adds technical requirements of its own. The Code was amended again in 2026, with changes in force on 1 May and 1 August. The Electrical Safety Authority inspects the installation, and larger projects add the IESO.

Short answer: Ontario connection requirements for generation

Ontario connection requirements for generation depend on who owns the line. For a distribution connection, the owner is a local distribution company (LDC) or Hydro One. Both work under the Distribution System Code (DSC) of the Ontario Energy Board (OEB). The Code sets the common process. Each distributor then publishes technical requirements, forms and agreements. Larger projects, and any project at transmission level, also involve the Independent Electricity System Operator (IESO). The broader comparison is in Canadian distributed generation interconnection by province, and the code framework in electrical codes and grid connection in Canada.

The documents that apply

Read these four layers in order.

  1. The Distribution System Code. It is the OEB’s rulebook for distributors. Amendments came into force on 1 May and 1 August 2026, and the consolidated Code is marked last revised on 1 August 2026. Use the version the OEB marks as current.
  2. The DER Connection Procedures (DERCP). The OEB issued version 3 with the final amendments on 18 December 2025, in force from 1 May 2026. They standardize the steps and forms that distributors use for distributed energy resources.
  3. The distributor’s technical requirements. Since 1 May 2026 the micro class covers facilities of 12 kW or less, up from 10 kW. Hydro One publishes a micro-generation document for that class. For larger facilities at 50 kV and below it publishes a distributed energy resources document, Revision 3 of 15 April 2013. It revises that document through numbered bulletins. The latest bulletin on its page is Bulletin 5 of 15 May 2023. Local utilities publish their own packages.
  4. The installation code. The Ontario Electrical Safety Code, administered with the Electrical Safety Authority (ESA), governs the customer’s installation.

How the process runs

Distributor packages published in 2025 and 2026 follow a similar order. The names differ slightly.

  1. Screening. The OEB launched the Centralized Capacity Information Map on 29 January 2026. It shows available load and hosting capacity on distribution systems. Distributors update it quarterly. Use it only to screen, not to promise capacity.
  2. Application and study agreement. The applicant files the connection impact assessment application and signs a study agreement.
  3. Connection impact assessment (CIA). The distributor studies the effect on its network and returns the technical conditions. At transmission level the same letters stand for the transmitter’s customer impact assessment.
  4. Cost and connection agreements. The parties sign a connection cost agreement and a connection agreement.
  5. Protection and drawings. The distributor asks for a single-line diagram and a protection philosophy checklist. Hydro One publishes its own checklist and single-line requirements.
  6. Inspection and commissioning. ESA inspects the installation. The generator then submits a commissioning report before it operates in parallel.

Size classes

Distributor packages published in 2026 describe a range for non-micro generation that runs from 12 kW up to 10 MW. They break it into small and mid-sized classes with different technical requirements. Utility guidance describes facilities above 10 MW as outside the distributor’s ordinary process, with the IESO’s assessment added. Treat the exact class limits as the distributor’s text. Voltage can move a class limit, so read the table for your connection voltage.

For the IESO stage, see the IESO connection assessment and approval process.

Technical requirements for inverter plants

Distributors expect certified inverters and ride-through behavior that matches their requirements. Hydro One’s Bulletin 4 of 30 April 2021 refers to CSA C22.3 No. 9 and to UL 1741 SA for the ride-through of inverter-based generators. Where a US design uses IEEE 1547, see the IEEE 1547 guide and who certifies what under IEEE 1547 and UL 1741 SB. Confirm with the distributor which route it accepts.

Worked example: what the impact assessment checks first

The numbers below are illustrative. A solar plant of 4.8 MW AC connects to a 27.6 kV feeder.

  • Rated current at power factor 1: 4,800,000 ÷ (1.732 × 27,600) = 100.4 A.
  • Assume the inverters can contribute 1.2 times rated current during a fault. Contribution = 1.2 × 100.4 = 120.5 A.
  • Assume the feeder’s three-phase fault current at the connection point is 6,000 A. The plant adds 120.5 ÷ 6,000 = 2.0 %.

A contribution of that size rarely changes breaker duty, but the distributor still studies it with its own model. The result shows why the application asks for inverter fault-current data, not only the nameplate. The real value comes from the manufacturer’s data sheet.

Checklist for the engineer

  • Identify the distributor and download its current technical requirements.
  • Record the DSC date and the DERCP version the distributor applies.
  • Screen the feeder with the capacity map, then confirm with the distributor.
  • Match plant AC capacity and voltage to the distributor’s size classes.
  • Prepare the single-line diagram, protection philosophy checklist and inverter data.
  • Confirm which ride-through standard the distributor accepts.
  • Plan ESA inspection and the commissioning report early.
  • Check whether the project is large enough to add the IESO.
  • Keep the package ready for your professional engineer to review and stamp.

Compare with the UK distribution process in how to read a DNO connection offer and the Australian one in embedded generation connection by distributor. For the anti-islanding behavior that distributors check, see IEEE 1547 anti-islanding.

From the rules to a design your P.Eng. can stamp

An Ontario application moves faster when the package matches the distributor’s documents. We prepare the engineering design for the connection: single-line diagram, protection approach and the equipment data the study needs. The package is ready for your professional engineer (P.Eng.), licensed by Professional Engineers Ontario, to review and stamp. Tiza does not stamp, sign or certify designs in Ontario. Contact us with the feeder voltage and plant size.

Frequently asked questions

Who do I apply to for a generator on an Ontario distribution line?

You apply to the distributor that owns the line, either a local distribution company or Hydro One. Its public package lists the forms, the study agreement and the technical requirements that apply to your size.

Does the Distribution System Code set all the technical requirements?

No. The Code sets the process and common obligations. Each distributor publishes technical interconnection requirements for generators, so a plant in one service territory can face different details from the next.

Does the Electrical Safety Authority replace the utility review?

No. The utility reviews how the plant affects its network. The Electrical Safety Authority inspects the electrical installation under the Ontario Electrical Safety Code. A project needs both.