Inverter Certification in Canada: CSA C22.2 No. 107.1

How inverters and power supplies are approved in Canada: CSA C22.2 No. 107.1, SCC-accredited certification bodies, field evaluation and the site checks.

By Shadai García, CEO and protection engineer at Tiza Group.

ManufacturerSCC-accreditedcertification bodyCertificateand markNo CanadiancertificationSpecial inspectionbody (SCC)Field labelthis unit onlyInspection authorityRule 2-024Approval flowfive inverters, 20 kW each, 600 Veach: 20,000 / (1.732 x 600) = 19.2 Acircuit: 19.2 / 0.8 = 24.1 Afive: 5 x 19.2 = 96.2 A at the buscheck each certificate scope and editiona US listing only leaves the file incomplete600 V bus=~20 kW19.2 A=~20 kW19.2 A=~20 kW19.2 A=~20 kW19.2 A=~20 kW19.2 A96.2 Ause nameplate values, not the power ratingApprovalCertificateMarkScopeEditionAuthority© tizagrp.comManufacturerSCC-accreditedcertification bodyCertificateand markNo CanadiancertificationSpecial inspectionbody (SCC)Field labelthis unit onlyInspection authorityRule 2-024Approval flowfive inverters, 20 kW each, 600 Veach: 20,000 / (1.732 x 600) = 19.2 Acircuit: 19.2 / 0.8 = 24.1 Afive: 5 x 19.2 = 96.2 A at the buscheck each certificate scope and editiona US listing only leaves the file incomplete600 V bus=~20 kW19.2 A=~20 kW19.2 A=~20 kW19.2 A=~20 kW19.2 A=~20 kW19.2 A96.2 Ause nameplate values, not the power ratingApprovalCertificateMarkScopeEditionAuthority© tizagrp.com
Approval path for an inverter under CEC Section 26 and CSA C22.2 No. 107.1: manufacturer, SCC-accredited certification body, certificate and mark to the inspection authority (Rule 2-024), with the field evaluation branch through a special inspection body and a field label, plus five 20 kW inverters at 600 V drawing 19.2 A each, a 24.1 A circuit rating each and 96.2 A at the common bus. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

In Canada, electrical equipment must be approved before it is used. Rule 2-024 of the Canadian Electrical Code requires certification by a body accredited by the Standards Council of Canada. Inverters, converters and power supplies are assessed to CSA C22.2 No. 107.1, Power conversion equipment, often together with UL 1741. Equipment without certification may be accepted only by a field evaluation.

Short answer: how an inverter is approved in Canada

Canadian installations need approved equipment. Rule 2-024 of the Canadian Electrical Code (CEC, CSA C22.1) requires electrical equipment to be approved. Approval means certification by an organization accredited by the Standards Council of Canada (SCC) against the applicable standard. For inverters, converters and power supplies the standard is CSA C22.2 No. 107.1, Power conversion equipment, published by CSA Group (formerly the Canadian Standards Association).

The answer to the usual question follows from that. A US listing alone does not make an inverter approved in Canada, and Canadian approval is shown on the nameplate by the mark of an accredited certification body. Many products carry both: a single certificate can cover UL 1741 and C22.2 No. 107.1.

For the three layers around this rule, see the overview of electrical codes and grid connection in Canada. Adoption of the Code differs by province, and the current national edition is CSA C22.1:24.

What Rule 2-024 requires

The rule says that equipment must be approved and of a kind, type and rating suitable for its use, including its environment. The authority having jurisdiction, usually the provincial inspection department, decides what it accepts. Equipment with a certification mark from an SCC-accredited body is the ordinary route. Rule 2-100 sets the markings the equipment must carry. The evidence of approval is the certification mark or the label of a special inspection body.

Two practical points follow from the rule.

  • Approval is not permanent. The authority can still reject approved equipment that is substandard or unsuitable for its conditions of use, under Rule 2-026.
  • Approval covers the use. An outdoor inverter needs an enclosure rating suitable for the site, and a hazardous-location product needs approval for that location.

Who certifies: SCC-accredited bodies

The Standards Council of Canada accredits certification bodies, and the Code accepts approvals only from those bodies. CSA Group writes the CSA standards, and certification to them is done by certification bodies accredited by the SCC. The SCC publishes a list of the recognized approval marks and a directory of accredited organizations. Always check the directory for the body and the scope on the certificate. A body can be accredited for product certification and not for field evaluation, and the reverse.

Certification bodies and special inspection bodies are different things. A certification body certifies a product type against a standard. A special inspection body evaluates one installed unit or a custom unit in the field.

What CSA C22.2 No. 107.1 covers

The standard sets the safety requirements for power conversion equipment: inverters, converters, power supplies and related products. The fourth edition, published in 2016, is the base edition, and CSA lists it as reaffirmed in 2021. Its scope covers equipment rated up to 1500 V, including utility-interactive inverters and photovoltaic power conversion equipment.

A CSA update to the fourth edition (Ed.4+U1) is listed in certification-body notices with an effective date of January 1, 2027. If your equipment is certified to the base edition, ask the manufacturer about the update before you order units that will be delivered after that date.

Inverters and the US listing. UL 1741 is written for inverters in the United States. The Canadian standard is broader, with clauses for several kinds of power conversion equipment, and the two are often assessed together for products sold in both markets. What matters on site is the nameplate: look for the certification mark that the Canadian authority recognizes and for the standard named in the certificate.

A listing is evidence of product safety, not of the right grid behaviour for a given utility. The grid requirements of each province are separate; the provincial utility sets them, as the overview linked above explains.

Where Section 26 fits

Section 26 of the CEC covers the installation of electrical equipment, including transformers and their protection. The product certification rule sits in Section 2. In a design, the certified inverter then gets its conductors from Section 4 and its protection from Section 14. Renewable systems add Section 64.

Worked example: output circuit of an inverter fleet

The numbers are illustrative and are not taken from a product.

Assumptions

  • Five three-phase inverters of 20 kW AC each, connected at 600 V.
  • Each inverter is treated as a continuous load on its AC circuit.
  • Each certificate names C22.2 No. 107.1 and covers 600 V AC output.

Step 1: current per inverter. I = 20 000 ÷ (√3 × 600) = 19.2 A.

Step 2: minimum circuit rating per inverter. The continuous load is limited to 80% of the circuit rating, so 19.2 ÷ 0.8 = 24.1 A. The next standard device size above that is 25 A or more.

Step 3: combined current. Five inverters give 5 × 19.2 = 96.2 A at the common bus. The bus protection and conductors have to be sized for that continuous current.

Step 4: certification check. Before the order, the file for each unit should show the following.

ItemWhere to confirm
Certification body is accredited by the SCCThe SCC directory
Standard named on the certificateThe certificate and the nameplate
Approved AC voltage and phase configurationThe certificate scope
Environmental rating for the siteThe nameplate and certificate
Edition of the standardThe certificate, against the edition the authority expects

Step 5: result. The fleet draws 96.2 A of AC current in total. The design package needs the nameplate values rather than the power rating, because the certified output current is what the Code uses.

If one unit shows only a US listing, the file is incomplete. The options are a certified replacement or a field evaluation that the authority agrees to accept before the order is confirmed.

Field evaluation as a last resort

Some equipment has no Canadian certification, for example custom-built power supplies or units that are already installed. The authority may accept a field evaluation by an SCC-accredited special inspection body, under the CSA model code for field evaluation. Authorities publish lists of the inspection bodies they accept. Field evaluation is not intended to replace certification, and a field label covers the unit that was evaluated, not the product line.

Common mistakes

  • Assuming a US listing is enough for the Canadian inspector.
  • Reading only the product brochure and never the certificate scope.
  • Ordering a different voltage configuration from the one that was certified.
  • Treating field evaluation as a routine alternative to certification.
  • Forgetting that a certified inverter still has to meet the utility’s interconnection requirements.

Checklist for the engineer

  • Confirm the CSA C22.1 edition and provincial amendments at permit date.
  • Collect the certificate and nameplate for every inverter, converter and power supply.
  • Confirm the certification body in the SCC directory and the standard named.
  • Match the certified voltage, phase and environment to the project.
  • Check the edition of C22.2 No. 107.1 against what the authority expects.
  • Plan a field evaluation with the authority early if any unit lacks certification.
  • Size circuits from certified output current, not from rated power.
  • Keep the package ready for the engineer of record to review and stamp.

From certified equipment to a design your engineer can stamp

Electrical engineering in Canada is sealed by a professional engineer (P.Eng.) licensed in the province or territory of the project. Tiza does not stamp, sign or certify designs or equipment. We prepare the engineering design: circuit and protection schedules, inverter data sheets organized for the authority and the utility, and the studies behind them, ready for your P.Eng. to review and stamp. Contact us to scope the package.

Frequently asked questions

Does a UL 1741 listing satisfy Canadian approval for an inverter?

Not by itself. Canada requires approval from a certification body accredited by the Standards Council of Canada, to the applicable CSA standard. For inverters that standard is CSA C22.2 No. 107.1. Many products carry a certificate that covers both UL 1741 and C22.2 No. 107.1, with the Canadian and US marks side by side.

What does CSA C22.2 No. 107.1 cover?

Its title is Power conversion equipment. The fourth edition of 2016 covers inverters, converters and power supplies up to 1500 V for commercial, industrial and residential use in non-hazardous locations. It includes requirements for utility-interactive inverters and for photovoltaic power conversion equipment.

What if the equipment has no Canadian certification?

The inspection authority may accept it after a field evaluation by a special inspection body accredited by the Standards Council of Canada, under the CSA field evaluation model code. Field evaluation is not a substitute for certification. It applies to cases such as custom-built equipment, and the authority decides whether to accept it.