Switchboard Lead Time: What Drives Delivery

What sets the lead time of a low-voltage switchboard: drawing approval, long-lead equipment, design verification, tests and shipping, with a schedule.

By Shadai García, CEO and protection engineer at Tiza Group.

MT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.comMT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.com
LV switchboard and MCC: automatic transfer and forms of separation. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The lead time of a switchboard is set by the critical path: drawing approval, the longest-lead device, assembly and wiring, tests and shipping. Scope changes and drawing review cycles lengthen it most. A worked example with its own assumptions shows 18 weeks, 20 with one more review and 16 with early purchase of the long-lead device.

Short answer

The lead time of a switchboard is set by its critical path: drawing approval, the longest-lead device, assembly and wiring, tests and shipping. What lengthens it most is usually not the shop but scope changes and drawing review cycles. A sound proposal states the lead time by stage and the event from which it starts to count.

The stages are in switchboard manufacturing and handover.

What moves the lead time

FactorHow it affectsHow to reduce it
Open scopeEach change reopens drawings and purchasesClose scope and data before the order; see data to specify a switchboard
Drawing approval cyclesEach revision adds days of drafting and replyOne cycle with a reply on an agreed date
Longest-lead deviceSets the start of assemblyEarly purchase after the single-line is approved
Unverified designRequires verification before assemblyUse a system already verified by its original manufacturer
Product certificateAn expired certificate stops the workCheck validity before ordering; see certified or uncertified switchboard
Tests and FAT with the ownerDepend on both calendarsFix the FAT date when placing the order
Shipping and site accessLarge units need lifting and permitsDefine weight, dimensions and route early

On unverified designs: clause 10.1 of IEC 61439-1 says that whoever adds arrangements not included in the original verification is considered the original manufacturer for those arrangements. See original manufacturer and assembly manufacturer and design verification.

The critical path

Critical path of a switchboard order
  1. Supplier: Drawings. Single-line, front view and terminals
  2. Owner: Approved in the first cycle? Yes: continue; No: back to step 1.
  3. Supplier: Purchase of the longest-lead device. Sets the start of assembly
  4. Supplier: Assembly and wiring. With the enclosure ready
  5. Supplier: Routine tests and FAT. With the date set at order
  6. Supplier: Packing and delivery. With the handover file

Enclosure preparation runs in parallel with the wait for the longest-lead device; that device, not the shop, drives the schedule.

Worked example: 18 weeks, 20 and 16

The values below are assumptions of the example, not market lead times. Replace them with those of your proposal.

StageWeeks
Drawings and first review by the supplier2
Owner approval1
Longest-lead device (in parallel with 3 weeks of enclosure preparation)8
Assembly3
Wiring2
Routine verification and FAT1
Packing and delivery1

Base case: 2 + 1 + 8 + 3 + 2 + 1 + 1 = 18 weeks. The 3 weeks of enclosure preparation overlap with the 8-week wait and do not add.

One more drawing revision: 1 week of changes and 1 of approval add 2 weeks: 20 weeks.

Early purchase: if the longest-lead device is ordered once the single-line is approved, at week 1 instead of week 3, 2 weeks are gained: 16 weeks. The risk is that a later single-line change leaves the wrong device purchased; do it only with the scope closed.

The difference between 16 and 20 weeks is 4 weeks, 22 % of the base case, and it came from owner decisions, not from the shop.

Planning the date backwards

The date that matters is energization, not factory delivery. It is calculated backwards. Using the base-case assumptions (18 weeks) and these additional ones: 1 week of shipping and lifting and 2 of site installation and testing.

  1. Target energization: week 30.
  2. Site installation and testing: 2 weeks, so the switchboard must be on site by week 28.
  3. Shipping and lifting: 1 week, so it leaves the factory in week 27.
  4. Lead time: 18 weeks, which include the drawings and their approval; the order must be signed in week 27 − 18 = week 9.

With one more drawing revision the order would have to be signed in week 7. A 2-week margin for the unexpected moves it to week 5. That is why the lead time is negotiated with the site, not only with the supplier.

What to ask for in the proposal

  • Lead time by stage and the event from which it counts: order, down payment, drawing approval.
  • Longest-lead device identified and its estimated arrival date.
  • Number of drawing review cycles included and the reply time of each party.
  • FAT date and delivery date, with their conditions.
  • Product certificate valid at the manufacturing date.
  • What happens to the lead time if the scope changes.
  • Weight, dimensions and shipping and lifting requirements.

What not to accept

Do not accept a single lead time with no stages and no starting point. Do not accept shortening it by cutting routine verification or the FAT: they are part of the product, not of the paperwork. And be wary of a delivery date that does not mention the longest-lead device. To compare proposals as a whole, read how to compare switchboard bids.

How we help

We provide the design engineering of low-voltage switchboards, including the specification package and the schedule by stage for the order: contact us with your target date.

References

  • IEC 61439-1, Low-voltage switchgear and controlgear assemblies: general rules, clause 10.1 (design verification).
  • Ministerio de Minas y Energía, RETIE (Resolution 40117 of 2024, amended by Resolution 40284 of 2026): switchboard product certificate.

Frequently asked questions

What does the lead time of a switchboard depend on?

On the critical path: how long drawing approval takes, when the longest-lead device arrives (for example the main breaker), assembly and wiring, tests and shipping. Scope changes after drawing approval and drawing revisions are the most common causes of delay.

Can lead time be shortened without losing quality?

Yes, without cutting tests. It is shortened by closing the scope earlier, approving drawings in a single cycle, buying the longest-lead device early once the single-line diagram is fixed and setting the FAT date in the order. Removing routine verification or the FAT is not an option: they are part of what is purchased.

Does an unverified design lengthen the lead time?

Yes. If the switchboard uses arrangements that the original manufacturer's design verification does not cover, IEC 61439-1 treats the assembler as the original manufacturer for those arrangements, who must verify them, for example by test. That adds weeks that belong in the schedule from the start.