In indirect metering the meter receives voltage and current from the secondaries of voltage and current transformers. The panel brings together those secondaries, the test block and the meter. Two checks define the design: the ratio and class of the transformers, and the voltage drop in the secondary wiring, which must stay a small fraction of the secondary voltage.
Indirect metering is the connection in which the meter sees neither the voltage nor the current of the network, only those of the secondaries of voltage transformers (VTs) and current transformers (CTs). It is the usual solution at medium voltage. It is one variant of types of electrical panels. If only the current needs transformers, see the semi-direct metering panel.
Short answer
In indirect metering the meter takes its voltage from voltage transformers and its current from current transformers. The panel holds the meter, a test block and the secondary wiring; at medium voltage the transformers usually sit in the switchgear and the panel is some distance away. Two checks define the design: the ratio and class of the transformers must match the accuracy level of the point, and the voltage drop between the VTs and the meter must stay very small.
What the panel contains
- Three-element meter, measuring each phase with its own voltage and current, of the class the point requires. See energy meter and multifunction meter.
- Test block to isolate the meter, short-circuit the CT secondaries and open the VT circuits.
- Protection of the voltage circuits, with fuses or a miniature breaker in each phase of the meter circuit.
- Marked and protected wiring on the most direct route, with as few connections and joints as possible.
- Tamper-resistant enclosure against weather, handling and physical damage, with seals.
- Backup meter where the point requires it, receiving the same voltage and current signals as the main meter.
- Communications for remote reading.
The transformers themselves are covered in current transformer and voltage transformer; their classes in accuracy classes of a metering CT and of a metering VT.
Design rules for the assembly
| Item | Rule |
|---|---|
| VT primary voltage | Equal to the nominal voltage of the metering point |
| Meter voltage | Equal to the VT secondary voltage |
| Windings | Metering windings dedicated to the meters where accuracy is critical |
| Burden | VTs and CTs operate within their rated burden, cables included, to keep their class |
| Three elements | Three VTs and three CTs at transmission voltage levels |
| Voltage drop | Calculated for the real cable length and kept in the file |
| Test block | Always, to allow on-site checks without interrupting supply |
Worked example
An industrial plant connects at 13.2 kV, with a 1.5 MVA transformer and a demand of 1.2 MW at power factor 0.95.
- Line current. I = 1,200 / (√3 × 13.2 × 0.95) = 55.2 A.
- CT ratio. A 50/5 CT is below the demand. Choose 75/5: the load sits at 74 % of the rated primary current.
- VT ratio. With three VTs connected phase to ground: 13,200/√3 V to 120/√3 V, ratio 110.
- Voltage drop of the wiring. The meter is 20 m from the VTs, with 2.5 mm² copper cable.
- Loop resistance = 0.0172 × (2 × 20) / 2.5 = 0.275 Ω.
- Voltage per phase at the meter: 120/√3 = 69.3 V.
- If the meter voltage circuit draws 1 VA per phase (from the meter data sheet), the current is 1 / 69.3 = 0.0144 A.
- Drop = 0.275 × 0.0144 = 0.004 V, which is 0.006 % of 69.3 V.
- Maximum distance. 0.1 % of 69.3 V is 0.069 V. With the same current, the permitted loop resistance is 0.069 / 0.0144 = 4.8 Ω, equivalent to about 350 m of 2.5 mm² cable.
The relative drop is the magnitude part of the error; the phase error must be included as well when the calculation is documented. If more burden is on the circuit, for example a backup meter, the current rises and the permitted distance falls.
Common mistakes
- Long, thin voltage circuit that uses up the voltage-drop margin.
- Sharing the metering winding with other equipment beyond metering purposes.
- Open CT secondary when the meter is opened without short-circuiting first.
- Oversized CT, working at very low current and losing accuracy.
- Meter with a nominal voltage different from the VT secondary.
- Metering point far from the connection point, which adds losses that must be compensated.
Checklist
- Accuracy level and classes (meter, CT and VT) defined.
- VT primary voltage equal to the nominal voltage of the point.
- CT ratio with the projected demand in the useful range.
- Dedicated metering windings.
- Voltage drop calculated with the real length and filed.
- Test block with seals, and protected voltage circuits.
- Backup meter when the point requires it.
- Product and calibration certificates for meter, CTs and VTs.
How we help
We design indirect metering panels remotely, worldwide: transformer selection, voltage-drop calculation, test block and wiring layout, adapted to the local code and the utility requirements you give us. See our primary engineering service and write to us with the voltage, the demand and the connection point.
Related guides
- Types of electrical panels: which one to choose for your load
- Semi-direct metering panel
- Revenue metering point panel
- Steps of an automatic capacitor bank
- Voltage transformer
- Accuracy classes of a voltage transformer for metering
References
- IEC 61869-2:2012, instrument transformers: additional requirements for current transformers.
- IEC 61869-3:2011, additional requirements for inductive voltage transformers.
- IEC 62053-22:2020, static meters for AC active energy (classes 0.1S, 0.2S and 0.5S).
Frequently asked questions
When is indirect metering used?
When the point voltage is medium or high and the meter cannot be connected directly. Voltage transformers reduce the voltage to a standard value (for example 120 V) and current transformers reduce the current to 5 A or 1 A. At transmission levels the meter is normally fed by three voltage and three current transformers.
What wiring error does indirect metering allow?
The limit comes from the metering rules or the contract that apply to the point; a drop of 0.1 % of the secondary voltage or less between the voltage transformer and the meter is a strict design target, and the calculation is kept in the metering file. It is computed from the loop resistance and the burden of the meter voltage circuit.
Can metering transformers also feed the protection?
It is better not to. Where accuracy matters, the metering windings are dedicated to the meters and the protection uses other windings or other transformers, so a protection burden never degrades the class of the meter.