ISO 8528-1:2018 defines six categories to declare the power of a generating set. COP is for constant load with no hour limit. PRP is for variable load with no hour limit and an average of up to 70 % over 24 h. LTP is for up to 500 h a year, and ESP for utility outages, up to 200 h a year. The standard adds DCP for data centres and MAX for small sets.
Short answer
The same generating set can show several powers on its data sheet, one per category of use. ISO 8528-1:2018 defines six categories in clause 14.3: continuous power (COP), prime power (PRP), limited-time running power (LTP), emergency standby power (ESP), data centre power (DCP) and maximum power of low-power sets (MAX). The category sets how many hours a year the set runs, whether the load is constant or variable and what average load it accepts. Choosing the wrong category shortens the life of the set.
The six categories in plain words
| Category | Hours per year | Load | Average and overload |
|---|---|---|---|
| COP, continuous | No limit | Constant | The set delivers 100 % all the time |
| PRP, prime | No limit | Variable | 24 h average up to 70 % of PRP; 10 % overload for 1 h within every 12 h, unless stated otherwise |
| LTP, limited time | Up to 500 h | Constant | 100 % of LTP is limited to 500 h a year |
| ESP, emergency standby | Up to 200 h, during utility outages or tests | Variable | 24 h average up to 70 % of ESP |
| DCP, data centres | No limit | Variable or constant | The manufacturer defines the power it guarantees for that use |
| MAX, small sets | — | Starting of appliances | Power the set holds for at least 5 min |
Values from clauses 14.3.2 to 14.3.7 of ISO 8528-1:2018; wording and format by Tiza Group.
Two general rules go with the table (clause 14.2). The power of a set is expressed in kVA at rated frequency and a power factor of 0.8 lagging, unless stated otherwise. And the categories declared by the manufacturer are the ones used: any other category applies only if manufacturer and customer agree on it in writing.
The power of the set is what remains available at its terminals for the load. It excludes the power drawn by the essential auxiliaries the engine needs to run (clause 14.1).
What each one is
COP. The maximum power the set delivers continuously at constant load, with no limit of hours per year, provided the manufacturer’s maintenance is followed. It is the category of a combined heat and power plant supplying base load.
PRP. The maximum power at variable load, also with no hour limit. It suits a site with no grid, or with a grid so unreliable that the set is the main source. The standard limits the 24 h average to 70 % of PRP, unless the engine manufacturer accepts another value. If your average load will be higher, the standard recommends moving to COP.
LTP. The power the set delivers at constant load for up to 500 h a year. It fits, for example, peak shaving: the set runs in parallel with the grid and takes a fixed load during the hours of highest consumption.
ESP. The power the set delivers during a utility outage, or in tests, for up to 200 h a year. It is the typical category of the emergency diesel generator of a substation, a hospital or a building. The 24 h average is also limited to 70 % of ESP.
DCP. The power the set delivers at variable or continuous load with no hour limit, for data centres. The standard makes the manufacturer responsible for defining that value according to the site and the reliability of the grid, with any hardware, software or maintenance adaptation needed. A note in the standard states that prolonged operation at load in parallel with the grid is not permitted.
MAX. It applies to low-power sets that feed appliances whose start is more demanding than their normal consumption. It is the power the set holds for at least 5 min with voltage within ±10 % and frequency within ±8 % of their rated values. COP must be at least 75 % of MAX.
How the 24 h average is calculated
For PRP and ESP the standard asks for the actual average power of the day, Ppa, with two rules:
- Powers below 30 % of the category power are counted as 30 %.
- Time with the set stopped does not enter the calculation.
Ppa = (P1·t1 + P2·t2 + … + Pn·tn) / (t1 + t2 + … + tn)
Our own example. A 500 kVA set in PRP, that is 400 kW at 0.8 power factor, runs like this in one day: 6 h at 380 kW, 10 h at 250 kW, 4 h at 80 kW and 4 h stopped.
- The 4 h at 80 kW are below 30 % (120 kW), so they count as 120 kW.
- The 4 h stopped are not counted: the denominator is 20 h.
- Ppa = (6 × 380 + 10 × 250 + 4 × 120) / 20 = 5260 / 20 = 263 kW.
The limit is 70 % of 400 kW, that is 280 kW. At 263 kW the day complies. If the 10 h at 250 kW became 300 kW, the average would rise to 288 kW and the duty would call for a COP set or a larger one.
The 6 h at 380 kW, 95 % of PRP, are acceptable: the standard limits the average, not each hour. The 10 % overload above PRP is only allowed for 1 h within every 12 h of operation.
Power depends on the site
Rated power is declared at the reference conditions of clause 11: total barometric pressure of 100 kPa, air at 25 °C and 30 % relative humidity. At most real sites the air is hotter or the pressure is lower, and the engine delivers less power.
That is why clause 13 asks the customer for these site data:
- The highest and lowest barometric pressure or, if not available, the altitude above sea level.
- The mean, minimum and maximum air temperatures in the hottest and coldest months.
- The highest and lowest air temperatures around the engine, which in a closed room can exceed those outside.
- The relative humidity at the maximum temperature.
- The minimum and maximum cooling water temperatures, if the set uses it.
With those data, the manufacturer adjusts the power and declares the site power. At high altitude this weighs a lot: a plant above 2500 m works at a pressure far below 100 kPa. The altitude and temperature adjustment comes from the engine manufacturer; do not improvise it with a rule of thumb.
Typical mistakes
- Buying an ESP set that will be the main source. ESP allows 200 h a year. Used all year, the set ages early, as clause 14.3.1 warns.
- Comparing data sheets with different categories. A “500 kVA standby” set and a “500 kVA prime” set are not equal: the second delivers more useful energy per year. See how manufacturers declare it in Cummins and Caterpillar generators.
- Sizing with the nameplate power without site adjustment. The nameplate applies at 25 °C and 100 kPa.
- Forgetting the power factor. Nameplate kVA assume 0.8 lagging; with loads at another power factor, check the alternator active and reactive power.
- Counting test hours separately. In ESP, tests also count toward the 200 h a year.
How the category combines with performance under load steps is explained in performance classes G1 to G4. What the engine must declare to sustain that power is in the generating set engine.
We support you with your generating set
At Tiza Group we test generating sets and their transfer schemes in medium, high and extra-high voltage substations and in industry: start on a real outage, load steps, load bank and alternator protection. Learn about our testing and commissioning service or write to us for a quote.
Related guides
- Emergency diesel generator: parts, ISO 8528 and tests
- Generating set performance classes G1 to G4
- Generating set engine to ISO 8528-2
- Generating set alternator to ISO 8528-3
- Cummins and Caterpillar generators
- Automatic transfer of sources
- Generator in parallel with the grid
References
- ISO 8528-1:2018, Reciprocating internal combustion engine driven alternating current generating sets — Part 1: Application, ratings and performance, third edition, clauses 11 and 13 and subclauses 7.1, 14.1, 14.2 and 14.3.1 to 14.3.7.
Frequently asked questions
Can I use a set rated for emergency standby power (ESP) as the main source of a plant with no grid?
No. ESP only applies during utility outages or tests, for up to 200 h of operation a year (ISO 8528-1:2018, clause 14.3.5). A plant that runs all year on the set as its only source needs a set rated in PRP if the load varies, or in COP if the load is constant.
How is the 24 h average power of a set in PRP calculated?
Multiply each power by the time it lasted, add the products and divide by the sum of the times. Powers below 30 % of the PRP are counted as 30 %, and time with the set stopped is not counted. The result must not exceed 70 % of the PRP, unless the engine manufacturer accepts another value (clause 14.3.3).
Does the nameplate power apply at any site?
No. Power is declared at the standard reference conditions: 100 kPa pressure, 25 °C air and 30 % relative humidity (clause 11). If the site is higher, hotter or more humid, the manufacturer adjusts the power and declares the site power, using the data the customer provides (clause 13).