The interconnection panel of a small-scale self-generator is the point where the inverter output joins the user's installation and the grid. It holds a dedicated inverter breaker, surge protection, the bidirectional meter when surplus is exported and the labels that NFPA 70 section 705 requires. Its design starts from the inverter current and from the rating of the existing busbar.
The interconnection panel is where the inverter output of a small-scale self-generator joins the user’s installation. It is one variant of types of electrical panels; on the DC side there is the solar combiner panel, and export metering is resolved in a revenue metering point panel.
Short answer
An interconnection panel gathers, at low voltage, the dedicated inverter breaker, the surge protection, the bidirectional meter if there is export, the labeling of the sources and the earthing. Two calculations govern the design: the inverter breaker (125 % of its rated output current) and the busbar check (NFPA 70 section 705.12, with its 120 % rule).
What it contains
- Inverter breaker, dedicated and labeled, which also serves as the disconnecting means of that source. With several inverters, one per inverter or one per group.
- Busbar or connection point inside the existing panel or in a new interconnection panel.
- AC surge protective device, coordinated with those on the DC side and at the service entrance. See coordinated SPDs.
- Bidirectional meter when surplus is exported.
- Directory or label showing the location of all source disconnecting means (section 705.10).
- Connection to the earthing grid of the installation.
- Spare space and enclosure with the IP rating the site needs; see IP rating of a panel.
Loss-of-grid (anti-islanding) protection normally sits in the inverter, which must meet the PV inverter standards; they are listed in PV inverter standards. Section 705.40 of NFPA 70 requires the source to disconnect automatically from all grid conductors when the grid is lost and not to reconnect until it is restored.
- Does the system export surplus to the grid?
- Yes: Inverter breaker, bidirectional meter and export agreement with the utility
- Yes: Load-side connection with a dedicated breaker
- No: Replace the panel, downrate the main breaker or connect on the supply side
- No: Inverter breaker and a control that prevents export (zero export)
- Yes: Inverter breaker, bidirectional meter and export agreement with the utility
Worked example
A three-phase 80 kW inverter at 400 V is connected to a panel with a 600 A busbar and a 400 A main breaker.
- Inverter output current. I = 80,000 / (√3 × 400) = 115.5 A.
- Inverter breaker. 125 % of the rated current: 1.25 × 115.5 = 144.3 A. The next standard size up is 150 A.
- 120 % busbar rule (NFPA 70-2017, 705.12(B)(2)(3)(b)):
- Sum: 144.3 A (125 % of the inverter) + 400 A (main breaker) = 544 A.
- Limit: 120 % × 600 A = 720 A.
- 544 A ≤ 720 A: it complies, with the inverter breaker at the end of the busbar opposite the main breaker.
- If the busbar were 400 A. Limit: 1.2 × 400 = 480 A; the sum, 544 A, exceeds it. It does not comply. The ways out are: replace the panel with one of a larger busbar, downrate the main breaker if the load allows, or connect on the supply side, with its own disconnect and utility agreement.
Short circuit and protection
The inverter breaker protects the cable between the inverter and the busbar, and its breaking capacity must cover the short-circuit current available at the panel, which is dominated by the network. The inverter itself contributes only a small multiple of its rated current, but the busbar and the breakers must still be rated for the network contribution. The inverter breaker is part of the busbar check: it cannot be replaced by a larger one without repeating that check.
What the panel must not do
- Hide the second source. Everyone who opens the panel must see, on the label, that it has two sources and where each disconnect is.
- Let the inverter breaker be moved. In the 120 % rule the position of the breaker is part of the compliance; a permanent label states it.
- Share the neutral or the earth path in a way that defeats the earth-fault protection already installed in the building.
- Use breakers not rated for back-feed at terminals that can now receive current from the inverter side.
Common mistakes
- Sizing the breaker with the nominal inverter current instead of 125 % of it.
- Connecting the inverter in the first free slot next to the main breaker.
- Forgetting the voltage drop between inverter and panel on long runs.
- Leaving the AC surge protection out because the DC side already has it.
- Not documenting the busbar check, which the utility or inspector asks for.
Checklist
- Rated output current of the inverter, from the data sheet.
- Inverter breaker at 125 % of that current, with breaking capacity for the available short circuit.
- Busbar checked against one of the 705.12(B)(2)(3) options, with the values documented.
- Inverter breaker in the position the chosen option requires, with a label forbidding relocation.
- Breakers suitable for back-feed at points that receive current through their load terminals.
- Voltage drop from the inverter to the connection point within the limit set by the applicable code.
- Bidirectional metering and seals if there is export.
- Directory of disconnecting means at the service entrance and at each source.
- Coordinated SPDs and earthing bonded to the existing grid.
- Design drawings and calculation report for the connection study.
How we help
We design interconnection panels remotely, worldwide: inverter breaker, busbar check, single-line diagram and bill of materials, adapted to the local code and the utility requirements you give us. See our primary engineering service and write to us with the inverter power and the existing panel.
Related guides
- Types of electrical panels: which one to choose for your load
- Solar DC combiner box
- Revenue metering point panel
- Surge protection in PV systems
References
- NFPA 70-2017, section 705 (705.10, 705.12 and 705.40). The current edition of NFPA 70 is 2026.
- IEC 62109 and IEC 62116, safety and anti-islanding of PV inverters.
Frequently asked questions
What does an interconnection panel for a small generator contain?
A dedicated breaker for the inverter output, sized at 125 % of its rated current; an AC surge protective device; the bidirectional meter if surplus is exported; the labeling of the sources and their disconnecting means; and the connection to the system earth bar.
How is it checked that the panel busbar can take the inverter?
With one of the options of NFPA 70-2017 section 705.12(B)(2)(3). In the 120 % rule, the sum of 125 % of the inverter current and the breaker that protects the busbar must not exceed 120 % of the busbar rating, with the inverter breaker at the end of the busbar opposite the supply.
Does the panel of a self-generator need a bidirectional meter?
If the system exports surplus to the grid, yes: the metering must record the energy flowing in and out separately. The meter requirements depend on the type of point and the utility.