Star-Delta Starter Panel: Contactors, Cables, Wiring

How a star-delta starter panel is wired and sized: current in each contactor, six motor cables, relay and interlocks, with a 22 kW worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

MT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.comMT/BTGinterlockATSLV busMMfeederCCMauxiliariesbusesUF 1UF 2UF 3term.Form 1no partitionsForm 2separate busbarsForm 3separate unitsForm 4separate terminalsIEC 61439-2: forms of internal separationIntegrationLSIG unitGatewaySCADA© tizagrp.com
LV switchboard and MCC: automatic transfer and forms of separation. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

In a star-delta panel the current is shared among three contactors and six cables to the motor. Two contactors carry about 58 % of the line current and the star contactor about 33 %. Sizing each device and cable that way, and interlocking the star contactor against the delta one, is what makes a correct panel.

Short answer

In a star-delta panel the motor current is shared among three contactors and six cables. The line and delta contactors each carry about 58 % of the rated line current, the star contactor about 33 %, and the six motor cables are sized for the phase current. That, plus an interlock that prevents closing star and delta together, defines a correct panel.

Why starting reduces current and torque to a third, which motors allow it and the control circuit are in star-delta starting. Its place among the other switchboards is in the parent guide, types of electrical switchboards.

What the panel contains

  • Short-circuit protection at the head, sized for the line current.
  • Line contactor (K1): connects the supply to the motor in both modes.
  • Star contactor (K3): joins the winding ends to form the star.
  • Delta contactor (K2): connects the windings in delta.
  • Overload relay, in the line or in series with the winding.
  • Timer (or the controller function) that decides the change from star to delta.
  • Interlock, electrical and where possible mechanical, between K3 and K2.
  • Control and signaling: start, stop, star and delta pilot lights.
  • Six output terminals to the motor.

Current in each device

The line current in delta is the motor rated current, In. The current per winding is In divided by √3, about 0.58 × In. In star the line current drops to a third of what it would be in delta.

DeviceCurrent carriedFactor on In
Head protectionLine current1.00
Line contactor K1Phase current0.58
Delta contactor K2Phase current0.58
Star contactor K3Current at the star point, only during starting0.33
Each of the six motor cablesPhase current0.58
Overload relay in series with the windingPhase current0.58

The star contactor carries less current and only during starting, so it can be smaller; it must nevertheless withstand the making and the starting current in star.

Worked example: 22 kW motor

Assumed data, not from a real project: 22 kW, 400 V motor connected in delta, with a rated line current of 40 A and a direct-on-line starting current of 7 times rated.

QuantityCalculationResult
Phase current in delta40 / √323.1 A
Current through K1 and K240 / √323.1 A
Current through K3 (star)40 / 313.3 A
Current in each motor cablePhase current23.1 A
Direct-on-line start7 × 40280 A
Star start280 / 393 A
Relay setting in series with the windingPhase current23.1 A
Relay setting in the lineLine current40 A

Conclusions from the example:

  1. Contactors K1 and K2 are chosen for about 23 A in category AC-3, not for 40 A; in practice the next commercial size is taken.
  2. Six cables sized for 23.1 A are needed instead of three for 40 A; the panel and the motor carry more conductors, and the motor terminal box must have room for six terminals.
  3. The starting peak drops from 280 A to 93 A, but torque also drops to a third; the load must be able to accelerate with that torque.
  4. A setting error on the relay in series with the winding (40 A instead of 23.1 A) leaves the motor without real protection: the relay allows a line current of 69 A before tripping.

The arithmetic in point 4: a 40 A setting in the winding equals 40 × √3 = 69.3 A of line current.

Wiring in the panel

  • Motor terminal marking: the six ends are identified as U1, V1, W1 and U2, V2, W2 or with the mark defined by the motor manufacturer; the panel uses the same mark on its terminals.
  • Usual arrangement: K1 takes L1, L2 and L3 to ends U1, V1 and W1; K2 takes L1, L2 and L3 to ends W2, U2 and V2; K3 joins U2, V2 and W2. In star, K1 and K3 close; in delta, K1 and K2. In this arrangement each line enters the motor through two contactors and each carries the phase current, hence the 0.58 factor. If the diagram connects K2 between the motor terminals, K1 carries the full line current and must be sized for it.
  • Power wiring with conductors of equal length and cross-section for each phase, so the currents share equally.
  • K2 and K3 interlock: a normally closed auxiliary contact of each in series with the coil of the other, plus a mechanical interlock if the contactor offers one.
  • Transition dead time: K3 opens and K2 closes after a short interval, so the opening arc is extinguished before the delta closes. The interval is set according to the manufacturer’s guide.
  • Change-over time: set according to how long the motor takes to accelerate in star; switching to delta too early reproduces a current peak similar to direct starting. See the transition in star-delta starting.

Checklist

  • The motor has six terminals and its delta voltage is the supply voltage.
  • K1 and K2 are sized for the phase current; K3 for the star current.
  • There are six cables of adequate cross-section and a terminal box with room.
  • The overload relay is set according to its position, line or winding.
  • The K2/K3 interlock is electrical and, if possible, mechanical.
  • The change-over time was set with the real motor and load.
  • Rotation is the same in star and in delta.
  • The load starts with a third of the available torque.

What not to do

  • Do not use star-delta on high-torque or heavy-start loads; see selecting a starter by application.
  • Do not wire K2 and K3 without an interlock.
  • Do not assume the cross-section of the six cables: it is calculated for the phase current and checked against the installation conditions.
  • Do not set the relay to the line current when it is in series with the winding.

How we help

We design the star-delta starter panel: contactor and cable sizing, wiring diagrams, interlocks and timing criteria, delivered remotely. See engineering design and studies.

References

  • IEC 60947-4-1, Electromechanical contactors and motor-starters, edition 5 (2023).
  • IEC 61439-1 and IEC 61439-2, Low-voltage switchgear and controlgear assemblies, 2020 edition.

Frequently asked questions

How many cables leave the panel for the motor in star-delta?

Six, one for each end of the three windings, because the motor is connected in star or delta from the panel. Each cable carries the phase current, which is 1/√3 (about 58 %) of the line current in delta.

Why can the star and delta contactors not close together?

Because they would short-circuit the phases. They are interlocked mechanically and electrically: the star contactor must open before the delta one closes, with a brief dead time between them.

Where is the overload relay placed in a star-delta starter?

It can sit in the line, ahead of the contactors, or in series with each winding. In the line it is set to the rated line current; in series with the winding, to the phase current, 58 % of the former. The relay manufacturer's instruction must be followed.