Distributed Generation Interconnection in Canada by Province

Distributed generation interconnection in Canada follows provincial rules. See who reviews a project in Ontario, Alberta and BC, with a sizing example.

By Shadai García, CEO and protection engineer at Tiza Group.

ProjectOntarioDistributor or Hydro One:connection impact assessmentAlberta5 MW or more?yesnoAESO clusterassessment and wireservice providerAESO independentassessmentBC35 kV or less?yesnoDistribution routefive stepsTransmission routetariff queueProcess flowA: 6.0 MW at 27.6 kV: OntarioB: 7.5 MW is above 5 MW: AESOC: 34.5 kV is below 35 kV: BCA Ontario: 6,000,000 / (1.732 x 27,600) = 125.5 AB Alberta: 7,500,000 / (1.732 x 25,000) = 173.2 AC BC: 8,000,000 / (1.732 x 34,500) = 133.9 A050100150200 Aillustrative; the utility confirms the route in writingRouteProvinceReviewer5 MW test35 kV testRoute© tizagrp.comProjectOntarioDistributor or Hydro One:connection impact assessmentAlberta5 MW or more?yesnoAESO clusterassessment and wireservice providerAESO independentassessmentBC35 kV or less?yesnoDistribution routefive stepsTransmission routetariff queueProcess flowA: 6.0 MW at 27.6 kV: OntarioB: 7.5 MW is above 5 MW: AESOC: 34.5 kV is below 35 kV: BCA Ontario: 6,000,000 / (1.732 x 27,600) = 125.5 AB Alberta: 7,500,000 / (1.732 x 25,000) = 173.2 AC BC: 8,000,000 / (1.732 x 34,500) = 133.9 A050100150200 Aillustrative; the utility confirms the route in writingRouteProvinceReviewer5 MW test35 kV testRoute© tizagrp.com
Distributed generation routes in Canada: a decision flow by province, with Ontario going to the distributor or Hydro One connection impact assessment, Alberta asking whether the plant injects 5 MW or more, and British Columbia asking whether the voltage is 35 kV or less, with the three example solar plants of 125.5 A, 173.2 A and 133.9 A. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Canada has no national process for connecting distributed generation. Each province decides who reviews a project, which documents apply and how studies are staged. In Ontario the local distributor or Hydro One leads under the Ontario Energy Board's Distribution System Code. In Alberta the AESO runs a cluster assessment for projects of 5 MW or more. In British Columbia BC Hydro runs a staged process for connections up to 35 kV. A design for one province does not transfer unchanged to another.

Short answer: distributed generation interconnection in Canada

Distributed generation interconnection in Canada is a provincial matter. The wiring code, CSA C22.1, is national in origin. The rules for connecting to the grid are not. The reviewer, the documents and the study sequence change at each provincial border, so the first design decision is the province. Three regimes are compared below: Ontario, Alberta and British Columbia. The wider code framework is in electrical codes and grid connection in Canada.

Who reviews the project

The table summarizes each regime as the operators’ public pages described it in November 2026.

ProvinceFirst reviewerMain documentsShape of the process
OntarioLocal distribution company (LDC), or Hydro OneOntario Energy Board (OEB) Distribution System Code and DER Connection ProceduresConnection impact assessment by the distributor; the Independent Electricity System Operator (IESO) assesses larger or transmission-connected projects
AlbertaWire service provider; the Alberta Electric System Operator (AESO) for projects of 5 MW or moreAESO cluster assessment pages and ISO rules, Division 503Staged assessment in clusters with fixed intake windows
British ColumbiaBC HydroDistribution generator interconnection requirements; transmission requirements above 35 kVFive steps from information request to interconnection agreement

Other provinces and territories each publish their own rules. Hydro-Québec, for example, has its own technical requirements. Do not assume that any of the three regimes above applies there.

What is common

Three elements repeat across provinces.

  • Certified equipment. Inverters and similar equipment carry certification to the applicable CSA C22.2 standard.
  • A consolidated interconnection standard. CSA C22.3 No. 9, in its second edition published in 2020, replaced the 2008 edition and gathers requirements that used to sit in three CSA documents. Utilities cite it, alongside their own requirements.
  • A study before the offer. The utility checks fault levels, voltage, protection and, for inverter plants, ride-through behavior. Names and stages differ. See the comparison in which interconnection study each market requires.

How each province works

Ontario. The Distribution System Code (DSC) of the OEB governs distributors. The OEB has amended it several times as part of its review of connections. Final amendments came with version 3 of the DER Connection Procedures and took effect on 1 May 2026. A further set, on data sharing with the IESO, took effect on 1 August 2026. Details are in connecting generation to an Ontario distributor and, for the IESO route, the IESO connection assessment.

Alberta. The AESO runs a cluster assessment for generation and storage that will inject 5 MW or more. It covers distribution-connected projects, assessed at the distribution connection point. Projects below 5 MW go through the AESO’s independent assessment. Distribution-connected generation below 5 MW also follows an AESO guide, with the local wire service provider as the entry point. See AESO connection and technical requirements.

British Columbia. BC Hydro treats interconnections up to 35 kV as distribution and those above 35 kV as transmission. Distribution requests are handled in order of arrival. See BC Hydro interconnection requirements.

Rules move, so confirm the current version

Several of these processes changed during 2025 and 2026. Ontario amended its Code in two steps. The IESO moved to a connection deposit tiered by project size on 1 September 2026. Alberta runs numbered clusters, and the AESO retired its older Division 502 technical rules on 1 April 2024. Before any application, read the version on the operator’s site and note its date in the project file.

Worked example: three illustrative projects

Three hypothetical solar plants show how the same project type lands in different processes. All values are illustrative, and the current rated current uses I = P ÷ (√3 × V) with a power factor of 1.

PlantProvinceAC capacityVoltageRated currentLikely route
AOntario6 × 1.0 = 6.0 MW27.6 kV6,000,000 ÷ (1.732 × 27,600) = 125.5 ADistributor connection impact assessment
BAlberta3 × 2.5 = 7.5 MW25 kV7,500,000 ÷ (1.732 × 25,000) = 173.2 A7.5 MW is above 5 MW, so AESO cluster assessment plus the wire service provider
CBritish Columbia2 × 4.0 = 8.0 MW34.5 kV8,000,000 ÷ (1.732 × 34,500) = 133.9 ADistribution route, because 34.5 kV is below 35 kV

Plant B shows the main trap. A size that a distributor treats as ordinary in one province triggers a system-operator process in another. The utility confirms the final route in writing.

Checklist for the engineer

  • Confirm the province, the utility and, where one exists, the system operator.
  • Download the current technical requirements and record the issue date.
  • Check which CSA C22.1 edition the province has adopted at permit date.
  • Confirm certification of every inverter and transformer to the applicable CSA C22.2 standard.
  • Compare plant AC capacity with each size threshold in the utility’s documents.
  • Ask whether export limiting changes the route. Do not assume it does.
  • Prepare the single-line diagram, protection philosophy and equipment data before applying.
  • Confirm which provincial engineering regulator requires a licensed engineer’s seal.
  • Keep the package ready for your professional engineer to review and stamp.

For comparison, see FERC Order 2023 cluster studies in the United States, the G98 and G99 routes in the United Kingdom and embedded generation by distributor in Australia. For inverter rules across markets, see IEEE 1547, G99, AS/NZS 4777 and the Canadian route compared. Licensing is covered in who must stamp electrical design by country.

From the rules to a design your P.Eng. can stamp

A Canadian application moves faster when the package matches the province where it is filed. We prepare the engineering design for a distributed generation connection: single-line diagram, protection approach and equipment data. The package is ready for your professional engineer (P.Eng.), licensed in the province of the project, to review and stamp. Tiza does not stamp, sign or certify designs in Canada. Contact us with the project size, voltage and province.

Frequently asked questions

Is there one distributed generation interconnection process for all of Canada?

No. Electricity is regulated provincially. Each province, and often each utility, publishes its own requirements and application steps. Equipment certification to CSA standards is the main common element.

Which standard do Canadian utilities use for distributed generation?

CSA C22.3 No. 9 covers interconnection of distributed energy resources, and its second edition dates from 2020. Utilities decide how they apply it, and many add their own technical requirements, so always read the utility's current document.

Does a project over 5 MW in Alberta go to the utility only?

Not necessarily. The AESO describes its cluster assessment as applying to generation and storage injecting 5 MW or more, including distribution-connected projects. The wire service provider is still part of the process.