A utility design and construction standard for networks and substations (version 3, 2023) gives concrete ratings for pole-mounted reclosers on 13.8 and 33 kV networks: 800 A, 16 kA breaking and 3 s withstand, vacuum interruption, solid internal insulation, sensors on all six poles, a heated IP54 control cabinet and a defined auxiliary supply. It is a practical design reference.
What the standard fixes
Section 5.10 of the utility’s standard asks for reclosers to follow IEC 62271-111 (IEEE C37.60): three-pole units with a magnetic actuator on each phase, mechanical latching for three-pole operation and a manual open/close handle.
| Rating | 13.8 kV network | 33 kV network |
|---|---|---|
| Rated voltage | 15.5 kV | 38 kV |
| Lightning impulse (BIL) | 110 kV | 170 kV |
| Power-frequency withstand | 50 kV | 70 kV |
| Rated current | 800 A | 800 A |
| Breaking capacity | 16 kA | 16 kA |
| Short-time withstand | 16 kA, 3 s | 16 kA, 3 s |
| Interrupting medium | Vacuum | Vacuum |
| Internal / external insulation | Solid dielectric / polymeric | Solid dielectric / polymeric |
| Creepage distance | 273 mm | 669 mm |
Design points beyond the table
- Sensing: one current and one voltage sensor on each of the six poles.
- Control cabinet: automatic heating against humidity and a minimum IP54 rating.
- Evidence: the supplier delivers the routine factory test reports required by the recloser’s manufacturing standard.
- Auxiliary supply: nearest low-voltage network after checking capacity, regulation and losses; otherwise a 0.5 kVA single-phase transformer, with surge arresters on its bushings and on the recloser.
- Design: Voltage, load and fault level at the point. 13.8 or 33 kV
- Design: Compare with the rating table. 800 A and 16 kA
- Design: Do load and fault level fit? Yes: continue; No: back to step 1.
- Design: Define auxiliary supply. Low-voltage network or 0.5 kVA transformer
- Utility: Design reviewed against the standard
Worked example with assumed numbers
Assumptions, not from a real project: a three-phase 13.8 kV branch, 5 MVA of expected load, 30 % growth, 12 kA three-phase fault level.
| Check | Calculation | Result |
|---|---|---|
| Load current | 5,000 kVA / (1.732 x 13.8 kV) = 209 A; x 1.3 = 272 A | Below 800 A |
| Breaking capacity | 12 kA against 16 kA | Passes |
| Fault level 18 kA | 18 kA against 16 kA | Fails: review the point |
The fault level comes from the system study, not from the recloser nameplate. The control functions are in recloser control functions and IEC 60870-5-104 link.
Closing
We design the protection coordination for the recloser your project requires and configure its control remotely. See remote configuration of protective relays and controls.
References
- IEC 62271-111 / IEEE C37.60, automatic circuit reclosers up to 38 kV.
Frequently asked questions
What breaking capacity does the standard set for a feeder recloser?
16 kA, with 16 kA short-time withstand for 3 s, for both the 13.8 kV class (15.5 kV rated) and the 33 kV class (38 kV rated). Rated current is 800 A and the interrupting medium is vacuum.
Why a sensor on each of the six poles?
One current and one voltage sensor on each of the six bushings lets the control measure on both sides of the interrupter. That supports directional functions and measuring on feeders where power can flow either way.
How is the control powered?
From the nearest low-voltage network once its capacity, voltage regulation and losses are checked. If there is none, from a single-phase 0.5 kVA auxiliary transformer, with surge arresters on its medium- and low-voltage bushings.