Building Distribution Boards: Main, Floor and Services

How a building's distribution boards are organized: main board, riser, floor boards and common services. Selection by zone and a ten-story worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

MT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.comMT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.com
LV switchboard and MCC: automatic transfer and forms of separation. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Electrical distribution in a building is built from a main board, a vertical riser, floor boards, meter boards and a common services board with backup. Each section's current is calculated with diversity factors that decrease as the number of floors served grows.

The distribution board system of a building is not a single board but a chain. Power enters through a main board, goes up a riser and is distributed to floor boards, meter boards and a common services board. Each section of the chain has its own design current.

Short answer

The electrical distribution of a building has five parts: the main board, which receives from the transformer or service entrance; the riser, in cable or busway, running through a vertical shaft; the floor boards, which feed each unit; the meter boards; and the common services board, for elevators, pumps and common-area lighting. Each section is sized for the load it really serves, not for the plain sum of all loads. The basic types are in types of electrical switchboards.

The parts and what each does

PartWhat it doesSized with
Main boardReceives power and feeds the riser and common servicesTotal building demand and transformer short-circuit current
RiserCarries power to the floorsCurrent per section and voltage drop
Meter boardHouses meters and their protectionNumber of units and utility requirements
Floor boardDistributes to the units on that floorFloor load and spare capacity
Common servicesElevators, pumps, stair pressurization, common areasMotor starting load and backup

The main board is a power assembly under IEC 61439-2. Floor boards operated by ordinary persons are distribution boards under IEC 61439-3. Metering requirements come from the local grid operator.

Choosing the riser

Cable or busway for the riser?
  • Do the cables for each floor fit in the vertical shaft and meet the voltage drop?
    • Yes: One cable feeder per floor from the main board
    • No: Is there room for a vertical busway?
      • Yes: Riser busway with a tap per floor
      • No: Split the building into two risers or relocate the main board

The guides busway: what it is and where it is used and types of busway explain the busbar alternative.

Worked example: a ten-story building

An office building of 10 floors at 208 V three-phase. Each floor has 60 kVA connected. Common services demand 80 kVA. The diversity factors are assumptions of the example; in a real project they are justified in the calculation report.

  1. Floor load: 10 × 60 = 600 kVA. With a diversity of 0.7: 420 kVA.
  2. Total demand: 420 + 80 = 500 kVA. Main board current: 500 / (√3 × 0.208) = 1,388 A.
  3. Lower riser section (floors 1 to 10): 420 / (√3 × 0.208) = 1,166 A.
  4. Riser from floor 6 to 10 (five floors, 300 kVA, with an assumed diversity of 0.75: 225 kVA): 225 / (√3 × 0.208) = 625 A.
  5. Each floor board: 60 kVA / (√3 × 0.208) = 166.5 A; with 25% spare, 208 A.

The result: the riser can carry less current on the upper floors. A busway built in sections takes advantage of that; with cables, the cross-section is reduced by section.

Common services and backup

Elevators, water pumps, stair pressurization and common-area lighting do not belong to any floor, and an outage in one of them affects all occupants. For that reason they have their own board, fed from the main board and not from a floor board. If the building has a standby generator, that board receives the backup supply through a transfer switch: see automatic transfer of sources. Elevator and pump motors draw a high starting current, so the breaker and cable are checked against that starting current and not only the running current. Which loads the generator backs up is defined in the design, circuit by circuit.

Checklist

  1. Connected load and demand per floor, with the diversity factor written down.
  2. Short-circuit current at the main board and at the riser base.
  3. Voltage drop from the main board to the farthest floor.
  4. Selectivity between the main board, each floor breaker and the outgoing ways.
  5. Location of the electrical room, ventilation and working space.
  6. Common services separate from the floors and with backup.
  7. Space and capacity reserved for one more floor or a new load.
  8. Compliance with the grid operator’s metering requirements.

What to avoid

  • Do not add all floor loads as if they ran at once: it oversizes the riser and the main board.
  • Do not connect elevators and pumps to a floor board.
  • Do not place the main board where it can flood or lacks ventilation.
  • Do not forget the voltage drop of the top floor with the future load.

How we help

We prepare the engineering design of building electrical distribution: load schedule, diversity, riser sizing, short-circuit and voltage drop calculations, specification and drawings. See engineering design and studies or contact us.

References

  • IEC 61439-1 and IEC 61439-2, 2020 edition: low-voltage and power assemblies.
  • IEC 61439-3:2024, distribution boards intended to be operated by ordinary persons.

Frequently asked questions

How many boards does a building have?

It depends on the design, but the structure is the same: a main board, a riser up to the floors, a board per floor or unit, meter boards and a common services board for elevators, pumps and common-area lighting.

Should the riser be cable or busway?

It is decided from the current, the space in the vertical shaft and the voltage drop. In tall buildings with high currents, busway usually takes less space than many parallel cables; in low buildings cable is usual.

Which board feeds the elevators and pumps?

The common services board, separate from the floors so that an outage or maintenance on one floor does not affect them, and with backup supply when a standby generator is planned.