Tiza Group

Home / Guides / Equipment, switchboards and substations

Semi-Direct Metering Panel: CTs, Test Block and Class

What a semi-direct metering panel contains: current transformers, test block, seals and accuracy class, with a worked CT ratio and burden example.

By Shadai García, CEO and protection engineer at Tiza Group.

utility gridboundaryVTCTmainbackupmeter data managercustomerloadbank=~solarquadrant I: imports P and Qbank switched in: quadrant IVthe solar plant exports: quadrant IIexports with the bank: quadrant IIIdaily reading to the meter data managerPQIIIIIIIVimportsexportskWhimpkWhexpkvarhimpkvarhexplogsmain and backup record the sameboth are read and comparedIEC 61850TCTRTVTRMMXUMMTR© tizagrp.comutility gridboundaryVTCTmainbackupmeter data managercustomerloadbank=~solarquadrant I: imports P and Qbank switched in: quadrant IVthe solar plant exports: quadrant IIexports with the bank: quadrant IIIdaily reading to the meter data managerPQIIIIIIIVimportsexportskWhimpkWhexpkvarhimpkvarhexplogsmain and backup record the sameboth are read and comparedIEC 61850TCTRTVTRMMXUMMTR© tizagrp.com
Energy meter at the commercial boundary: measuring CT and PT, main and backup, four quadrants. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

In semi-direct metering the meter takes the voltage directly from the network and the current through current transformers. The panel brings together those transformers, the test block, the meter and the seals. The accuracy class of meter and CTs follows the accuracy level the metering point requires, and the CT burden must be checked against the cable length.

Semi-direct metering is used when the installation current is too large to pass through the meter, but the voltage does not call for transformers. It is one variant of types of electrical panels. If the voltage also needs transformers, the case is the indirect metering panel.

Short answer

In semi-direct metering the meter takes the voltage directly from the network and the current from current transformers (CTs) installed on the phases. The panel holds the CTs, a test block, the meter, marked wiring and seal points. The meter and CT classes follow the accuracy level required at the metering point.

The three connections

ConnectionVoltage seen by the meterCurrent seen by the meter
DirectThat of the loadThat of the load
Semi-directThat of the loadSecondary of current transformers
IndirectSecondary of voltage transformersSecondary of current transformers
Which metering connection does the point need
  • Does the load current pass directly through the meter?
    • Yes: Direct metering, no transformers
    • No: Is the point at low voltage and does the meter accept that voltage directly?
      • Yes: Semi-direct metering with current transformers and a test block
      • No: Indirect metering with current and voltage transformers

What the panel contains

  • Current transformers, one per phase, with their ratio and accuracy class. They are covered in current transformer and accuracy classes of a metering CT.
  • Test block, which isolates the meter, short-circuits the CT secondaries and connects a reference meter without interrupting supply.
  • Meter for active energy (and reactive if required), of the right class; see energy meter and multifunction meter.
  • Tamper-resistant enclosure protecting the equipment against weather, handling and physical damage, with marked and protected wiring.
  • Seals on the sensitive elements: meter, CTs and test block.
  • Communications for remote reading, if the point requires it.

The secondary of a CT must never be left open under load: it develops dangerous voltages and damages the transformer. That is why the test block short-circuits the secondaries first and only then opens the meter. Terminals and their marking are covered in terminals and secondaries of the current transformer.

Accuracy class

The classes come from the accuracy level of the metering point. The meter classes (0.2S, 0.5S) are defined in IEC 62053-22:2020 and the CT classes in IEC 61869-2:2012. The table below shows a typical pairing:

Billing accuracy levelActive energy meterCT
High0.2S0.2S
Medium0.5S0.5S

Worked example

An installation at 400 V has a demand of 250 kW at power factor 0.9.

  1. Line current: I = 250,000 / (√3 × 400 × 0.9) = 401 A.
  2. CT ratio: a 400/5 CT would be at its limit with no margin. Choose 500/5: at 401 A the secondary delivers 4.0 A.
  3. Secondary burden with a 6 mm² copper cable, 6 m from the CTs to the meter:
    • Loop resistance = 0.0172 × (2 × 6) / 6 = 0.034 Ω.
    • Cable loss at 5 A: 0.034 × 25 = 0.86 VA.
    • If the meter draws, for example, 0.5 VA per phase (from the data sheet of the chosen meter), the total burden is about 1.4 VA.
  4. The total burden must stay inside the rated burden range of the CT, which its data sheet sets and under which it guarantees its class.
  5. With a 1 A secondary the same cable loses 0.034 × 1 = 0.034 VA, 25 times less. A 1 A secondary is therefore the better choice when the meter is far from the CTs.

Where the measurement is taken

The metering point should be at the point where the supply is delivered, so that the meter records what the user receives or exports without having to correct for transformer or cable losses. When the user owns a transformer and the energy is delivered on its high-voltage side, the metering moves there and the case is normally indirect metering at medium voltage. Semi-direct metering at low voltage fits installations whose delivery point is on the low-voltage side, for example when the transformer belongs to the utility.

Common mistakes

  • CT too small for the demand, which saturates or overheats at peak load.
  • CT too large, which works at a very small fraction of its rated current and loses accuracy at light load.
  • Secondary left open when the meter is removed without first shorting the CTs on the test block.
  • Long secondary runs with 5 A CTs, which add burden and push the CT out of its class; a 1 A secondary or a larger cross-section fixes it.
  • Unmarked wiring and no seal points, which make later checks and audits slow.
  • Phase sequence or polarity errors between CTs and voltage taps, which make the meter read wrong or even negative power; they are found by a phase check at commissioning.

Checklist

  • Metering point accuracy level confirmed with the utility or the contract.
  • Meter and CT classes that match it.
  • CT ratio so that the demand sits inside the current range of the class, without overload.
  • Secondary burden calculated with the real cable length.
  • Test block with seal points.
  • Wiring marked, with the correct cross-section and a direct route.
  • Enclosure with a degree of protection suited to the site.
  • Product certificates and calibration reports before commissioning.
  • Utility construction standard reviewed before assembly.

How we help

We design semi-direct metering panels remotely, worldwide: CT selection, burden calculation, test block and enclosure layout, adapted to the local code and the utility requirements you give us. See our primary engineering service and write to us with the demand and the connection point.

References

  • IEC 61869-2:2012, instrument transformers: additional requirements for current transformers.
  • IEC 62053-22:2020, static meters for AC active energy (classes 0.1S, 0.2S and 0.5S).

Frequently asked questions

What is semi-direct metering?

It is the connection in which the meter receives the voltage directly from the network, as the load does, and the current from the secondary windings of current transformers. It is used when the current is too high to pass straight through the meter.

Does a semi-direct metering panel need a test block?

Yes, in practice. A test block lets the meter be isolated or replaced without interrupting supply, short-circuits the CT secondaries safely before the meter is opened, and allows a reference meter to be connected for on-site checks.

Which accuracy class does a semi-direct metering panel use?

It depends on the accuracy level the metering point requires. For billing-grade measurement the usual choice is a class 0.5S or 0.2S meter under IEC 62053-22 with class S current transformers under IEC 61869-2; the class is fixed by the utility or the energy contract.

WhatsApp