ISO 8528-1:2018 defines four performance classes for a generating set according to what the load demands from voltage, frequency and waveform. G1 serves simple loads, G2 behaves almost like the public grid, G3 serves demanding loads such as telecommunications and thyristor loads, and G4 covers exceptional demands such as computer equipment.
Short answer
The performance class states how stable the energy delivered by a generating set must be when the load changes. ISO 8528-1:2018 defines four classes in clause 8. Class G1 serves loads that only need basic voltage and frequency values. Class G2 behaves almost like the public grid, with acceptable temporary deviations. Class G3 serves loads that make severe demands on frequency, voltage and waveform. Class G4 is for exceptionally severe demands. The class is chosen for the most sensitive load the set will feed.
The four classes
| Class | What the load demands | Example given by the standard |
|---|---|---|
| G1 | Only basic voltage and frequency values | General purpose: lighting and simple electrical loads |
| G2 | Voltage very close to the public grid; temporary deviations accepted when the load changes | Lighting, pumps, fans and hoists |
| G3 | Severe demands on stability and level of frequency, voltage and waveform | Telecommunications and thyristor-controlled loads |
| G4 | Exceptionally severe demands | Data-processing equipment and computer systems |
Classes and examples from clause 8 of ISO 8528-1:2018; wording and format by Tiza Group.
For G3 the standard adds a warning: rectifiers and thyristor loads may need special consideration for their effect on the alternator voltage waveform. A battery charger, a UPS or a variable speed drive are loads of that kind.
Why a higher class costs more
When a load is switched on suddenly, voltage and frequency deviate for a moment. ISO 8528-1:2018, clause 15.2, explains that the deviation depends on the size of the change in active power (kW) and reactive power (kvar) relative to the capacity of the set, and on the dynamic behaviour of engine and alternator.
A higher class asks for smaller deviations and faster recovery. ISO 8528-3:2005 warns that asking for a voltage dip or a recovery time stricter than needed can lead to a much larger alternator, and that the system fault level rises with it (Table 3, note d).
So the class is not ordered “just in case”. Ask for the one the most sensitive load needs and declare the actual load step.
Where the numbers are
ISO 8528-1 defines the classes in words. The numerical limits are spread over other parts of the series:
- The engine: ISO 8528-2:2018, clause 13, sets the speed droop by class. For example, up to 5 % in G2 and up to 3 % in G3; in G4 it is agreed between manufacturer and customer. We explain it in the generating set engine.
- The alternator: ISO 8528-3, clause 13, sets by class the steady-state voltage deviation, the transient dip and rise and the recovery time. We explain it in the generating set alternator.
- The complete set: ISO 8528-5 sets the limits of the whole set under load steps. That part is not summarised in this guide.
ISO 8528-3:2005 states that its values apply to the alternator at constant speed, and that engine speed regulation can change them. Real performance belongs to the engine, alternator and regulator together.
The class is not the only thing to specify
ISO 8528-1:2018 asks to define, together with the class, other features of the duty:
The mode of operation (clause 7.1). Continuous or limited time, at constant or varying load. It relates to the power category; see COP, PRP, LTP and ESP ratings.
Single or parallel (clause 7.3). In parallel with other sets or with the grid, the customer must give the grid characteristics: voltage and frequency range and variation, and impedance. In parallel with the public grid, the utility’s permission and protective equipment are required. See generator in parallel with the grid.
Start-up and control (clause 7.4). Manual, semi-automatic or automatic.
Start-up time (clause 7.5). It is the time between the moment power is demanded and the moment it is available. The standard distinguishes three types of set with a specified time:
| Type | How it works | Interruption seen by the load |
|---|---|---|
| Long break | The set starts from standstill when power is demanded | Fairly long |
| Short break | A rotating machine with stored mechanical energy holds the load while the transfer takes place | Short, usually milliseconds |
| No break | Continuously running machines and stored energy hold the load | None; a temporary frequency deviation may occur |
Wording and format by Tiza Group from clause 7.5.3 of ISO 8528-1:2018.
In the no-break set, the frequency deviation allowed during transfer must be agreed between customer and manufacturer. The typical emergency set of a substation is long break: it starts on command from the automatic transfer of sources.
Our own example
An industrial plant wants a set for three loads: lighting and pumps, a control room with a 60 kVA UPS, and a 75 kW compressor with direct-on-line starting.
- The most sensitive load is the UPS, a rectifier load. It points to G3, with the clause 8 warning about waveform.
- The compressor is the largest load step. It is declared with its power, its starting current and its starting method, because the actual voltage dip depends on them.
- Lighting and pumps alone would only need G2.
The specification reads: class G3, maximum step equal to the compressor start, 60 kVA non-linear load declared, long break with automatic start. With those data the manufacturer chooses engine, alternator and regulator. What is not declared is not designed.
Typical mistakes
- Asking for G4 for everything. It makes the alternator more expensive and raises fault current with no benefit for simple loads.
- Asking for a class without stating the step. The class defines limits for an agreed step; without the real step, the manufacturer assumes another.
- Forgetting non-linear loads. Rectifiers, UPS units and drives distort the alternator voltage.
- Confusing class with power category. G1 to G4 deal with power quality; COP, PRP, LTP and ESP deal with how much energy and for how many hours.
Load steps are checked on site with a load bank or the real load; see emergency diesel generator.
We support you with your generating set
At Tiza Group we test generating sets and their transfer schemes in medium, high and extra-high voltage substations and in industry, including load steps and the voltage and frequency response. Learn about our testing and commissioning service or write to us for a quote.
Related guides
- Generating set ratings: COP, PRP, LTP and ESP
- Generating set engine to ISO 8528-2
- Generating set alternator to ISO 8528-3
- Emergency diesel generator: parts, ISO 8528 and tests
- Generator excitation and AVR
- Starting large motors and voltage dip
References
- ISO 8528-1:2018, Reciprocating internal combustion engine driven alternating current generating sets — Part 1: Application, ratings and performance, third edition, clauses 7.1, 7.3, 7.4, 7.5 and 15.2 and clause 8.
- ISO 8528-2:2018, Part 2: Engines, third edition, clause 13 and Table 2.
- ISO 8528-3:2005, Part 3: Alternating current generators for generating sets, second edition, clause 13 and Table 3. The current edition is the 2020 one.
Frequently asked questions
What class does a set feeding a UPS or a rectifier need?
ISO 8528-1:2018 gives thyristor-controlled loads and telecommunications as examples of class G3, and warns that rectifiers and thyristor loads may need special consideration for their effect on the alternator waveform (clause 8). Tell the manufacturer what non-linear load the set will carry.
Does class G3 guarantee that a large motor will start without trouble?
Not by itself. The class sets voltage and frequency limits for an agreed load step, but the actual dip depends on the size of the step, its power factor and the engine and alternator of the set (clause 15.2). If starting a motor is critical, declare it in the purchase with its power and starting method.
Where are the numerical values of each class?
ISO 8528-1 defines the classes in words. Engine speed regulation limits are in ISO 8528-2, alternator limits in ISO 8528-3, and those of the complete set under load steps in ISO 8528-5.