To design and quote a low-voltage switchboard the engineer needs seven groups of data: the electrical system, the load, the short circuit, the site, protection and metering, the required standards and delivery conditions. With them the offer is comparable and the assembly is designed once; without them the designer assumes, and the assumptions return later as extras.
Short answer
To get an LV switchboard designed and quoted, provide seven groups of data: electrical system (voltage, frequency and earthing), load and growth, prospective short-circuit current, site conditions, protection and metering, required standards and delivery conditions. With the single-line diagram and a load schedule you already have half of it. The rest should be confirmed before the request goes out, not after.
The whole process is in specifying an LV switchboard before ordering, and the formal template of the standard in data to specify a low-voltage assembly. Below is which data is worth sending, what the designer uses it for and how to get it.
The data and what it is used for
- System and short circuit. Fix the insulation, the busbar strength and the breaking capacity of the breakers
- Load and growth. Fix the busbar current, the number of feeders and the spare capacity
- Site and environment. Fix the IP degree, the ventilation and the enclosure material
- Protection, metering and standards. Fix the control devices, the auxiliary wiring and the tests
- Comparable offer. The designer quotes a defined design, not an assumption
| Group | What to send | What the designer uses it for | How to get it |
|---|---|---|---|
| Electrical system | Voltage, frequency, phases and wires, earthing system | Devices, insulation, protection against electric shock | Single-line diagram and substation drawing |
| Load | Load schedule, simultaneity factor, expected growth | Busbar current, number of feeders, spare space | Design load schedule |
| Short circuit | Prospective current at the incoming terminals and contributions from large motors | Strength of the assembly and breaking capacity of the breakers | Network operator or short-circuit study |
| Site | Indoor or outdoor, altitude, temperature, humidity, dust, corrosion | IP degree, ventilation, enclosure material | Site visit |
| Protection and metering | Protection functions, meters, communications, transfer | Switching and control devices, auxiliary wiring | Protection study and utility requirements |
| Standards | IEC 61439, local regulations, owner standards | Tests, evidence, documentation | Contract and company policy |
| Delivery | Place, date, who unloads and who connects | Packing, schedule, installation scope | Project schedule |
What is most often forgotten
- Growth. A switchboard without spare capacity forces another one within a few years. IEC 61439-1 allows a rated diversity factor (RDF) to be declared, explained in rated diversity factor of a switchboard; if it is not declared, the designer assumes every feeder is loaded at the same time.
- Altitude. The normal service conditions of IEC 61439-1 (clause 7.1.4) reach 2,000 m. Above that, lower dielectric strength and weaker cooling must be considered. See service conditions of a switchboard.
- Motor contributions. Large motors feed a fault; if the calculated short circuit leaves them out, the figure is short.
- Cable entry and exit. From the top or the bottom, size, number of cables per phase and whether they arrive by busway. It changes dimensions and connection space.
- Who commissions. If the scope does not say it, the offer does not include it.
Worked example: a pumping station
A pumping station at 480 V three-phase has three 75 kW motors, two running and one on standby, plus 20 A of auxiliary services. It is fed from a 500 kVA transformer with 5 % impedance.
- Current of each motor. With efficiency 0.94 and power factor 0.87 (example assumptions; use the actual nameplate data): 75,000 / (√3 × 480 × 0.94 × 0.87) = 110 A.
- Simultaneous current. Two motors running plus the auxiliaries: 2 × 110 + 20 = 240 A.
- With 25 % growth: 240 × 1.25 = 300 A. The busbar is specified at 400 A.
- Short circuit. The transformer rated current is 500,000 / (√3 × 480) = 601 A; with 5 % impedance and an infinite source, 601 / 0.05 = 12.0 kA, not counting the contribution of the two running motors, which the short-circuit study adds. That total goes in the request as the maximum prospective current; the designer offers the standard rated value above it.
- Three motor feeders. Each with its starter and protection for 110 A full-load current.
With this data the designer sizes the assembly. Without calculation 4, a 400 A switchboard could come out with a short-circuit strength lower than the fault that can occur on site.
List to send with the request
- Updated single-line diagram and load schedule with growth.
- Voltage, frequency and earthing system.
- Short-circuit current at the incomer and its source (network operator or study).
- Site, altitude, temperature and environment.
- Location in the plant and access routes for installation.
- Protection, metering and communications required.
- Required standards and documents expected at delivery.
- Desired delivery date and who installs and commissions.
- Open questions you prefer the designer to propose.
After receiving the offers
If every offer answers to the same data, they can be compared line by line. If one asks for additional information, that is a good sign: it means the designer reviewed the request. Comparison and the contract continue in what a switchboard contract should include; if the switchboard replaces an existing one, first see new switchboard or upgrade the existing one.
How we can help
At Tiza Group we prepare the engineering of low-voltage switchboards: specification, short-circuit and protection studies and design review. See our primary engineering service and send us your single-line diagram and load schedule so we can quote the scope.
Related guides
- Specifying an LV switchboard before ordering
- Data to specify a low-voltage assembly
- What a switchboard contract should include
- New switchboard or upgrade the existing one
- Rated current of a switchboard: InA and Inc
- Icw, Ipk and Icc of a switchboard
- Service conditions of a low-voltage switchboard
- Electrical Panel Price: What Drives the Cost
- Panel Quotation: What to Request and How to Review It
- Certified Switchboard: What Certification Proves
References
- IEC 61439-1:2020, Low-voltage switchgear and controlgear assemblies: general rules (Annex C and clauses 5.3 and 7.1).
- IEC 61439-2:2020, Power switchgear and controlgear assemblies.
Frequently asked questions
What if I do not know the short-circuit current?
Ask the network operator or calculate it with a short-circuit study. A first conservative figure comes from the transformer rating and its nameplate impedance, assuming an infinite source upstream. Do not quote blind: the breakers and the strength of the assembly depend on that value.
Is the single-line diagram enough to quote?
It is the most useful document, but it is not enough. The single-line diagram shows what is fed and how it is protected; the environment, the growth, the required standards, the cable entry and the delivery conditions are missing.
Should I name device brands?
If your plant has already standardized a brand for spares or support, say so. If not, give the characteristics and let each offer propose the equivalent reference, then compare the references between offers.