AS 2067 is the Australian standard for substations and high voltage installations above 1 kV a.c. The 2016 edition added requirements for substations in or near buildings, expanded the earthing content and moved closer to IEC 61936. Network operators and regulators apply it through their own rules, and a fault level example shows how equipment ratings are checked.
A high voltage installation in Australia is rarely designed from a blank page. The network operator has its own rules, the regulator expects a recognised standard, and AS 2067 is the standard most often named. The wider framework is in the Australia electrical codes and grid connection guide. The earthing part has its own guide: AS 2067 earthing of high voltage installations.
Short answer: what is AS 2067 for high voltage installations over 1 kV?
AS 2067 gives the minimum requirements for the design and erection of substations and other high voltage installations above 1 kV a.c., at frequencies up to and including 60 Hz. It addresses the safe arrangement of equipment, clearances, protection against fire spread, earthing and the supporting systems. It does not replace the rules of the network operator, which are often stricter and specific to its own network.
Editions
AS 2067:2016 is the third edition, published in September 2016. Standards Australia said at the time that the revision addressed fire risk from substations within or near buildings and reflected changes to the National Construction Code. It also expanded the earthing content with reference to the Energy Networks Association’s earthing handbook and moved closer to the international standard IEC 61936. A draft, DR AS 61936.1:2025, based on IEC 61936-1:2021, was open for public comment until 21 April 2026. Standards Australia says it may eventually replace AS 2067, and that AS 2067:2016 remains current. Until a replacement is published and adopted, use the edition that the network operator or the electrical safety regulator names.
Standards Australia notes that existing installations are not automatically required to comply with the changes. Even so, a review of the installation against the current text is good practice, since regulators and network operators may ask for proof of compliance.
Where the standard sits
- Regulators. In Victoria, the standard is listed alongside the Electricity Safety Act 1998 and its regulations as applying to network operators and those who design, install and maintain high voltage installations. Other states have their own references.
- Network operators. They apply the standard through their own technical rules for connection and construction.
- Related standards. Cables, switchgear and transformers have their own product standards, and the low-voltage side follows AS/NZS 3000. See AS/NZS 3000 main earthing and MEN systems.
- Solar and storage plants. A plant substation is a high voltage installation too. See solar plant protection and PCC settings.
The design topics it organises
- Layout and clearances. Distances between live parts, and from live parts to people and structures, depend on the voltage level and the insulation.
- Fire and containment. Substations in or near buildings need measures against fire spread and oil or fluid spill. For equipment in the same area, see disconnector selection for a substation.
- Earthing. The earth system limits touch and step voltages and carries fault current. See the earthing guide in this series.
- Protection and fault clearance. Clearance times drive both equipment duty and earthing design.
- Signs, access and operation. Barriers, fences, labels and operating procedures.
For the physical station design, see solar MV power station (skid).
Figure: single-line diagram of a distribution substation at 22 kV with incoming line, circuit breaker, transformer, low-voltage board and earth system.
Worked example: fault level and equipment rating
These values are illustrative. A 22 kV busbar has a three-phase fault level of 250 MVA at the connection point.
- Symmetrical short-circuit current: 250 / (√3 × 22) = 250 / 38.105 = 6.56 kA.
- Assume an X/R ratio that gives a peak factor of 2.5. The peak current is 2.5 × 6.56 = 16.4 kA.
- Choose switchgear with a short-circuit breaking current above 6.56 kA. The next standard rating up is 8 kA, and many projects choose 12.5 kA or 16 kA for future growth.
- Choose a peak making and withstand rating above 16.4 kA. An 8 kA device built for a 2.5 factor gives 20 kA, which satisfies the check.
- Duration. The rating applies for a standard time, commonly 1 s or 3 s, and the protection clearing time must stay within it.
If the network later increases its fault level to 400 MVA, the current becomes 400 / 38.105 = 10.5 kA. An 8 kA device would then be inadequate. This is why the network operator’s future fault level is part of the design brief. For protection coordination, see short-circuit and protection coordination in solar plants.
Checklist for the engineer
- Confirm the edition and any draft status with the regulator and the network operator.
- Obtain the network operator’s technical rules for the connection and the fault levels, present and future.
- Define layout, clearances, fire measures and access for the substation location.
- Select equipment ratings from the calculated fault level, with margin.
- Design the earth system and check touch and step voltages: see AS 2067 earthing of high voltage installations.
- Review the protection clearing times against the equipment ratings.
- Prepare the commissioning plan. See substation commissioning and testing.
Legal frame
In Queensland, professional engineering services must be provided by or under the direct supervision of an RPEQ, and Victoria has required registration for electrical engineers since 2023. Other states and territories set their own rules. High voltage work is also regulated by the state electrical safety authority and the network operator. Tiza delivers engineering and studies ready for your RPEQ in Queensland, or the registered or chartered engineer your state requires, to review and certify. Tiza does not stamp, sign or certify.
How Tiza can help
If your project needs high voltage engineering design or power system studies, such as fault level, protection coordination and earthing, Tiza prepares them remotely and in English. Contact us with the network data and the single-line diagram.
Frequently asked questions
What does AS 2067 cover?
AS 2067 sets minimum requirements for the design and erection of substations and other high voltage installations with nominal voltages above 1 kV a.c. and frequency up to 60 Hz. It covers items such as layout, clearances, fire risk, earthing and protection, and it is used with the network operator's own requirements.
Which edition of AS 2067 is current?
AS 2067:2016, the third edition, is the edition in the catalogue. A draft, DR AS 61936.1:2025, based on IEC 61936-1:2021, closed for public comment in April 2026 and may eventually replace it. Confirm the status of the draft and the edition your network operator or regulator names before you issue a design.
Does an existing substation have to be rebuilt to meet the 2016 edition?
Standards Australia states that existing installations are not automatically required to comply with the changes. A review of the installation is still advised, because a regulator or network operator may ask for proof of compliance when work is done or when a new connection is made.