Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

AS/NZS 1768 Lightning Protection: Risk Assessment

AS/NZS 1768 lightning protection, now AS 1768:2021: how the risk assessment decides protection, what a system includes and a strike-frequency example.

By Shadai García, CEO and protection engineer at Tiza Group.

air terminaldownconductorearth terminationMainswitchboardsupplySPDDatacabinetdata lineSPDsupplydatabondinglightning10⁻⁶10⁻⁵10⁻⁴10⁻³tolerable1 × 10⁻⁵1.2 × 10⁻⁴1.2 × 10⁻⁵no protectionP = 0.1with SPCRP = 0.01above the target:add SPDs at thesupply and at sensitiveequipment, assess againrisk per year, log scaleN = 3 × 7,930 × 10⁻⁶ = 0.0238 per yearRiskStrikes NProbability PLoss LRiskMeasures© tizagrp.comair terminaldownconductorearth terminationMainswitchboardsupplySPDDatacabinetdata lineSPDsupplydatabondinglightning10⁻⁶10⁻⁵10⁻⁴10⁻³tolerable1 × 10⁻⁵1.2 × 10⁻⁴1.2 × 10⁻⁵no protectionP = 0.1with SPCRP = 0.01above the target:add SPDs at thesupply and at sensitiveequipment, assess againrisk per year, log scaleN = 3 × 7,930 × 10⁻⁶ = 0.0238 per yearRiskStrikes NProbability PLoss LRiskMeasures© tizagrp.com
AS 1768 building protection: external system, bonding and surge protective devices at the main switchboard and data cabinet, and the risk example against the tolerable level. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

AS/NZS 1768 was the Australian and New Zealand lightning protection standard. Its 2007 edition was revised and redesignated AS 1768:2021, a major revision that moves closer to the international IEC approach. The core idea is a risk assessment: the designer compares a calculated risk of lightning damage with a tolerable level and then chooses external protection, bonding and surge protective devices. The ground flash density at the site is a key input.

AS/NZS 1768 lightning protection is the standard Australian designers know by that name. Its 2007 joint edition was revised and redesignated as AS 1768:2021, and the number to quote on a new project is the 2021 one. The standard’s method is a risk assessment: a calculated risk of lightning damage is compared with a tolerable level, and the design adds protection until the comparison works. The overall framework is in the Australia electrical codes and grid connection guide.

Short answer: how does AS 1768 decide if protection is needed?

AS 1768:2021 includes a risk assessment tool. The designer estimates how often lightning will strike the structure, the probability that a strike causes damage and the resulting loss, and compares the product with a tolerable risk. If the risk is too high, the designer adds measures: an external lightning protection system, equipotential bonding, surge protective devices or a combination. A key input is the ground flash density, taken from a national map for the site. The standard adds that protection can be justified whatever the result of the assessment.

Edition and status

The current edition is AS 1768:2021, listed by Standards Australia as revising and replacing AS/NZS 1768:2007. The 2021 revision is a major change that brings the standard closer to the IEC approach. State regulators and the building rules decide where compliance is required, so confirm with the authority for the state in question.

What a protection scheme includes

Three layers appear in most schemes, and the risk assessment says which are needed:

  1. External protection. Air terminals, down conductors and an earth termination that take the strike current to ground in a controlled path.
  2. Bonding. Metallic services, structure and the earthing system are tied together so that potential differences inside the building stay low. This links to AS/NZS 3000 main earthing and MEN systems.
  3. Surge protective devices. Devices at the supply and at sensitive equipment limit the overvoltage that enters through power and signal cables.

The international method behind this thinking is covered in the guides on lightning protection of a structure, classes I to IV, lightning protection zones and lightning overvoltages in a substation. Where the Australian standard follows its own method, use the Australian edition.

Where a solar or storage project meets it

A large solar plant or a battery site is exposed: open ground, long cable runs and metallic structures. The risk assessment therefore covers the inverter stations, the control building and the communication lines, not only the main building. Surge protection on the d.c. side, bonding of the array frames and a coordinated earthing design all appear in the assessment.

Worked example: how often is the building struck?

This example is illustrative. A warehouse is 60 m long, 30 m wide and 8 m high. The site’s ground flash density is taken as 3 flashes per km² per year, a figure chosen for the example, not a map value.

  1. Equivalent collection area, using a common simplified approach with a 3H boundary: A = L × W + 2 × (3H) × (L + W) + π × (3H)²
  2. A = 60 × 30 + 2 × 24 × 90 + π × 24² = 1,800 + 4,320 + 1,810 = 7,930 m².
  3. Expected strikes per year: N = 3 × 7,930 × 10⁻⁶ = 0.0238 per year, about one strike every 42 years.
  4. Take a probability of damage per strike of 0.1 with no protection, and a loss factor of 0.05 for the loss being assessed. Risk = 0.0238 × 0.1 × 0.05 = 1.2 × 10⁻⁴ per year.
  5. Suppose the owner’s tolerable level for this loss is 1 × 10⁻⁵ per year, a target chosen for the example. The unprotected building is above it.
  6. With protection that reduces the probability of damage to 0.01, the risk becomes 1.2 × 10⁻⁵. That is closer but still above, so the designer adds surge protective devices at the supply and at the sensitive equipment to reduce the loss factor, and runs the assessment again.

The real assessment uses the standard’s method, its factors and the site’s mapped density. The example only shows the logic: frequency times probability times loss, compared with a tolerable level, repeated until the design passes.

Figure: block diagram of a building with an external lightning protection system, a bonded earthing system and surge protective devices at the main switchboard and at a data cabinet.

Checklist for the engineer

  • Quote the edition: AS 1768:2021.
  • Take the ground flash density for the site from the official map.
  • Define the structure, its services and the losses that matter to the owner.
  • Run the risk assessment and record the tolerable level used and who set it.
  • Specify bonding and surge protection together with any external system.
  • Check the earthing design against AS/NZS 3000 earthing and, for substations, the utility’s rules.
  • Plan inspection and maintenance with records. See inspection and maintenance of a lightning protection system.
  • Check the state regulator and the building rules for any mandatory requirement.

For the protective devices inside an installation, see AS/NZS 3000 RCD requirements and overcurrent protection. For the switchboard that carries the main surge protective device, see AS/NZS 61439 switchboards in Australia. For the United Kingdom view of surge protection, see BS 7671 chapter 44 overvoltage and surge protection.

Who certifies

Engineering registration is a state matter. In Queensland, professional engineering services must be provided by, or under the direct supervision of, an RPEQ. Victoria has required registration for electrical engineers since 2023, and other states set their own rules. Tiza does not stamp, sign or certify the assessment or the design.

How Tiza can help

If your project needs the risk assessment and the protection concept prepared, Tiza provides engineering design in English: the assessment, the protection layout and the bonding and earthing drawings. Tiza delivers engineering ready for your RPEQ in Queensland, or the registered or chartered engineer your state requires, to review and certify. Contact us with the site layout and the equipment list.

Frequently asked questions

Is AS/NZS 1768 still the current standard?

The 2007 joint edition was revised and redesignated as AS 1768:2021, which carries the Australian-only prefix. Designers working in Australia use the 2021 edition. For a project in New Zealand, confirm with the local authority which document applies.

Is lightning protection mandatory for every building in Australia?

No general rule makes it mandatory. The need comes from the risk assessment, from the building and electrical rules that call for it in specific cases, and from the owner's or insurer's requirements. The standard also says protection can be justified even when the assessment result is acceptable.

Does a lightning protection system make a building safe from lightning?

No. Following the standard reduces the probability of damage and injury but does not remove it. That is why the design pairs external protection with bonding and surge protective devices, and why inspection and maintenance matter.

WhatsApp