The contract for a low-voltage switchboard turns the specification into obligations: scope and exclusions, standards and edition, acceptance tests, delivery documents, schedule and delay damages, milestone payments and warranty. A contract that refers to the offer without listing these points leaves the discussion for delivery day.
Short answer
The contract for an LV switchboard should include, as a minimum: the scope with its exclusions, the technical specification as an annex, the standards with their edition, the acceptance tests and delivery documents, the schedule with the consequences of delay, milestone payments and the warranty. Every point that is left out is later resolved by the assumptions of each party.
The previous step is in specifying an LV switchboard before ordering. What follows is what is technical and must be written for the contract to be fulfillable; the legal side is for your legal adviser.
Technical and commercial clauses
| Clause | What to fix | Risk if missing |
|---|---|---|
| Scope | What is designed, delivered, installed, connected and commissioned; what is excluded | Extras for everything not written |
| Contract documents | Order of precedence: contract, specification, offer | Contradictions with no tie-break rule |
| Standards | IEC 61439-1 and -2 with edition; local regulations | Dispute about what had to be met |
| Components | References or acceptable equivalents; changes only with authorization | Unannounced substitutions |
| Tests | Routine verification, additional tests, buyer attendance | Delivery without evidence |
| Delivery documents | As-built drawings, records, manuals, certificates, settings | A switchboard nobody can maintain |
| Schedule and damages | Date, milestones, delay damages and their cap | Deadlines without consequences |
| Payments | Milestones, retention and conditions for each payment | Payments disconnected from progress |
| Warranty | Coverage, start, period and claims | Claims without a route |
| Bonds | Cover, amounts and validity | Breach without backing |
| Changes | Who approves them and how they are priced | Changes made verbally |
Technical evidence the contract should require
- Design verification. The design must be verified by the original manufacturer under clause 10 of IEC 61439-1 (test, comparison with a tested reference design or assessment). Ask for the summary of what was verified: design verification.
- Routine verification. Every switchboard is verified before it leaves (clause 11), with a signed record. See routine verification.
- Who is who. The contract should say who is the original manufacturer and who is the assembly manufacturer: original manufacturer and assembly manufacturer.
- Design verification. The original manufacturer delivers the summary of tests, comparison or assessment
- Routine verification. The assembly manufacturer delivers the signed record of that unit
- Factory acceptance. The buyer or its representative attends and signs the record
- Certificates and drawings. Applicable certificates and as-built drawings
- Dispatch. The payment tied to this milestone is released
Worked example: payments and delay damages
Take a contract of value 100 (in whatever unit) with these milestones, which are illustrative and not a recommendation:
| Milestone | Payment | Cumulative |
|---|---|---|
| Signature and drawing approval | 30 | 30 |
| Factory acceptance | 40 | 70 |
| Delivery on site | 25 | 95 |
| Commissioning | 5 | 100 |
The final 5 is a retention released when the switchboard is commissioned with its signed test record.
Delay damages are set at 0.5 % of the contract value per week, capped at 10 %:
- Six weeks late: 6 × 0.5 % = 3 % of the contract, that is, 3.
- Twenty weeks late: 20 × 0.5 % = 10 %, which is the cap: it stops growing.
The cap protects the supplier from unlimited damages and gives the buyer a known figure; if what is late is one milestone and not the whole, the clause must say on what value it is calculated.
Approving drawings before manufacture
An order that saves money: the supplier submits the manufacturing drawings (single-line diagram, front view, bill of materials and busbar arrangement) and the buyer approves them in writing before the devices are bought and the sheet metal is cut. The contract fixes how many days each party has to review and what happens if the buyer changes something after approval: the change is priced and the schedule adjusted, not done verbally. This avoids the most frequent cause of delay: modifications that arrive when the assembly is half built.
It is also worth fixing what happens if the contract ends early: who keeps the drawings, what is paid for what is already built and what happens to the devices bought for that order.
Checklist before signing
- The scope says who installs, connects and commissions.
- The technical specification is an annex with an order of precedence.
- The standards are listed with their edition.
- The main components are listed, with a rule to substitute them.
- The tests and delivery documents are listed.
- There is a date, milestones, delay damages and a cap.
- Payments are tied to evidence, not only to dates.
- The warranty says from when it runs and how a claim is made: switchboard warranty.
- Bonds are defined.
- Changes require written approval.
How we can help
At Tiza Group we prepare the engineering of low-voltage switchboards: specification, test lists, short-circuit and protection studies and design review. See our primary engineering service and tell us about your project so we can quote the scope.
Related guides
- Specifying an LV switchboard before ordering
- Design data an LV switchboard needs before quoting
- Switchboard warranty
- New switchboard or upgrade the existing one
- Original manufacturer and assembly manufacturer
- Design verification of a switchboard
- Electrical Panel Price: What Drives the Cost
- Panel Quotation: What to Request and How to Review It
- Certified Switchboard: What Certification Proves
References
- IEC 61439-1:2020, Low-voltage switchgear and controlgear assemblies: general rules (clauses 10 and 11).
- IEC 61439-2:2020, Power switchgear and controlgear assemblies.
Frequently asked questions
Should the contract include the full technical specification?
Yes, as an annex with an order of precedence: if the offer and the specification contradict each other, it must be written which one prevails. A contract that only says 'as per offer' leaves out whatever the offer does not mention.
How is the factory acceptance test written?
With the routine verification of IEC 61439-1 (clause 11) as a minimum, the date of the test, who attends for the buyer and what happens if it fails. Any additional test, such as a visual inspection against drawings, is listed separately.
Is design verification part of the contract?
It should be. Ask for a summary of what was verified under clause 10 of IEC 61439-1 (test, comparison with a tested reference design or assessment) and who performed it, because it is the evidence that the design meets the standard.