UL 1741 SB vs IEEE 1547: Who Certifies What

UL 1741 SB vs IEEE 1547: one sets interconnection behavior, the other certifies the product. See who decides what, with a worked example and a checklist.

By Shadai García, CEO and protection engineer at Tiza Group.

IEEE 1547-2018 + 1547a-2020interconnection requirementsIEEE 1547.1-2020test proceduresUL 1741, Supplement SBlaboratory listingdesign basismodel, firmware, listingutilitytechnical rulessettingstableutility permission to operate1.06 x 480 V = 508.8 V line to linerange 1.05 to 1.10 pu = 504 to 528 V508.8 V is inside the rangedatasheet does not state Supplement SBask for the certificate before accepting504 V528 Vinverter range508.8 V requiredsetting fits the unitlisting supplement not confirmeda fitting setting is not a listingChainRequirementTest procedureListingDesign basis© tizagrp.comIEEE 1547-2018 + 1547a-2020interconnection requirementsIEEE 1547.1-2020test proceduresUL 1741, Supplement SBlaboratory listingdesign basismodel, firmware, listingutilitytechnical rulessettingstableutility permission to operate1.06 x 480 V = 508.8 V line to linerange 1.05 to 1.10 pu = 504 to 528 V508.8 V is inside the rangedatasheet does not state Supplement SBask for the certificate before accepting504 V528 Vinverter range508.8 V requiredsetting fits the unitlisting supplement not confirmeda fitting setting is not a listingChainRequirementTest procedureListingDesign basis© tizagrp.com
IEEE 1547 versus UL 1741 SB: requirement, test procedure, laboratory listing and design basis with the utility rules, and a volt-watt setpoint of 1.06 per unit on 480 V checked against the inverter range. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

UL 1741 SB vs IEEE 1547 is not a choice between two rivals. IEEE 1547 states how a distributed energy resource must behave at the utility connection, IEEE 1547.1 defines how that behavior is tested, and UL 1741 with Supplement SB is how a laboratory certifies an inverter against those tests. The utility then decides which settings apply.

UL 1741 SB vs IEEE 1547 comes up on US inverter projects, and the two documents do different jobs. One says what the equipment must do. The other is how a laboratory proves that a product can do it.

This guide is based on IEEE 1547-2018 with its 2020 amendment, IEEE 1547.1-2020, and the third edition of UL 1741 that includes Supplement SB.

Short answer

IEEE 1547 sets the interconnection and interoperability requirements for distributed energy resources (DER) on the distribution system. IEEE 1547.1 gives the test procedures. UL 1741 with Supplement SB is the certification route: a nationally recognized laboratory tests the inverter against those procedures and lists it. The utility decides which settings are required and whether a listed unit is accepted for a given site.

Figure: three boxes in sequence, interconnection standard, test procedure and certification, with the utility and the installer shown at the end of the chain.

The wider framework is in the US electrical codes and grid interconnection guide. The functions that Supplement SB adds are explained in the guide on UL 1741 SB grid support.

Who does what

DocumentWhat it isWho uses it
IEEE 1547-2018 (with 1547a-2020)Interconnection and interoperability requirements for DERUtilities, regulators, designers
IEEE 1547.1-2020Test procedures to check conformity with IEEE 1547Laboratories, manufacturers
UL 1741, third edition, with Supplement SBProduct safety standard that includes the grid-support testsLaboratories, manufacturers, installers, inspectors
Utility rules or tariffSettings, studies and process for a given networkEveryone on the project

Where the confusion comes from

The three documents appear together in utility checklists, so they are often treated as one. Three differences matter in practice.

  • A standard is not a certificate. IEEE 1547 is a document. It cannot be held up as proof that a product complies. The listing is the proof.
  • A listing is not an approval. A listed inverter can still be installed with the wrong settings, on a feeder that cannot take it, or without the study the utility requires.
  • A listing is not the final word on edition. Supplement SB indicates compliance with IEEE 1547-2018 and IEEE 1547.1-2020. States have adopted these requirements at different times, so the edition your utility asks for must be confirmed.

The earlier supplement

Supplement SA was introduced to meet California’s early smart-inverter requirements. Supplement SB follows the national standard. Some programs still reference SA, and some inverters carry both, with the settings selected by firmware. The program that applies to your project, not the market in general, decides which listing is acceptable.

How the chain works on a project

  1. The utility’s technical requirements name the standard and the required listing.
  2. The designer selects an inverter whose listing matches, and records the model, firmware and listing in the design basis.
  3. The study and the settings table use the required values inside the allowed ranges.
  4. The installer loads the settings and the commissioning check confirms them. See IEEE 1547 commissioning tests.
  5. The utility gives permission to operate.

Where a plant is larger and connects at transmission level, the framework changes. See IEEE 2800 vs IEEE 1547.

Worked example (illustrative)

A designer compares an inverter datasheet with a utility’s requirements for a 250 kW plant on a 480 V service. The utility asks for a listing to UL 1741 with Supplement SB, and for a volt-watt function that starts to reduce power at 1.06 per unit voltage.

Step 1. Convert the setpoint to volts. 1.06 × 480 V = 508.8 V line to line.

Step 2. Check the inverter range. The datasheet in this example lets the volt-watt start be set between 1.05 and 1.10 per unit, which is 504 V to 528 V. The required 508.8 V is inside the range.

Step 3. Check the evidence. The datasheet shows a listing to UL 1741 but does not state Supplement SB. The designer asks the manufacturer for the listing certificate.

Step 4. Decide. The setting fits, but the unit cannot be accepted until the certificate confirms the supplement the utility requires. The listing is recorded in the design basis only after that.

The numbers are illustrative. The lesson is that a setting that fits is not evidence of a listing.

What the utility usually asks for

The utility’s technical requirements normally list the standard, the listing and the study. Many also ask for a datasheet, the listing certificate, a single-line diagram and a settings table with the application. Having these ready before the application shortens the review, because the reviewer can match each requirement with a document instead of writing back for it. Request the listing certificate from the manufacturer with the quotation.

Checklist for the engineer

  • Identify the edition of IEEE 1547 and the listing the utility requires.
  • Obtain the listing certificate for the exact model and firmware.
  • Check that the required settings fall inside the unit’s adjustable ranges.
  • Note whether the program still accepts Supplement SA or requires SB.
  • Record the listing, firmware and settings in the design basis.
  • Plan the commissioning check against the approved settings table.
  • Confirm in writing whether the utility accepts the listing as it stands.

Who signs and seals

In the United States a design is normally signed and sealed by a professional engineer licensed in the state of the project. Our engineering is delivered ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States, and does not issue product listings.

How Tiza can help

If you need the single-line diagram, the equipment selection basis and the settings table prepared for the utility submittal, Tiza provides engineering design, remotely and in English, ready for your engineer of record to review and stamp. Contact us with the inverter data and the utility’s requirements.

Frequently asked questions

Is UL 1741 SB the same as IEEE 1547?

No. IEEE 1547 is an interconnection standard for distributed energy resources. UL 1741 is a product safety standard, and Supplement SB adds the grid-support tests that follow IEEE 1547 and IEEE 1547.1. One defines the behavior, the other certifies the product.

Does a UL 1741 SB listing mean the utility will approve the project?

No. The listing shows that the inverter type passed the tests. The utility still reviews the study, the settings, the protection and the commissioning evidence for the specific site.

Who sets the voltage and frequency settings, the standard or the utility?

The standard gives default values and allowed ranges. The utility or its regulator can require values inside those ranges. The installer loads the required set and records it at commissioning.