Two switchboard bids can be compared only when they cover the same scope. The method: a single specification, a technical compliance matrix, clarification of what is missing and only then scoring, with price as one criterion among others. An example with three bids and fixed weights shows how the cheapest bid can come last.
Short answer
To compare switchboard bids you must start from one scope: a single specification, a technical compliance matrix, clarification of what is missing and only then scoring, with price as one criterion among others. The lowest bid may be the one that covers least; that does not make it bad, but its price cannot be placed next to that of a bid with more scope.
For what a certified switchboard must carry see certified or uncertified switchboard, and for the delivery clock, switchboard lead time.
The method
- One specification for everyone. Same scope, same data
- Receive the bids. With their scope and exceptions
- Technical compliance matrix. One column per bid
- Does any bid price less than requested? Yes: continue; No: Score.
- Ask for clarification and pricing of what is missing. With the same deadline
- Score and decide. With weights fixed before opening prices
The order matters: the weights are fixed before the prices are opened. That way the score is not adjusted to favor anyone. And every clarification question is answered to all bidders, so that none has information the others did not.
What to compare
| Criterion | What to look at | Where it is explained |
|---|---|---|
| Currents | Rated current of the assembly and of each outgoing circuit | Rated current InA and Inc |
| Short-circuit | Icw, Ipk and Icc withstand, not only the breaking capacity of the breakers | Icw, Ipk and Icc |
| Structure | Form of separation, IP and IK degrees, fixed or withdrawable parts | Fixed, removable and withdrawable parts |
| Design verification | Which system, from which original manufacturer, by which method | Design verification |
| Product certificate | Of the complete assembly, valid at the manufacturing date | RETIE product certificate |
| Tests | Routine verification, FAT and who attends | Routine verification |
| Documents | As-built drawings, protocol, manuals, settings list | Manufacturing and handover |
| Lead time | By stage and with its starting point | Lead time |
| Warranty and support | Duration, what it covers and who answers | Bid conditions |
| Price | With the complete scope | Scored last |
Worked example: three bids
Three bids are compared for the same switchboard. Prices are expressed as relative indices (the lowest = 100), not as real values, and the weights add up to 100. All are assumptions of the example.
| Criterion | Weight | Bid A | Bid B | Bid C |
|---|---|---|---|---|
| Technical compliance | 30 | 24 | 29 | 30 |
| Certification and design verification | 20 | 10 | 20 | 20 |
| Tests and documents | 15 | 6 | 14 | 15 |
| Lead time | 10 | 8 | 6 | 4 |
| Warranty and support | 5 | 3 | 4 | 5 |
| Price (index) | 20 | 100 | 108 | 121 |
The price score is calculated as 20 × (lowest price ÷ price of the bid):
- A: 20 × 100 ÷ 100 = 20.0
- B: 20 × 100 ÷ 108 = 18.5
- C: 20 × 100 ÷ 121 = 16.5
Totals:
| A | B | C | |
|---|---|---|---|
| Sum of technical and lead-time criteria | 51 | 73 | 74 |
| Price score | 20.0 | 18.5 | 16.5 |
| Total | 71.0 | 91.5 | 90.5 |
The cheapest bid, A, comes last because it includes neither a valid certificate nor a FAT. Where a product certificate is mandatory, as in Colombia, such a bid is not admissible; it is scored here only to show its effect on the matrix. B wins by one point over C, which costs 121 against 108 and has the longest lead time. If C shortened its lead time the result would change: that is why the matrix is a decision tool, not a verdict. The weights for your project are yours.
Scope that is often left out
What a bid does not include weighs as much as what it includes. Ask in writing whether each item is in or out of the price:
- Transport, lifting and unloading on site.
- FAT with the owner present and its travel costs.
- As-built drawings and manuals.
- Nameplates, marking and warning labels.
- Commissioning spares and special tools.
- Commissioning and operator training.
- Follow-up of the product certificate during the warranty.
Each item that one bid excludes and another includes must be valued against the specification, not by intuition. If a bidder prices it separately, add it before comparing.
Warning signs in a bid
- No product certificate for the assembly, or one for the enclosure only.
- «Equivalent make» without saying which, on the main breakers.
- No test protocol or FAT in the scope.
- Lead time with no stages and no starting point.
- Scope to be clarified «after the order».
- A short-circuit rating that does not match the study.
Checklist
- Single specification issued to all with the same deadline.
- Matrix weights fixed before opening prices.
- Matrix with one column per bid and exceptions noted.
- Clarifications requested in writing and answered.
- Certificates checked at the manufacturing date.
- Prices compared for the same scope.
- Decision recorded with its score.
How we help
We provide the design engineering of low-voltage switchboards, including the specification and the bid evaluation matrix: contact us with your specification or load list.
Related guides
- Certified or uncertified switchboard
- Switchboard lead time
- Switchboard manufacturing and handover
- Data to specify an LV switchboard
- Original manufacturer and assembly manufacturer
- Icw, Ipk and Icc of a switchboard
- How to Specify an LV Switchboard Before Ordering
- Electrical Panel Price: What Drives the Cost
- Panel Quotation: What to Request and How to Review It
References
- IEC 61439-1 and IEC 61439-2, low-voltage switchgear and controlgear assemblies: design and routine verification.
- Ministerio de Minas y Energía, RETIE (Resolution 40117 of 2024, amended by Resolution 40284 of 2026): switchboard product certificate.
Frequently asked questions
Why is the lowest bid not always the best?
Because it may cover less: a different short-circuit rating, different breakers, no product certificate, no FAT or no documents. What is not priced today is paid for later as an extra, or carried as a risk. Prices are compared only for bids with the same scope.
Which technical criteria should be compared between bids?
Rated current and short-circuit withstand rating, form of separation, IP degree, make and reference of the breakers, design verification of the system, product certificate of the assembly, tests included, handover documents, lead time by stage, warranty and support.
How is a bid that does not price something the others do treated?
The bidder is asked to clarify and price what is missing before scoring, with the same specification for everyone. If it does not, it is recorded as non-compliance. Its price is not compared with the others as if it were equal.