Clause S5.2.5.15 of the National Electricity Rules requires the asynchronous part of a generating system to operate stably and stay connected at a short circuit ratio of 3.0, assessed with AEMO's system strength impact assessment guidelines. The performance standard records the agreed ratio, the active power used to calculate it and any arrangements agreed to close a shortfall.
Clause S5.2.5.15 of the National Electricity Rules (NER) is the short circuit ratio requirement for inverter-based plant. It asks whether the plant can keep operating when the grid at its connection point is weak. The short circuit ratio (SCR) is the grid fault level divided by the plant’s power, so a low ratio means a weak grid. The clause sits in Schedule 5.2 and is one of the generator performance standards (GPS) described in the Australia electrical codes and grid connection guide.
Short answer
S5.2.5.15 requires an asynchronous production system to have plant capability sufficient to operate stably and remain connected at a short circuit ratio of 3.0. The ratio is assessed with the method in AEMO’s System Strength Impact Assessment Guidelines. The performance standard records the agreed ratio, the active power used to calculate it and any arrangements agreed to close a shortfall.
What the clause says, in plain words
The wording comes from the final rule of the Improving the NEM access standards, Package 1 (Rule 2025 No. 6), in force from 21 August 2025.
- Scope. The clause applies only to asynchronous production units. In a plant that mixes synchronous and asynchronous units, it covers the asynchronous part.
- Minimum access standard. The plant must operate stably and stay connected at an SCR of 3.0, assessed as the system strength impact assessment guidelines prescribe.
- What is recorded. The performance standard states the agreed SCR, which is the lower of 3.0 and the value at which the plant has proven capability. It also states the active power capability or maximum demand, whichever is greater, used to calculate it. Any arrangements agreed for a shortfall are written in too.
- Settings. The capability may be shown with any suitable control and protection settings. They can differ from the settings used for other standards in S5.2.5.
The Rules define SCR as the synchronous three phase fault level at the connection point, in MVA, divided by the greater of the plant’s active power capability and its maximum demand, in MW. The fault level leaves out any fault current from the plant side of the connection point. AEMO’s guidelines call the ratio the plant can withstand the “withstand SCR”. The wider framework is in the guide on AEMO system strength requirements and SCR studies, and the calculation of the fault level in the guide on short circuit models and fault level requirements.
When the plant cannot reach 3.0
The clause gives a path when the plant cannot meet the minimum standard by itself. If AEMO, the network service provider (NSP) and the system strength service provider agree, the applicant can show two things:
- Legally binding commitments to invest in its plant, or to obtain services, to remedy the shortfall at its own cost, either at connection or in agreed circumstances such as a change in the fault level.
- Operating arrangements agreed with the NSP that apply while that remedy is not yet in place.
The applicant can invest in its own plant so that it works at 3.0. Alternatively, it can buy services from the NSP, the system strength service provider or another registered participant. In that case the 3.0 test uses a fault level that excludes any contribution from the facilities providing the service.
What the assessor asks for
AEMO’s guidelines say the applicant proves capability with dynamic simulation, not with a static fault calculation. The tests run on site-specific models of the plant. In AEMO’s guidance, an initialisation run that is not stable at the declared ratio means the plant cannot demonstrate compliance. The model settings used for this clause must be listed, with any differences from those used for other standards. The guide on PSS/E and PSCAD models for inverter-based plant covers the model side. The same ratio also feeds the GPS compliance demonstration plan.
Worked example (illustrative)
These values are illustrative. A solar farm has an active power capability of 80 MW and its maximum demand is lower. The NSP gives a minimum synchronous fault level at the connection point of 360 MVA with the network intact and 216 MVA with the most critical line out.
Step 1: the ratio in each case
- Intact network: 360 / 80 = 4.5.
- Critical contingency: 216 / 80 = 2.7.
Step 2: compare with 3.0
- Fault level needed for 3.0: 3.0 × 80 = 240 MVA.
- Shortfall in the contingency: 240 - 216 = 24 MVA.
Result. The network is above 3.0 in normal conditions and below it with the line out. Suppose the inverter model is proven stable down to an SCR of 2.5. The agreed value recorded is then 2.5, the lower of 3.0 and the proven value. The fault level needed is then 2.5 × 80 = 200 MVA, which is below 216 MVA, so the contingency case is covered. If the plant is proven stable at 3.0 and no lower, it meets the minimum access standard. The 24 MVA gap in the contingency is then a system strength matter, assessed under the system strength impact assessment guidelines. The arrangements in paragraph (e) of the clause apply only when the plant cannot reach 3.0 at all.
Figure: the connection point with the network equivalent on one side and the inverter plant on the other, with the fault level and the plant power that set the ratio.
Checklist for the engineer
- Confirm the plant is asynchronous in whole or in part, and which units the clause covers.
- Obtain from the NSP the minimum fault level in normal and contingency conditions, in writing.
- Calculate the ratio with the active power capability or maximum demand, whichever is greater.
- Test the model in dynamic simulation at 3.0 and at the lowest ratio the manufacturer declares.
- List the control and protection settings used, and any difference from other standards.
- Decide the route if there is a shortfall: plant investment, services or operating arrangements.
- Write the agreed ratio, the power used and the arrangements into the proposed performance standard.
Next step
Tiza runs the fault level cases, the weak-grid simulations and the written evidence that support a proposal under S5.2.5.15. Tiza does not stamp, sign or certify: it delivers studies and engineering ready for your RPEQ in Queensland, or your registered or chartered engineer in other states, to review and certify. Contact us with the connection point data and the inverter model.
Related guides
See the generic explanation of short-circuit ratio and weak grids, the NER Chapter 5 guide, clause S5.2.5.16 on voltage phase angle shift and network feeder impedance and short-circuit power.
Frequently asked questions
What short circuit ratio does S5.2.5.15 require?
The minimum access standard is stable operation and staying connected at a short circuit ratio of 3.0. The performance standard records the lower of 3.0 and the value at which the plant has demonstrated that capability.
Which plant does the clause apply to?
Only to asynchronous production units, such as inverter-based solar, wind and battery plant. In a mixed plant it applies to the production system only to the extent of its asynchronous units.
What if the plant cannot operate at a ratio of 3.0?
With the agreement of AEMO, the network service provider and the system strength service provider, the applicant can commit to extra plant investment or to services that remedy the shortfall, together with operating arrangements until that remedy is in place.