The DC combiner box joins several photovoltaic strings into one output toward the inverter. It holds gPV fuses per string, positive and negative busbars, a DC disconnect switch and, where the site calls for it, surge protection. It is designed from the module short-circuit current, the number of strings and the reverse current that can flow in a fault.
The solar DC combiner box gathers the outputs of several strings into one output to the inverter. The parts of a combiner are described in string combiner box. It is one variant of types of electrical panels. The AC side of the plant is the interconnection panel.
Short answer
A combiner panel joins N strings in parallel with gPV fuses on each string (where needed), positive and negative busbars, a DC disconnect switch rated for the array voltage and, depending on the site, surge protection and current monitoring. It is sized from the module short-circuit current (Isc): the output carries N × Isc, and the design current is obtained with the factor in the applicable code.
When it is used and when it is not
With multi-MPPT string inverters each string goes straight to the inverter and no combiner is needed. The panel is justified when there are many strings per inverter, particularly with central inverters, or when the distance to the inverter makes a single larger cable convenient. See the comparison in central or string inverter.
What drives the design
| Element | Sized from | What to check |
|---|---|---|
| String fuse | String design current and the module maximum series fuse | gPV fuse (IEC 60269-6), rated for the array DC voltage |
| Busbars | N × Isc with the code factor | Cross-section and insulation at array voltage |
| Disconnect switch | Output current and maximum array voltage | IEC 60947-3 utilization category, DC-PV1 or DC-PV2 |
| Surge protection | Maximum DC operating voltage | IEC 61643-31 up to 1,500 V DC |
| Enclosure | Site, radiation and humidity | IP rating; see IP rating of a panel |
| Output | Design current and voltage drop | Output cable cross-section |
On the IEC 60947-3 categories: switch manufacturers describe DC-PV1 as the category for switching strings where no reverse current or significant overcurrent can occur, and DC-PV2 as the one for circuits where severe overcurrent may occur. The switch catalogue states which one it meets and at what current per pole. Switches and fuses are covered in gPV fuses and DC disconnects.
Selection table by number of strings
For strings of a module with Isc = 14.0 A (example data; use your data sheet). The maximum circuit current is N × Isc × 1.25 under NFPA 70-2017 section 690.8(A)(1). The cable and its protection are then sized for 125 % of that maximum current (sections 690.8(B) and 690.9(B)); the edition adopted locally may number these subsections differently:
| Strings (N) | Output Isc (N × 14.0 A) | Maximum current (× 1.25) | Cable and protection (× 1.25 again) | Reverse current in a faulted string ((N − 1) × 14.0 A) |
|---|---|---|---|---|
| 4 | 56 A | 70 A | 87.5 A | 42 A |
| 8 | 112 A | 140 A | 175 A | 98 A |
| 12 | 168 A | 210 A | 262.5 A | 154 A |
| 16 | 224 A | 280 A | 350 A | 210 A |
The disconnect switch and the output cable are selected with the value in column 4.
Worked example
A 12-string box. The module has Isc = 14.0 A and its data sheet gives a maximum series fuse of 25 A (example data).
- Does each string need a fuse? The maximum reverse current is (12 − 1) × 14.0 = 154 A, far above the 25 A the module withstands. Yes: every string gets a fuse.
- Fuse of one string. Maximum string current: 1.25 × 14.0 = 17.5 A. Minimum fuse rating: 1.25 × 17.5 = 21.9 A (section 690.9(B)). Maximum rating: the module maximum series fuse, 25 A. A 25 A gPV fuse meets both limits.
- Box output. Total Isc = 12 × 14.0 = 168 A. Maximum current = 1.25 × 168 = 210 A. Output cable and its protection: 1.25 × 210 = 262.5 A. The disconnect switch and the output cable must carry at least that current, at the maximum array voltage.
- Fuse holders. Their number depends on whether the design protects one pole or both poles of each string; the criterion is in string combiner box and in the applicable code.
The maximum array voltage is calculated from the string Voc corrected for the minimum site temperature; the procedure is in sizing PV strings.
Marking and safety
- IEC 62548-1:2023 covers the marking of array and string combiner boxes.
- Photovoltaic circuits do not share an enclosure with circuits of other systems unless a physical barrier separates them.
- With the switch open, the strings stay energized as long as there is light; the label must say so. See lockout and tagging in solar plants.
Checklist
- Module Isc, Voc and maximum series fuse taken from the data sheet.
- Reverse current calculated and the per-string fuse decision documented.
- gPV fuses rated for the array DC voltage.
- Disconnect switch of the category and current stated in its catalogue.
- DC surge protection if the site and the wiring call for it; see surge protection in PV systems.
- Busbars and terminals sized for the design current.
- Enclosure with an IP rating and radiation resistance suited to the site.
- Warning marking and diagram inside the door.
- Cable glands and connectors that keep the IP rating at each string entry.
How we help
We design combiner panels remotely, worldwide: fuse and disconnect selection, busbar and enclosure layout, single-line diagram and bill of materials, adapted to the local code and the utility requirements you give us. See our primary engineering service and write to us with the module, the number of strings and the inverter.
Related guides
- Types of electrical panels: which one to choose for your load
- Distributed generation interconnection panel
- Revenue metering point panel
- String combiner box: parts and functions
- gPV fuses and DC disconnects
- Sizing PV strings
- Surge protection in PV systems
References
- IEC 62548-1:2023, Photovoltaic (PV) arrays – Part 1: Design requirements.
- IEC 60269-6, fuse-links for the protection of solar photovoltaic energy systems.
- IEC 60947-3:2020 (edition 4), switches and disconnectors, utilization categories DC-PV1 and DC-PV2.
- IEC 61643-31:2018, surge protective devices for photovoltaic installations.
- NFPA 70-2017, sections 690.8(A)(1), 690.8(B) and 690.9(B).
Frequently asked questions
What is a solar combiner box?
It is the enclosure where the outputs of several PV strings are paralleled before being carried to the inverter in a larger cable. It houses the protection of each string, the positive and negative busbars, the DC disconnect switch and sometimes the surge protection and monitoring.
When does each string need a fuse?
When the reverse current that can flow through a faulted string exceeds what the module withstands. That reverse current is (N − 1) times the module short-circuit current, with N strings in parallel, and it is compared with the maximum series fuse stated on the module data sheet. This is the IEC 62548 criterion.
Which standards cover combiner boxes?
IEC 62548-1:2023 gives the design requirements for PV arrays, including the marking of array and string combiner boxes. Fuses are specified under IEC 60269-6, disconnect switches under IEC 60947-3 and DC surge protective devices under IEC 61643-31.