A custom switchboard is designed for a specific installation: its own dimensions, single-line diagram, devices and fault levels. It requires the client to fix the input data in writing, the design to be verified under IEC 61439, and the finished board to pass routine verification by its manufacturer.
A custom switchboard is designed for a specific installation: its dimensions, single-line diagram, devices and short-circuit level. Compared with a catalog board it offers fit, but it raises a question: who demonstrates that this board meets the standard?
Short answer
A custom switchboard is a board whose design is adapted to the data of a project, instead of coming from a list of fixed models. To be safe and certifiable it needs: the client to fix the starting data in writing, the design to be verified under IEC 61439 (by test, comparison or assessment), and each finished board to pass routine verification. The general case of board types is in types of electrical switchboards.
What the client must define
IEC 61439-1 includes an informative user information template, and IEC 61439-2 lists the points agreed between manufacturer and user. Most problems with a custom board start with a datum that was never written down.
| Datum | Why it matters |
|---|---|
| Single-line diagram and loads | Defines breakers, busbars and outgoing ways |
| Voltage, frequency and earthing system | Sets insulation and the protective conductor scheme |
| Short-circuit current at the point | Sets the assembly’s Icw, Ipk and Icc |
| Altitude, temperature and environment | Current correction and material selection |
| IP and IK degree | Enclosure for the location |
| Form of separation and unit type | How much can be worked on with the rest energized |
| Access (front, rear, sides) | Room and door dimensions |
| Spare capacity and planned expansion | Space and busbars to grow |
The guide data to specify a low-voltage switchboard explains each point in detail.
Who verifies the design
IEC 61439-1 distinguishes the original manufacturer, who designs and verifies, from the assembly manufacturer, who answers for the finished assembly. A custom board can fall in two situations: within an already verified system, or with its own arrangements. See original manufacturer and assembly manufacturer and design verification for the three methods.
- Is there a catalog board that covers function, current, short-circuit and dimensions?
- Yes: Catalog board, with its product certificate
- No: Does the arrangement fall within an already verified board system, following its instructions?
- Yes: Custom board without new design verification
- No: Custom board with verification of the own arrangements, by test, comparison or assessment
Who answers for the finished board
Two points matter for a custom board:
- A certificate for the empty enclosure does not replace the verification of the board. The assembly manufacturer answers for the complete board, enclosure with devices.
- Each finished board passes routine verification by the assembly manufacturer before delivery, in addition to the design verification.
Worked example: the RDF of a custom board
A custom board has six outgoing ways of 400 A each. The designer declares a rated diversity factor (RDF) of 0.6, the per-unit value of rated current at which the circuits can be loaded simultaneously (IEC 61439-1, clause 5.4).
- Sum of the outgoing rated currents: 6 × 400 = 2,400 A.
- Simultaneous load with RDF 0.6: 2,400 × 0.6 = 1,440 A. The assembly’s rated current must be at least 1,440 A.
- Continuous current each outgoing way accepts with all loaded: 400 × 0.6 = 240 A.
- With an RDF of 0.8, the simultaneous load rises to 1,920 A and each way accepts 320 A continuously. The assembly then needs busbars and heat dissipation for that value.
If the real loads are lower than the declared RDF the board has margin; if higher, it overheats. For that reason the RDF is agreed with the client before the design is frozen. See rated diversity factor.
Specification checklist
- Approved single-line diagram and load schedule.
- Short-circuit current at the point, with the study behind it.
- Site conditions in writing, including altitude.
- Form of separation, unit type and access.
- An agreed RDF, not an assumed one.
- Who the original manufacturer of the system is and which part of the board falls outside what was verified.
- Design verification records that cover the whole board.
- Routine tests, drawings, manual and as-built single-line diagram.
What to avoid
- Do not accept «custom» as an excuse to skip design verification.
- Do not request a late change in short-circuit level without rechecking busbars and supports.
- Do not mix components from several systems in one board unless someone answers for the verification of the assembly.
- Do not release a design without an approved single-line diagram.
How we help
We prepare the engineering design of custom switchboards: single-line diagram, short-circuit and rating calculations, RDF definition, specification and drawings. See engineering design and studies or contact us.
Related guides
- Types of electrical switchboards
- Main low-voltage switchboard: what it is and what it holds
- Forms of separation of a switchboard
- Original manufacturer and assembly manufacturer: IEC 61439
- Data to specify a low-voltage switchboard
References
- IEC 61439-1:2020: definitions of original manufacturer and assembly manufacturer, clause 5.4 (RDF), clause 10 (design verification) and clause 11 (routine verification).
- IEC 61439-2:2020: items subject to agreement between manufacturer and user.
Frequently asked questions
Does a custom switchboard need its own proof of conformity?
Yes. Being custom does not exempt it: its design must be verified under IEC 61439 and each finished board must pass routine verification. A certificate for the empty enclosure does not cover the complete board.
Who verifies the design of a custom switchboard?
If the board is assembled within a system already verified by its original manufacturer and following its instructions, verification is not repeated. If it includes own arrangements that were not verified, whoever designs them takes on their verification by test, comparison or assessment.
What must the client provide for the board to come out right?
The single-line diagram, load and short-circuit currents, voltage and earthing system, site conditions, degree of protection, form of separation and mounting and maintenance preferences, all in writing.