Solar Farm Interconnection Studies in Canada

Interconnection studies a solar farm goes through in Ontario, Alberta, Québec and BC: who runs each one, how long the path takes, and a worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

OntarioApplicationwith transmitterSIA (IESO)CIA (transmitter)Conditionalapproval, 1 yearAlbertaSASRintake windowCluster: 5 MW+Independent: <5 MWExecutionphaseQuébecRequest withtechnical dataInterconnectionstudy + FacilitiesConnectionagreementBritish ColumbiaFeasibilitystudySystem impactstudyFacilitiesstudyStudy path40 MW AC solar farm at transmission voltageAlberta: 40 MW above 5 MW, cluster assessmentreactive range 0.33 x 40 = 13.2 Mvar each wayshort-circuit ratio 600 / 40 = 15 and 200 / 40 = 5Ontario: 12 + 18 + 1 + 3 + 3 = 37 monthswith 36 months to build: 55 monthsOntario schedule, months01224364855approval 12build 1837 monthsmarket, register, commission: 1 + 3 + 3approval 12build 3655 months1 + 3 + 3illustrative farm; IESO typical durationsProcessApplicationStudyApprovalBuildCommissioning© tizagrp.comOntarioApplicationwith transmitterSIA (IESO)CIA (transmitter)Conditionalapproval, 1 yearAlbertaSASRintake windowCluster: 5 MW+Independent: <5 MWExecutionphaseQuébecRequest withtechnical dataInterconnectionstudy + FacilitiesConnectionagreementBritish ColumbiaFeasibilitystudySystem impactstudyFacilitiesstudyStudy path40 MW AC solar farm at transmission voltageAlberta: 40 MW above 5 MW, cluster assessmentreactive range 0.33 x 40 = 13.2 Mvar each wayshort-circuit ratio 600 / 40 = 15 and 200 / 40 = 5Ontario: 12 + 18 + 1 + 3 + 3 = 37 monthswith 36 months to build: 55 monthsOntario schedule, months01224364855approval 12build 1837 monthsmarket, register, commission: 1 + 3 + 3approval 12build 3655 months1 + 3 + 3illustrative farm; IESO typical durationsProcessApplicationStudyApprovalBuildCommissioning© tizagrp.com
Flow chart of the interconnection study path of a solar farm by province, with the document each stage produces: Ontario application, system impact assessment by the IESO and customer impact assessment by the transmitter, Alberta system access service request with cluster or independent assessment, Québec interconnection study and Facilities Study, and British Columbia feasibility, system impact and facilities studies; with the Ontario schedule of 37 or 55 months for a 40 MW example. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A solar farm in Canada does not follow one national study sequence. In Ontario the IESO runs a system impact assessment and the transmitter a customer impact assessment. In Alberta the AESO uses a cluster assessment for projects injecting 5 MW or more. Hydro-Québec runs an interconnection study and a facilities study under its tariff, and BC Hydro posts feasibility, system impact and facilities studies. Each province has its own stages, owners and timelines.

Short answer: solar farm interconnection studies in Canada

A solar farm interconnection study in Canada is run by the system operator or the transmission utility of the province, and the sequence differs in each. Ontario uses a system impact assessment by the IESO and a customer impact assessment by the transmitter. Alberta uses a cluster assessment for projects of 5 MW or more. Hydro-Québec uses an interconnection study followed by a facilities study. BC Hydro posts feasibility, system impact and facilities studies. For the wider frame, see the overview of Canadian electrical codes and grid connection, and for a cross-country table, interconnection study by country.

Ontario: IESO assessment and transmitter assessment

The IESO describes six stages for a new or modified facility:

  1. Prepare the application with the transmitter or distributor.
  2. Obtain conditional approval to connect, typically about one year.
  3. Design and build, 18 to 36 months.
  4. Authorise market and program participation, about one month.
  5. Register equipment, at least three months.
  6. Commission equipment and validate performance, at least three months.

For a transmission connection, the IESO runs the system impact assessment (SIA) and the transmitter runs the customer impact assessment (CIA). For a distribution connection, the distributor’s process comes first and the distributor may involve the IESO and the transmitter. Stages 4 to 6 apply to market participants.

Alberta: system access service request and cluster assessment

The AESO process has an assessment phase and an execution phase. The developer files a System Access Service Request (SASR) through an intake window. Generation and storage projects that inject 5 MW or more at the connection point, whether on the transmission or the distribution system, go through the cluster assessment. Projects injecting less than 5 MW use the independent assessment. For a plant on the distribution system, the distribution facility owner is the first contact. The AESO guides on the process were last updated in 2025 and 2026, so download the current edition.

Québec: interconnection study and facilities study

Hydro-Québec’s transmission requirements define the interconnection study as the system impact study of its Open Access Transmission Tariff, and refer to the Facilities Study of the same tariff. The request includes the technical information listed in an annex of the requirements. Hydro-Québec then sends a connection agreement that sets out the applicable technical requirements. Details of those requirements are in Hydro-Québec technical requirements for generators.

British Columbia: studies posted under the tariff

BC Hydro posts study reports for its transmission generator interconnection queue under its Open Access Transmission Tariff. The listings show feasibility studies, system impact studies and facilities studies. Read the tariff and the current queue documents for the stage rules and the timelines.

What the studies look at

Names change, but the technical content is similar. A system impact study usually checks:

  • Short-circuit levels before and after the plant, which affect breaker ratings and protection. See short-circuit study.
  • Load flow: thermal loading and voltage on the nearby network. See load flow study.
  • Dynamic behaviour: stability, ride-through and inverter controls, sometimes with electromagnetic transient models. See EMT study.
  • Protection: the scheme at the connection point, as covered in protection at the point of interconnection.

The operator may also ask for model data. In Alberta, ISO rules 503.20 and 503.21 deal with model validation testing and reporting facility modelling data. For the US equivalent of the stage sequence, see interconnection study stages.

Worked example (illustrative)

A 40 MW AC solar farm connects at transmission voltage. The fault levels are assumed values.

  1. Route. In Alberta, 40 MW injection is above 5 MW, so the project goes through the cluster assessment. In Québec, 40 MW is above the 1.0 MW threshold of the transmission requirements. In Ontario, it needs the SIA and CIA.
  2. Reactive capability to design for. Ontario Appendix 4.2 asks for up to 33% of rated active power, at the high-voltage terminal of the main output transformer. That is 0.33 × 40 = 13.2 Mvar. Québec asks for ±0.33 p.u. at a power factor of 0.95: 40 × tan(acos 0.95) = 13.1 Mvar. Design for about 13.2 Mvar each way and let the study confirm.
  3. Short-circuit ratio at the connection point. If the fault level is 600 MVA, the ratio is 600 ÷ 40 = 15. If it is 200 MVA, the ratio is 200 ÷ 40 = 5. The lower value signals a weaker connection, and the operator may ask for dynamic or EMT studies. The operator decides the threshold.
  4. Ontario schedule. Add the IESO’s typical durations. With 18 months to build: 12 + 18 + 1 + 3 + 3 = 37 months. With 36 months to build: 12 + 36 + 1 + 3 + 3 = 55 months.

Checklist for the engineer

  • Identify the operator or utility for the connection point and its current process document.
  • Confirm the study path for the plant size and voltage.
  • Prepare the single-line diagram, inverter data sheets and transformer data.
  • Prepare the dynamic models and the ride-through settings.
  • Calculate reactive capability at the connection point, not at the inverter.
  • List the agreements, deposits and deadlines in the process.
  • Keep a dated record of every data change after filing.
  • Have the study reports reviewed by the engineer of record before accepting conditions.

In Canada, electrical engineering is stamped by a professional engineer (P.Eng.) licensed in the province or territory of the project. Tiza prepares studies and engineering ready for your P.Eng. to review and stamp. Tiza does not stamp, sign or certify designs.

From the study request to a package your engineer can stamp

A well-prepared package shortens the questions between filing and the first study result. We run power-system studies for solar and storage plants and prepare the single-line diagrams, protection approach and equipment data, ready for your engineer of record to review and stamp. Contact us with the plant data and the connection point.

Figure: flow chart of the study path in Ontario, Alberta and Québec, with the document each stage produces.

References

  • IESO, Connection Process (stages 1 to 6); Renewed Market Rules, Chapter 4 Appendices, Issue 2.0, December 3, 2025, Appendix 4.2.
  • AESO, Connecting to the grid: assessment phase, cluster assessment and independent assessment; ISO rules 503.20 and 503.21.
  • Hydro-Québec TransÉnergie, Technical Requirements for the Connection of Generating Stations to the Hydro-Québec Transmission System, Decision D-2022-088, effective July 15, 2022.
  • BC Hydro, Transmission Generator Interconnection Studies page.

Frequently asked questions

What is a system impact assessment in Ontario?

It is the IESO study of how a new or modified transmission connection affects grid reliability. The transmitter runs a separate customer impact assessment. Both apply to new or modified connections to the transmission system.

Which Alberta process applies to a 40 MW solar farm?

The AESO cluster assessment, which applies to generation and storage projects injecting 5 MW or more into the Alberta interconnected electric system. Projects injecting less than 5 MW use the independent assessment.

How long does the Ontario connection path take?

The IESO gives typical durations by stage: about one year for conditional approval and 18 to 36 months to design and build, followed by market, registration and commissioning stages. Overall, it states more than three years for new facilities.