What an LV Switchboard Contract Should Include

Technical clauses an LV switchboard contract should carry: scope, standards, tests, documents, schedule and payments, with a worked milestone example.

By Shadai García, CEO and protection engineer at Tiza Group.

MT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.comMT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.com
LV switchboard and MCC: automatic transfer and forms of separation. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The contract for a low-voltage switchboard turns the specification into obligations: scope and exclusions, standards and edition, acceptance tests, delivery documents, schedule and delay damages, milestone payments and warranty. A contract that refers to the offer without listing these points leaves the discussion for delivery day.

Short answer

The contract for an LV switchboard should include, as a minimum: the scope with its exclusions, the technical specification as an annex, the standards with their edition, the acceptance tests and delivery documents, the schedule with the consequences of delay, milestone payments and the warranty. Every point that is left out is later resolved by the assumptions of each party.

The previous step is in specifying an LV switchboard before ordering. What follows is what is technical and must be written for the contract to be fulfillable; the legal side is for your legal adviser.

Technical and commercial clauses

ClauseWhat to fixRisk if missing
ScopeWhat is designed, delivered, installed, connected and commissioned; what is excludedExtras for everything not written
Contract documentsOrder of precedence: contract, specification, offerContradictions with no tie-break rule
StandardsIEC 61439-1 and -2 with edition; local regulationsDispute about what had to be met
ComponentsReferences or acceptable equivalents; changes only with authorizationUnannounced substitutions
TestsRoutine verification, additional tests, buyer attendanceDelivery without evidence
Delivery documentsAs-built drawings, records, manuals, certificates, settingsA switchboard nobody can maintain
Schedule and damagesDate, milestones, delay damages and their capDeadlines without consequences
PaymentsMilestones, retention and conditions for each paymentPayments disconnected from progress
WarrantyCoverage, start, period and claimsClaims without a route
BondsCover, amounts and validityBreach without backing
ChangesWho approves them and how they are pricedChanges made verbally

Technical evidence the contract should require

  • Design verification. The design must be verified by the original manufacturer under clause 10 of IEC 61439-1 (test, comparison with a tested reference design or assessment). Ask for the summary of what was verified: design verification.
  • Routine verification. Every switchboard is verified before it leaves (clause 11), with a signed record. See routine verification.
  • Who is who. The contract should say who is the original manufacturer and who is the assembly manufacturer: original manufacturer and assembly manufacturer.
What each party signs before dispatch
  1. Design verification. The original manufacturer delivers the summary of tests, comparison or assessment
  2. Routine verification. The assembly manufacturer delivers the signed record of that unit
  3. Factory acceptance. The buyer or its representative attends and signs the record
  4. Certificates and drawings. Applicable certificates and as-built drawings
  5. Dispatch. The payment tied to this milestone is released

Worked example: payments and delay damages

Take a contract of value 100 (in whatever unit) with these milestones, which are illustrative and not a recommendation:

MilestonePaymentCumulative
Signature and drawing approval3030
Factory acceptance4070
Delivery on site2595
Commissioning5100

The final 5 is a retention released when the switchboard is commissioned with its signed test record.

Delay damages are set at 0.5 % of the contract value per week, capped at 10 %:

  • Six weeks late: 6 × 0.5 % = 3 % of the contract, that is, 3.
  • Twenty weeks late: 20 × 0.5 % = 10 %, which is the cap: it stops growing.

The cap protects the supplier from unlimited damages and gives the buyer a known figure; if what is late is one milestone and not the whole, the clause must say on what value it is calculated.

Approving drawings before manufacture

An order that saves money: the supplier submits the manufacturing drawings (single-line diagram, front view, bill of materials and busbar arrangement) and the buyer approves them in writing before the devices are bought and the sheet metal is cut. The contract fixes how many days each party has to review and what happens if the buyer changes something after approval: the change is priced and the schedule adjusted, not done verbally. This avoids the most frequent cause of delay: modifications that arrive when the assembly is half built.

It is also worth fixing what happens if the contract ends early: who keeps the drawings, what is paid for what is already built and what happens to the devices bought for that order.

Checklist before signing

  • The scope says who installs, connects and commissions.
  • The technical specification is an annex with an order of precedence.
  • The standards are listed with their edition.
  • The main components are listed, with a rule to substitute them.
  • The tests and delivery documents are listed.
  • There is a date, milestones, delay damages and a cap.
  • Payments are tied to evidence, not only to dates.
  • The warranty says from when it runs and how a claim is made: switchboard warranty.
  • Bonds are defined.
  • Changes require written approval.

How we can help

At Tiza Group we prepare the engineering of low-voltage switchboards: specification, test lists, short-circuit and protection studies and design review. See our primary engineering service and tell us about your project so we can quote the scope.

References

  • IEC 61439-1:2020, Low-voltage switchgear and controlgear assemblies: general rules (clauses 10 and 11).
  • IEC 61439-2:2020, Power switchgear and controlgear assemblies.

Frequently asked questions

Should the contract include the full technical specification?

Yes, as an annex with an order of precedence: if the offer and the specification contradict each other, it must be written which one prevails. A contract that only says 'as per offer' leaves out whatever the offer does not mention.

How is the factory acceptance test written?

With the routine verification of IEC 61439-1 (clause 11) as a minimum, the date of the test, who attends for the buyer and what happens if it fails. Any additional test, such as a visual inspection against drawings, is listed separately.

Is design verification part of the contract?

It should be. Ask for a summary of what was verified under clause 10 of IEC 61439-1 (test, comparison with a tested reference design or assessment) and who performed it, because it is the evidence that the design meets the standard.