Tiza Group

Home / Guides / Codes and grid connection: US, UK, CA, AU

NEC Article 445: Generator Installation Rules Explained

NEC article 445 generators: conductor ampacity at 115 percent, overcurrent protection, disconnect and shutdown rules, and a full worked sizing example.

By Shadai García, CEO and protection engineer at Tiza Group.

G500 kW, 0.8 pfovercurrentdisconnect480 V loadsenginestopcontrolPowerControl500 kW / 0.8 = 625 kVA625,000 / (1.732 x 480) = 751.8 Ax 1.15 = 864.5 A, conductors 865 Athen device, disconnect, shutdowncurrent (A)751.8 Anameplate864.5 Ax 1.15 (445.13)SizingNameplate115 percentConductorProtectionShutdown© tizagrp.comG500 kW, 0.8 pfovercurrentdisconnect480 V loadsenginestopcontrolPowerControl500 kW / 0.8 = 625 kVA625,000 / (1.732 x 480) = 751.8 Ax 1.15 = 864.5 A, conductors 865 Athen device, disconnect, shutdowncurrent (A)751.8 Anameplate864.5 Ax 1.15 (445.13)SizingNameplate115 percentConductorProtectionShutdown© tizagrp.com
NEC Article 445: a 500 kW, 0.8 power factor standby generator with its overcurrent device, disconnect and engine stop control, and the nameplate current and the 115 percent conductor ampacity. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

NEC Article 445 covers the installation of generators: location, nameplate marking, overcurrent protection, conductor ampacity, guarding and the means to disconnect the generator and shut down its prime mover. Conductors from the generator terminals are sized at no less than 115 percent of the nameplate current. Protection of the machine itself, as a power system problem, is a separate subject handled by relays and studies.

NEC article 445 generators is the part of the National Electrical Code (NEC, NFPA 70) that governs how a generator is installed. It covers where the machine sits, how it is marked, how its conductors are sized and protected, and how it is disconnected and stopped. It applies to a diesel set in a hospital as it does to a generator on a factory site.

The wider framework is in the US electrical codes and grid interconnection guide. The machine itself and its relays are covered in the existing guides on the synchronous generator and its protection and on protection of a generator set.

Section numbers here follow the 2023 edition of the NEC. Confirm the numbering and local amendments in the edition your authority having jurisdiction (AHJ) has adopted.

Short answer

Article 445 asks for a generator that is marked, protected and located so it can be maintained safely. Conductors from the generator terminals are sized for at least 115 percent of the nameplate current (section 445.13). Overcurrent protection is covered by section 445.12 and Article 240. Section 445.18 covers the disconnecting means and the shutdown of the prime mover. The article leaves relay protection against internal and system faults to engineering practice.

What the article covers

The article is a set of installation rules:

  • Location and marking. The machine is installed where it can be reached for service and it carries a nameplate with its ratings.
  • Overcurrent protection. The generator and its conductors need protection, with rules on where the device sits and how it is rated.
  • Conductor ampacity. The conductors from the terminals are sized above the nameplate current, as shown below.
  • Protection of live parts and guards. People are kept away from live and moving parts.
  • Disconnect and shutdown. The generator output can be opened, and the prime mover can be stopped so it cannot restart on its own.

Related equipment is covered elsewhere in the NEC. Transfer equipment, emergency and standby systems have their own articles, and generator output that feeds the utility falls under the interconnection rules of the US codes guide.

Conductor ampacity at 115 percent

The 115 percent rule is the number most designers remember from this article. Its purpose is margin: a generator can run above its nameplate for a time, and the conductors must not be the weak part. It applies to the conductors from the terminals. It is not the final cable selection, which also needs the terminal temperature rating, the ambient and fill corrections and the voltage drop.

Disconnect and shutdown

Section 445.18 deals with two functions that look alike and are not:

  • The disconnecting means opens the generator output, so work can be done on the load side.
  • The shutdown of the prime mover stops the engine or turbine, so the machine cannot produce power again until it is restarted by someone.

Generators in parallel have their own arrangement. The design depends on what the AHJ accepts, so cite the exact subsection from the adopted code.

What the NEC does not cover

Article 445 is not a protection study. It does not set how a large generator is protected against stator faults, loss of excitation, reverse power or abnormal frequency. Those protections are chosen by the protection engineer, and in a grid-connected plant the utility will often specify them. The guides on generator grounding methods and fault currents and on the fault contribution of a generator show where the technical decisions are made.

The fault current of the generator also reaches the switchboards it feeds. Their ratings are checked as described in the sister guides on NEC Article 408 and on the available fault current marking. A battery-backed system next to the generator has its own article, covered in NEC Article 480.

Figure: a standby generator with its output disconnect, overcurrent protection, transfer switch and the shutdown signal to the prime mover.

Worked example: a standby generator at 480 V

The data are illustrative. A standby generator is rated 500 kW at 0.8 power factor, 480 V, three-phase.

  1. Apparent power: S = 500 / 0.8 = 625 kVA.
  2. Nameplate current: I = 625,000 / (1.732 × 480) = 751.8 A.
  3. Minimum conductor ampacity under 445.13: 751.8 × 1.15 = 864.5 A.
  4. Choose a conductor set, normally in parallel. Its ampacity must be at least 865 A in the NEC table of the adopted edition, at the terminal temperature rating, after the installation corrections.
  5. Select the overcurrent device and the disconnect for the same current, and check the ratings against the fault current that the generator and the utility can deliver.
  6. Check the shutdown arrangement: a disconnect on the output and a way to stop the engine.

Only the sequence matters here: nameplate current, the 115 percent factor, conductor, protection and finally the disconnect and shutdown.

Checklist for the engineer

  • Confirm the NEC edition and amendments adopted by the AHJ.
  • Read the generator nameplate and compute the rated current.
  • Size the conductors at no less than 115 percent of that current, then apply the terminal and installation corrections.
  • Select the overcurrent protection and check it against the available fault current.
  • Provide the disconnecting means and the shutdown of the prime mover required by section 445.18 of the adopted edition.
  • Provide guards and working space for the machine.
  • Check grounding and the neutral arrangement with the system design.
  • Coordinate the generator protection relays and the transfer scheme with the owner and the utility.

Who signs and seals

In the United States a design normally has to be signed and sealed by a professional engineer licensed in the state of the project. Generator installations are also reviewed by the fire authority and, for backup systems, by the utility.

Independent review of a generator package

When the generator, the switchgear and the transfer system come from a third party, an independent review can find gaps before the inspector does. It checks conductor sizing, protection ratings, the disconnect and shutdown arrangement and the fault current. Tiza offers independent review of a third-party design, ready for your engineer of record to review and stamp, remotely and in English. Tiza does not sign, seal or certify work in the United States. Contact us with the drawings and the equipment data.

Frequently asked questions

How are conductors from a generator sized under Article 445?

Section 445.13 asks for an ampacity of at least 115 percent of the nameplate current of the generator. Then the usual rules apply for the terminal temperature rating, correction factors and the table of the edition. The result is checked against the overcurrent device, which is covered in section 445.12 and Article 240.

What is the difference between a generator disconnect and an emergency shutdown?

The disconnect opens the generator output. The shutdown stops the prime mover so the machine cannot keep producing power. Section 445.18 deals with both. Confirm the arrangement with the AHJ.

Does Article 445 cover the protection relays of a large generator?

No. Article 445 is an installation rule. Protection against internal faults, loss of field, reverse power and similar conditions is designed with a protection study and relays. The NEC sets the minimum safety rules that the inspector checks. The relays and settings are set by engineering practice and the utility's requirements.

WhatsApp