Earthing of a high voltage installation in Australia is designed so that touch and step voltages stay below tolerable limits during a fault. AS 2067:2016 expanded its earthing content with reference to the Energy Networks Association's earthing handbook. The design chain runs from earth fault current to ground potential rise and then to touch voltage, and an illustrative example shows the main levers.
Earthing is where a high voltage design meets the human body. A fault in a substation pushes current into the ground, the ground around the substation rises in voltage, and a person touching metalwork may be exposed to part of that difference. The chain below is the one a designer works through in Australia. It builds on AS 2067 high voltage installations over 1 kV and the Australia electrical codes and grid connection guide.
Short answer: how does AS 2067 handle earthing and touch voltage in high voltage installations?
AS 2067 requires the earth system of a high voltage installation to keep touch and step voltages below tolerable limits during a fault, and to carry fault current without damage. The 2016 edition expanded its earthing content with reference to the Energy Networks Association’s earthing handbook. The designer calculates the earth fault current, the part that flows through the earth system and the resulting ground potential rise. Then the touch, step and transferred voltages are compared with the limits that the standard and the network operator name.
Editions
AS 2067:2016 is the third edition, and the earthing content was substantially expanded in that revision. A draft, DR AS 61936.1:2025, may eventually replace it. Always use the edition and the earthing rules that the network operator or the regulator names, and confirm them before a design is issued. Tolerable touch voltages depend on the edition and on fault clearing times, so take them from that edition.
The design chain
- Earth fault current. Found from a fault study of the network at the substation, for single-phase-to-earth faults at the worst location and system condition.
- Split of current. Part of the fault current returns through metallic paths such as cable screens and overhead earth wires. Only the rest flows through the earth system. See partial earth currents in an earth fault.
- Earth system resistance. Calculated from the soil, the grid layout and the electrodes. See grounding grid resistance: IEEE 80 formulas.
- Ground potential rise (GPR). The earth current multiplied by the resistance.
- Touch and step voltages. Calculated from the grid geometry and surface layer, and compared with the tolerable values for the fault duration. See gravel layer and the Cs factor and tolerable body current according to IEEE 80.
- Transferred voltage. Voltages carried out of the site by fences, pipes, cable screens and the neutral. See transferred voltage: cables, pipes and fences.
Methods differ by country, so compare with earthing grid: IEEE 80 vs EN 50522 and New Zealand’s ECP 35 when a project uses a foreign method.
The Australian twist: MEN and shared earths
In Australia, low-voltage networks use the multiple earthed neutral (MEN) system. A distribution substation often has a high voltage earth and a low-voltage neutral earth that are either combined or separated. This choice decides how much of the GPR is transferred to customers’ installations. A combined earth keeps the voltage between metalwork inside the substation low but exports the GPR to the network. A separated earth keeps customers safe if the distance and resistance are sufficient, but needs more space and verification. The designer must check the transferred voltage against the limit that the network operator sets for the low-voltage side. See AS/NZS 3000 main earthing and MEN systems.
Figure: single-line diagram of a distribution substation earth system showing earth fault current, the part returning by the cable screen, the earth grid, and the connection to the low-voltage neutral.
Worked example: ground potential rise
These values are illustrative.
A substation has a single-phase-to-earth fault current of 3200 A on the 22 kV side. The cable screens and overhead earth wire carry 40 % back to the source, so 60 % flows through the earth grid, or a split factor of 0.6. The grid resistance is 0.8 Ω.
- Current into the earth grid: 0.6 × 3200 = 1920 A.
- GPR: 1920 × 0.8 = 1536 V.
- Assume the grid study gives a maximum touch voltage of 25 % of GPR. The touch voltage is 0.25 × 1536 = 384 V.
- Compare 384 V with the tolerable touch voltage for the fault clearing time from your edition. If it is above, improve the design: lower the resistance, add conductors, increase the surface layer resistivity or reduce the fault clearing time.
- If a design change lowers the grid resistance to 0.5 Ω, GPR becomes 1920 × 0.5 = 960 V, and the touch voltage becomes 0.25 × 960 = 240 V.
The calculation shows the main levers. The tolerable values come from the standard and the network operator.
Checklist for the engineer
- Confirm the edition of AS 2067 and the network operator’s earthing rules.
- Obtain the earth fault current and clearing times, including future system changes.
- Calculate the current split and the earth resistance from measured soil data.
- Calculate GPR, touch, step and transferred voltages.
- Take tolerable values from the named edition, not from summaries.
- Decide between combined and separate high voltage and low voltage earths, and check the transferred voltage.
- Plan the verification: earth resistance and continuity measurements at commissioning.
Legal frame
In Queensland, professional engineering services must be provided by or under the direct supervision of an RPEQ, and Victoria has required registration for electrical engineers since 2023. Other states and territories set their own rules. Earthing designs usually need review by the network operator as well. Tiza delivers engineering and studies ready for your RPEQ in Queensland, or the registered or chartered engineer your state requires, to review and certify. Tiza does not stamp, sign or certify.
How Tiza can help
If your project needs an earthing study or a power system study, Tiza prepares fault current, current split and ground potential rise calculations remotely and in English. Contact us with the soil data, the fault levels and the site layout.
Frequently asked questions
What touch voltage limit does AS 2067 set?
The limit depends on the fault clearing time and on the assumptions the standard makes about the body and the contact. The values are in the standard and in the network operator's own earthing rules. Take them from the edition your regulator or network operator names.
What is ground potential rise?
It is the voltage the earth system reaches relative to remote earth when fault current flows into it. It equals the part of the fault current that actually flows through the earth system multiplied by the earth system resistance. It is the starting point for checking touch, step and transferred voltages.
How does the low-voltage MEN system connect to a high voltage earth?
In a multiple earthed neutral system, the low-voltage neutral is earthed at many points. If a high voltage earth and the low-voltage earth are combined or close, a high voltage fault can put a voltage on customer installations. The design chooses combined or separate earths and checks the transferred voltage.