UL 9540A Thermal Runaway Test and UL 9540 Explained

UL 9540 lists a battery storage system; UL 9540A tests thermal runaway fire spread. See how they differ, what the test levels give and a worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

Cell levelsingle cellRunaway temperaturegas releasedModule levelcells in a moduleSpread betweencells in the moduleUnit levelcabinet or rackSpread between modulesfire outside the unitInstallation levellarge-scale layoutLarge-scale testof the arrangementUL 9540 listingFire code reviewProcess flow16 cabinets × 261 kWh = 4,176 kWh600 / 261 = 2.3: at most 2 per group (522 kWh)16 / 2 = 8 groups8 groups need 7 separations8 groups of 2 cabinets7 separations between the groups600 kWh assumed limit2 cabinets: 522 kWh3 cabinets: 783 kWhillustrative values; the 600 kWh limit is an assumptionUL 9540ACellModuleUnitInstallationListing© tizagrp.comCell levelsingle cellRunaway temperaturegas releasedModule levelcells in a moduleSpread betweencells in the moduleUnit levelcabinet or rackSpread between modulesfire outside the unitInstallation levellarge-scale layoutLarge-scale testof the arrangementUL 9540 listingFire code reviewProcess flow16 cabinets × 261 kWh = 4,176 kWh600 / 261 = 2.3: at most 2 per group (522 kWh)16 / 2 = 8 groups8 groups need 7 separations8 groups of 2 cabinets7 separations between the groups600 kWh assumed limit2 cabinets: 522 kWh3 cabinets: 783 kWhillustrative values; the 600 kWh limit is an assumptionUL 9540ACellModuleUnitInstallationListing© tizagrp.com
UL 9540A test levels as a block diagram: cell, module, unit and installation, each passing its data (runaway temperature and gas, spread between cells, spread between modules and fire outside the unit, large-scale test) to the UL 9540 listing and to the fire code review, with the worked example of 16 cabinets of 261 kilowatt-hours, 4,176 kilowatt-hours in total, groups of 2 cabinets of 522 kilowatt-hours against an assumed 600 kilowatt-hour limit, 8 groups and 7 separations. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

UL 9540 is the product safety standard for energy storage systems and equipment. UL 9540A is a test method that measures how a battery behaves in thermal runaway and how fire spreads. The test report feeds the product listing and the fire code review, but it is data, not an approval. A design needs both the listing and the right edition of the test.

A battery cabinet arrives with two labels that sound alike. One says UL 9540. The other is a test report called UL 9540A. They answer different questions, and confusing them leads to rejected permits.

Editions cited: UL 9540, third edition (2023), and UL 9540A, fifth edition (2025). The sixth edition of UL 9540A was published in March 2026. Confirm the edition the authority accepts.

Short answer

UL 9540 is the safety standard for energy storage systems and equipment. A listing means a recognized laboratory evaluated the system as a product. UL 9540A is a test method. It forces a battery into thermal runaway, a self-heating chain reaction, and measures whether fire spreads, how much heat is released and what gases come out. The results feed the listing and the fire code review. The fire code that most jurisdictions use for siting is covered in the NFPA 855 guide.

The wider framework is in the US electrical codes and grid interconnection guide.

Figure: the test levels, from cell to module to unit to installation, with the data each level passes to the listing and to the fire review.

UL 9540 in plain terms

The standard looks at the system as a whole. It covers the battery, the battery management system, the power conversion and the safety functions that work together. The aim is to show that the combination was evaluated, not only the parts. A system listing usually builds on listings of the components, such as the battery to the UL 1973 standard and the inverter to UL 1741. See the guide on BESS parts and standards for how those parts fit.

A listing does not replace the installation review. The NEC Article 706 guide covers what the electrical inspector checks, and the interconnection guide covers what the utility checks.

UL 9540A in plain terms

The test method works in levels.

  • Cell level. A single cell is driven into thermal runaway to find out at what temperature it happens and what gas it releases.
  • Module level. The test checks whether a failing cell spreads to its neighbors in a module.
  • Unit level. A full cabinet or rack is tested to see whether fire spreads between modules and outside the unit.
  • Installation level. A large-scale test of a representative arrangement. The sixth edition expands this level, in line with the large-scale fire testing that the 2026 edition of NFPA 855 calls for.

In the fifth edition, the installation level was run only when the unit level did not meet its criteria. In the sixth edition, the unit level stays for residential systems and for non-residential systems with an active propagation prevention system. Other non-residential systems move to the installation level, which now has pass and fail criteria. During the transition, reports to either edition are in circulation.

What the report gives a designer

The report is not a listing. Even where a test level has pass and fail criteria, it provides data that others interpret:

  • Whether thermal runaway propagated between cells, modules and units.
  • Peak heat release and the flame extent outside the enclosure.
  • The flammable gas released and its composition.
  • Whether the enclosure walls and doors withstood the exposure.

Fire protection engineers use these values to justify spacing, barriers, ventilation and suppression. The guide on lithium-ion battery safety and service life explains the chemistry behind the results.

Worked example (illustrative)

Illustrative data, not from any project. A site uses 16 cabinets with a nominal 261 kWh each. The fire authority is assumed to accept groups of cabinets up to 600 kWh, with a barrier or spacing between groups. The cabinet report shows no propagation between cabinets.

  1. Total energy: 16 x 261 = 4,176 kWh.
  2. Cabinets per group: 600 / 261 = 2.3, so at most 2 cabinets per group (522 kWh).
  3. Number of groups: 16 / 2 = 8.
  4. Gaps needed: 8 groups need 7 separations.

If the report instead showed propagation between cabinets, the authority could require a smaller group or a barrier. The 600 kWh figure is an assumption for the example, not a code value. The real limit comes from the edition and local amendments in force.

Reading a listing and a report together

Two checks save most of the trouble. First, match names: the model, the configuration and the firmware named on the listing must be the ones on the purchase order. Second, match scope: the report should state the test level, the edition and the chemistry. A report written for one chemistry says little about another. When the manufacturer changes the cell supplier, ask whether the listing and the report still cover the new cell. If they do not, the authority may treat the product as untested.

Where projects go wrong

  • Treating a test report as a listing, or the reverse.
  • Quoting an edition of UL 9540A different from the one the authority accepts.
  • Changing the cabinet layout after the test, so the report no longer represents the product.
  • Assuming a listing covers site-specific siting.
  • Not keeping the report with the project records for the inspector.

Checklist for the engineer

  • Ask the authority which edition of UL 9540A and of the fire code it accepts.
  • Obtain the UL 9540 listing for the exact model and configuration.
  • Obtain the UL 9540A report, its edition and the test level.
  • Check that the installed layout matches the tested one.
  • Extract propagation, heat release and gas data for the fire review.
  • Keep the evidence in the commissioning records.

Who signs and seals

Storage designs for a US project are normally reviewed and sealed by a professional engineer licensed in the state of the project. Fire protection work follows local rules. Tiza delivers engineering ready for your engineer of record to review and stamp. Tiza does not sign, seal or certify work in the United States, and it does not issue listings or test reports.

How Tiza can help

If you need to assemble the evidence for a storage permit, Tiza delivers engineering design in English, remotely: the single-line diagram, the equipment schedule and the documentation matrix that ties each listing and test report to the model installed. All of it is ready for your engineer of record to review and stamp. Contact us with your equipment data.

Frequently asked questions

What is the difference between UL 9540 and UL 9540A?

UL 9540 evaluates a complete energy storage system as a product and results in a listing. UL 9540A is a test method for thermal runaway fire propagation. Its report supports the listing and the fire code review but is not a listing by itself.

Does passing UL 9540A mean a battery system is safe?

No. The test reports how the system behaves in a defined thermal runaway scenario, including whether fire spreads and what gas is released. The authority and the designer use that data to set separation, protection and siting.

Which edition of UL 9540A applies to a project?

It depends on the date of the test and on what the authority accepts. The fifth edition was published in 2025, and the sixth edition, published in March 2026, expands the large-scale installation-level test. Ask the authority which edition it accepts.