Before energization, each protection function of the recloser control is tested on its own, then the settings are compared with the coordination study and the automatic reconnection is proven. The utility's witness test goes smoothly when the plant arrives with a complete record and an installation that matches the approved design.
Short answer
The tests of a recloser before energization follow one order: each function alone, then the settings against the study, then the automatic reconnection, and last the integrated test with the utility present. The installation has to match what was approved, and every result goes into a record the utility can read.
Test procedures for the equipment itself are in recloser commissioning tests before energizing.
- Design: Approved design and coordination study. Same protections as installed
- Design: Individual function tests. Pickup, delay, trip logic
- Design: Settings check against the study. File and printout compared
- Design: Reconnection test. Minimum time and three-phase voltage
- Utility: Witness test. Protection and disconnection checked
- Utility: Any nonconformity? No: continue; Yes: back to step 2.
- Utility: Connection
What the record contains
| Item | Content |
|---|---|
| Settings | Values loaded in the control, with the file and date |
| Function tests | Injected value, measured pickup and delay, pass or fail |
| Device operation | Opening and closing from the control and locally |
| Reconnection | Timer value and the three-phase voltage condition |
| Auxiliary supply | Operation of the control and the device with the main supply removed |
| Changes | Differences from the approved design, shown on as-built drawings |
Example schedule (assumptions)
For a 0.6 MW plant with a recloser at the point of connection:
| Step | Assumed time |
|---|---|
| Individual function tests | 1 day |
| Settings check and reconnection test | 1 day |
| Corrections | 2 days |
| Witness test | 1 day |
Design checklist
- Settings file equal to the study.
- Every function tested with injection and recorded.
- Reconnection delay and three-phase check proven.
- Auxiliary supply tested.
- As-built drawings match the installation.
We provide the design engineering and the remote configuration of the recloser control, from the coordination study to the settings file and the test plan: contact us with your network data and we will propose a scope. See remote relay configuration.
Related guides
- Recloser: what it is, how it works and tests
- Recloser settings: reclosing, curves and sequence
- Anti-islanding protection
References
- IEC 62271-111:2019 / IEEE C37.60-2018, automatic circuit reclosers for alternating current systems up to 38 kV.
Frequently asked questions
What is tested first on a recloser control?
Each protection function individually: pickup, delay and trip logic, and the operation of the interrupting device. Doing this before the integrated tests avoids failures during the witness test.
What must the settings be compared with?
With the values in the approved design and, where it applies, the protection coordination study, so selectivity with the grid and with other generating units at the same point holds.
How is automatic reconnection proven?
By checking that the system re-energizes only after the minimum time has elapsed and only when voltage is present on all three phases of the circuit or bus, avoiding premature reclosing on an abnormal grid.