Conventional Low-Voltage MCC: Parts and Sizing

What a conventional low-voltage MCC is, what it is made of and how its busbar is sized: a worked example with diversity and a design checklist.

By Shadai García, CEO and protection engineer at Tiza Group.

MT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.comMT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.com
LV switchboard and MCC: automatic transfer and forms of separation. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A conventional MCC groups the starters of several motors in vertical sections fed from a common busbar and controlled with conventional wiring, without its own digital communication. It is sized by the sum of currents with a diversity factor, by the source short circuit and by the number of units with spares.

Short answer

A conventional low-voltage MCC is a switchboard made of vertical sections, each with several motor starter units fed from a common horizontal busbar. It is called conventional because control and signaling are wired point to point, without its own communication bus. It is sized with three data: the sum of motor currents with a diversity factor, the short-circuit current of the source and the number of units with spares.

The MCC with communications and integrated motor relays is in intelligent MCC, and the version with drawers that can be withdrawn live is in MCC with withdrawable drawers. The MCC’s place among the other switchboards is in types of electrical switchboards.

What it is made of

  • Vertical section structure, normally steel, with a front door and wireways.
  • Main horizontal busbar, running the length of the MCC and fed from the incoming supply or incomer breaker.
  • Vertical busbar in each section, distributing power to the units.
  • Starter units: each with its protection, contactor and overload relay, installed in standard-height compartments or multiples of it.
  • Feeder and control units for other loads: feeders, control transformers, lighting.
  • Earth bar along the whole structure.
  • Field wiring trough in each section for motor and control cables.
  • Control and signaling: pushbuttons, selectors and pilot lights on each unit door, with wiring to the process control through terminals.

In a conventional MCC the units are usually fixed or plug-in; the withdrawable version has its own guide. The difference among the three is in fixed, disconnectable and withdrawable parts.

What drives the design

  1. Motor list with power, rated current, type of starting and duty.
  2. Source: voltage, transformer rating and reactance, or short-circuit level at the point.
  3. Diversity: how many motors run at once.
  4. Growth: spare units and space for future sections.
  5. Environment: indoor or outdoor, dust, humidity, IP degree.
  6. Internal arc: whether the project asks for a design tested against arcing.
  7. Form of separation of IEC 61439-2: from form 1 to 4b, according to what must be workable with the rest energized. See LV switchboard and MCC.

Worked example: 12-motor MCC with spares

Assumed data, not from a real project: 400 V three-phase, motor currents estimated with an efficiency times power factor of 0.8 (real data come from each motor nameplate).

MotorsPowerEstimated currentSubtotal
611 kW20 A120 A
422 kW40 A160 A
237 kW67 A134 A
Sum414 A

The estimated current is P / (√3 × 400 × 0.8): 11 kW gives 19.9 A; 22 kW, 39.7 A; 37 kW, 66.8 A.

  1. Diversity. If the process allows only 80 % of the connected current to run at once, the busbar design current is 414 × 0.8 = 331 A. That factor must be justified by the process, and the manufacturer declares it on the assembly as the rated diversity factor, under IEC 61439-1.
  2. Spares. Allowing 25 % growth on the design current gives 331 × 1.25 = 414 A.
  3. Busbar. A 400 A busbar falls short of 414 A; the next value of the usual series, 630 A, is chosen.
  4. Short circuit. With an 800 kVA transformer at 6 % impedance, the rated current is 1,155 A and the short-circuit current 19.3 kA on an infinite bus. The busbar and units must withstand it for the clearing time, or be protected by the upstream device. The rated short-time withstand of the assembly is requested from the manufacturer.
  5. Units. Twelve motors plus two spares make 14 units; at six per section, three sections.

The practical lesson is that the busbar is defined by planned growth and by the short circuit more than by starting current.

Selection table

DecisionOptionsCriterion
Unit typeFixed, plug-in or withdrawableRequired service continuity
Form of separation1, 2, 3 or 4What is worked on with the rest energized
Unit protectionMotor circuit breaker, breaker plus relay, fusesCurrent and coordination level
StartingDirect, star-delta, soft starter, driveLoad and network
ControlWired to terminals, with PLC or with busControl system
AccessFront or double frontRoom space
Internal arcUntested or testedRisk and safety policy

Checklist

  • The motor list is complete, with nameplate currents.
  • The units are coordinated with their protection (see type 1 and type 2 coordination).
  • The busbar withstands the source short circuit and the design states it.
  • There are spare units and space for another section.
  • The earth bar is continuous along the whole MCC.
  • The field troughs have room for the planned cables.
  • Each unit label shows motor, power and source panel.
  • Emergency stop and process interlocks are provided.

What not to do

  • Do not add nameplate currents without judgment and apply diversity without justifying it.
  • Do not size the busbar without knowing the source short circuit.
  • Do not fill the MCC without spares or growth space.
  • Do not modify a verified assembly without the original manufacturer validating it; see original manufacturer and assembly manufacturer.

How we help

We design the MCC: motor list, busbar and short-circuit sizing, form of separation, single-line and control diagrams, delivered remotely. See engineering design and studies.

References

  • IEC 61439-1 and IEC 61439-2, Low-voltage switchgear and controlgear assemblies, 2020 edition.
  • IEC 60947-4-1, Electromechanical contactors and motor-starters, edition 5 (2023).
  • UL 845, Motor Control Centers, sixth edition (2021).

Frequently asked questions

How does a conventional MCC differ from an intelligent one?

The conventional MCC is operated and signaled with point-to-point wiring and electromechanical or basic electronic relays; the intelligent one adds communicating motor relays and a bus to the control system. The structure, busbars and units are equivalent; what changes is what is wired to the control system.

How is the horizontal busbar of an MCC sized?

The rated currents of the motors are added, the diversity factor the project can justify is applied, a spare allowance for expansion is added and the standard busbar rating above is chosen. The busbar must also withstand the short-circuit current of the source.

Which standard covers the MCC?

IEC 61439-2 covers power assemblies, including MCCs, up to 1,000 V AC. In North America UL 845 is used, whose sixth edition dates from 2021. The coordination of each starter follows IEC 60947-4-1.