Hydro-Québec sets the technical rules for connecting a generating station to its transmission system in one public document. The Régie de l'énergie approved it in Decision D-2022-088, effective July 15, 2022. It covers voltage and frequency ride-through, reactive power, protection, telecommunications and real-time data. A dedicated chapter applies to wind, solar and storage plants connected through inverters.
Short answer: Hydro-Québec technical requirements for generators
Hydro-Québec technical requirements for generators are written in one public document: Technical Requirements for the Connection of Generating Stations to the Hydro-Québec Transmission System. The version in force is the one approved under Decision D-2022-088 of the Régie de l’énergie, effective July 15, 2022. It applies to stations with an installed capacity of 1.0 MW or more, unless a clause states otherwise. Québec is one of several provincial regimes, so read it next to the overview of Canadian electrical codes and grid connection.
Where this document applies, and where it does not
The requirements cover a station connected directly to the Hydro-Québec transmission system or through a customer facility. They also apply when an existing station undergoes a substantial change, such as new inverters, new control software or a different maximum power.
A plant connected to the distribution system follows a different document, Requirements for the Interconnection of Distributed Generation to the Hydro-Québec Medium-Voltage Distribution System (E.12-01). A few clauses still reach those plants because they affect the transmission system: frequency response, frequency control, frequency protection, remote tripping and the measurement of active and reactive power.
Hydro-Québec may add project-specific requirements after its studies. The public document is the starting point, not the whole contract.
How the document is organised
| Chapter | Subject |
|---|---|
| 4 | Technical information the applicant provides |
| 5 | General requirements, switchyard and connection characteristics |
| 6 | Voltage and frequency requirements, including ride-through |
| 7 | Equipment: grounding, breakers, arresters, step-up transformers |
| 8 | Protection system requirements |
| 9 | Real-time data and telecommunications for operations |
| 10 and 11 | Verification of compliance and event recorders |
| 12 | Requirements specific to plants connected through inverters |
The table summarizes the contents list. Cite chapter and clause numbers in design documents.
Inverter-based plants: what SERMO means
The document uses the term SERMO for an energy source connected through inverters. It covers type III and type IV wind plants, photovoltaic plants, battery storage and hybrids that mix variable generation with storage. For these plants, chapter 12 replaces the general ride-through, voltage-protection and frequency-protection clauses.
Chapter 12 also requires compliance with IEEE 2800-2022. See IEEE 2800 ride-through and reactive capability for how that standard is built.
Low-voltage ride-through (Table 8 of chapter 12)
Voltages are positive-sequence values on the high-voltage side of the switchyard. The plant must stay in service for at least the durations below.
| Voltage (p.u.) | Minimum time in service |
|---|---|
| 0.90 to 1.0 | Continuously |
| Below 0.90 | 30 s |
| Below 0.85 | 2.0 s |
| Below 0.75 | 1.0 s |
| Below 0.25 | 3.4 × V + 0.15 s |
The inverters may block temporarily if the voltage falls to 0.1 p.u., and they must resume within 5 cycles after the voltage recovers. Hydro-Québec may set a higher blocking threshold. During a fault without blocking, the plant injects reactive current according to the severity of the disturbance.
Overvoltage and frequency
Overvoltage ride-through starts at 1.10 p.u. for 300 s and ends at 0.033 s above 1.40 p.u. Frequency is continuous between 59.4 and 60.6 Hz. For example, below 58.5 Hz the plant stays in service for at least 1.5 minutes, and below 57.5 Hz for 10 s. The plant must also ride through frequency changes of up to 4 Hz/s in either direction.
Reactive power and voltage control
An inverter plant needs an automatic voltage regulation function. It must supply and absorb reactive power at a power factor of 0.95 or better on the high-voltage side, equal to at least ±0.33 p.u. of rated power. The voltage function has a permanent droop adjustable from 0% to 10%.
Protection and telecommunications
Chapter 8 sets the protection philosophy. The main points are:
- Two primary protections, each with its own trip relay, to remove the plant’s contribution to transmission faults.
- Separate secondary windings on current and voltage transformers for the two protections.
- Breaker failure protection, with a dedicated link to trip remote breakers when fast clearing is needed.
- Remote tripping when Hydro-Québec requires it, for example if line reclosing is faster than 2 s or islanding is possible.
- A battery with at least 8 hours of backup for the protection supply, or 2 to 4 hours if station services can be restored from another source.
- No automatic reclosing of the station unless agreed after the interconnection study.
Hydro-Québec supplies, installs and maintains the equipment that carries teleprotection signals. The plant supplies power, secure space, ducts, junction boxes and the tone or teleprotection units.
Worked example (illustrative)
A 60 MW solar plant connects at 230 kV. The fault voltages and clearing times are assumed values.
- A three-phase fault clears in 0.15 s and leaves 0.05 p.u. at the switchyard. The minimum time in service is 3.4 × 0.05 + 0.15 = 0.32 s. The fault lasts 0.15 s, so the margin is 0.17 s.
- A slow-cleared fault holds 0.10 p.u. The minimum time is 3.4 × 0.10 + 0.15 = 0.49 s.
- The slowest fault in the document, cleared in 0.75 s, corresponds to a voltage up to (0.75 − 0.15) ÷ 3.4 = 0.176 p.u. Check: 3.4 × 0.176 + 0.15 = 0.75 s.
- Reactive range: 0.33 × 60 MW = 19.8 Mvar in each direction. Using power factor 0.95, 60 × tan(acos 0.95) = 19.7 Mvar. The two agree, as the document states.
Checklist for the engineer
- Confirm the version of the requirements and any project-specific requirements in the connection agreement.
- Classify the plant: transmission, customer facility or distribution.
- Check inverter ride-through settings against Table 8 and the overvoltage and frequency tables.
- Verify the high-voltage reference point for every voltage and frequency setting.
- Size the reactive capability for ±0.33 p.u., including collector system effects.
- Design two protections with separate CT and VT windings and independent trip circuits.
- Define breaker failure, remote tripping and the teleprotection junction point.
- Disable automatic reclosing unless Hydro-Québec has agreed in writing.
- Plan the verification tests and event recorders.
Legal frame
In Canada, electrical engineering is stamped by a professional engineer (P.Eng.) licensed in the province or territory where the work is done. Tiza does not stamp, sign or certify designs there.
From the requirements to a design your engineer can stamp
Turning chapter 8 and chapter 12 into drawings, settings and study inputs is where most of the work lies. We prepare the engineering design and the power-system studies for a Hydro-Québec connection: single-line and protection diagrams, ride-through and reactive checks, and the data package. The result is ready for your engineer of record to review and stamp. Contact us with the plant data and the connection point.
Figure: single-line diagram of a solar plant at the Hydro-Québec connection point. Each of the two primary protections is fed by its own CT and VT secondary winding and trips the breaker through its own trip relay. The teleprotection channel links the plant relays to the remote substation.
Related guides
- Ride-through requirements by province in Canada
- Protection at the point of interconnection in Canada
- Solar farm interconnection studies in Canada
- Ride-through requirements compared: US, UK and Australia
- NERC PRC-029 ride-through for inverter-based resources
- Teleprotection on renewable plant evacuation lines
References
- Hydro-Québec TransÉnergie, Technical Requirements for the Connection of Generating Stations to the Hydro-Québec Transmission System, Decision D-2022-088, effective July 15, 2022.
- Hydro-Québec, Requirements for the Interconnection of Distributed Generation to the Hydro-Québec Medium-Voltage Distribution System (E.12-01), as cited in the document above.
- IEEE 2800-2022, as required by chapter 12 of the Hydro-Québec document.
Frequently asked questions
Which Hydro-Québec document sets the connection requirements for generators?
For plants on the transmission system, it is the Technical Requirements for the Connection of Generating Stations to the Hydro-Québec Transmission System. The version in force follows Decision D-2022-088, effective July 15, 2022. It applies to stations of 1.0 MW or more unless a clause says otherwise.
Do solar and battery plants follow the same ride-through rules as hydro units?
No. Plants connected through inverters, which the document calls SERMOs, follow a dedicated chapter that replaces the general ride-through clauses for them. That chapter also requires compliance with IEEE 2800-2022.
Can a plant reclose automatically after a fault?
Not unless Hydro-Québec agrees otherwise after the interconnection study. The document prohibits automatic reclosing of a generating station by default, whether the fault is inside the plant or on the transmission system.