AEMO asks for plant models in two stages. The R1 package goes in with the connection application and no later than three months before commissioning. The R2 package updates it with measured data within three months after commissioning tests. Between them, AEMO runs a dynamic model acceptance test on the PSS/E and PSCAD models. Passing it does not show the plant meets its performance standards.
AEMO asks for the plant model twice: an R1 submission before connection and an R2 submission after commissioning. In between, it checks the models with a dynamic model acceptance test (DMAT). The wider framework is in the Australia electrical codes and grid connection guide.
Short answer
R1 is the model and data package that goes to AEMO and the network service provider (NSP) with the connection application, and in any case no later than three months before commissioning. R2 updates it within three months after the commissioning tests, with data checked against measurements. The DMAT is AEMO’s test of the models themselves. It does not test whether the plant meets its performance standards.
The two submissions
Clause S5.2.4 of the National Electricity Rules (NER) sets the information a plant must provide. It applies to a production system of 30 MW or more, or a synchronous condenser system of 30 MVA or more. The information is due by the earlier of the connection application, the submission of amended performance standards, or three months before commissioning.
- R1. The package includes information on the protection and control systems: functional block diagrams, the parameters of each block, the non-linear elements and encrypted models for the software AEMO names. AEMO also gets the model source code where the Power System Model Guidelines require it. A releasable user guide goes to AEMO and the NSPs.
- R2. The participant updates the information within 3 months after commissioning tests are completed. It must also update it when it learns the information is incomplete, inaccurate or out of date, or when AEMO or the NSP asks.
The model content is explained in the AEMO model guidelines guide. The control tuning in R1 must match the range of fault levels and system impedance the NSP gives for the connection point, and the releasable user guide records the levels used.
What AEMO tests: the DMAT
AEMO’s Dynamic Model Acceptance Test Guideline (version 3.0, effective 3 June 2024) explains how AEMO assesses models before accepting them for system studies, connection applications, registration and plant alterations. The tests apply to the positive-sequence PSS/E model and to the PSCAD/EMTDC model. The objectives include:
- Robustness of the model across defined limits of system strength.
- Consistency between the two models, and with the manufacturer’s validation.
- Documentation that meets the Rules and the Power System Model Guidelines.
The guideline also lists the documents required. They include the compiled models, source code, block diagrams, complete parameter lists, set-up instructions and validation reports on fault ride-through for inverter-based plant. A model delivered as a black box is not acceptable. The guideline asks for the minimum short circuit ratio the equipment can sustain to be stated and shown by test, defined at the equipment terminals. Test groups include balanced and unbalanced faults, voltage and frequency disturbances, set-point steps and abrupt voltage angle changes. Those groups run at low and high short circuit ratios and at different X/R ratios. The guide on PSS/E and PSCAD models gives more detail on those families.
In the guideline’s pathway, the proponent or the NSP, as agreed, does the initial screening of the single machine infinite bus tests, and AEMO does the final assessment and acceptance. The NSP screens the PSCAD wide-area network model, and AEMO accepts it.
AEMO is explicit about limits. Model acceptance does not assess compliance with access standards, and does not show that the models will meet compliance requirements for a project. The R2 validation and ongoing compliance obligations still apply.
Worked example (illustrative)
These values are illustrative. A 120 MW solar farm plans commissioning on 1 September 2027. The commissioning tests finish on 15 September 2027.
Timeline
- R1 deadline, if the application is later than that: three months before 1 September 2027 is 1 June 2027.
- R2 deadline: three months after 15 September 2027 is 15 December 2027.
Test count for the phase angle family. The guideline lists six grid voltage angle tests, and each covers four steps: +40, −40, +60 and −60 degrees.
- Step applications: 6 × 4 = 24.
Declared short circuit ratio. The manufacturer declares a lowest ratio of 2.0. AEMO’s guideline asks for a verification test at or below the declared limit, for example 5 % or 10 % lower.
- Fault level at the limit: 2.0 × 120 = 240 MVA.
- Test at 5 % lower: 1.9 × 120 = 228 MVA.
- Test at 10 % lower: 1.8 × 120 = 216 MVA.
Result. The plan must have the R1 package ready by 1 June 2027 at the latest, with models tested before they are submitted. The model validation work for R2 needs to be scheduled with the commissioning tests, so that the measurements exist by mid-September. The grid equivalents for the declared-limit tests are set at 228 and 216 MVA, below the 240 MVA of the declared ratio.
Figure: the sequence from application to registration, with the R1 package, the model acceptance test, the commissioning tests and the R2 package, and the data flows to AEMO and the NSP.
Checklist for the engineer
- List the R1 contents from S5.2.4 and the Power System Model Guidelines and assign an owner to each item.
- Confirm that the PSS/E and PSCAD models give consistent results for balanced events.
- Document the lowest short circuit ratio and the evidence that supports it.
- Ask the NSP for the fault level range and X/R ratios in writing, and record them in the user guide.
- Plan the commissioning tests so that they give the measurements R2 needs.
- Keep the version of AEMO’s guideline that applies in the project file.
- Update the models whenever settings or equipment change.
Next step
Tiza prepares model packages, benchmarking between PSS/E and PSCAD, and the validation reports that support R1 and R2. Tiza does not stamp, sign or certify: it delivers studies and engineering ready for your RPEQ in Queensland, or your registered or chartered engineer in other states, to review and certify. Contact us with the plant data and the connection stage.
Related guides
See the GPS compliance demonstration plan, AEMO system strength requirements and SCR studies, short circuit models and fault level requirements and EMT study models.
Frequently asked questions
What is the difference between R1 and R2 submissions?
R1 is the model and data package supplied before connection. R2 is the update that follows commissioning tests, validated against measurements from the plant. Clause S5.2.4 sets the timing for both.
Does passing model acceptance testing show compliance?
No. AEMO states that the acceptance tests do not assess compliance with performance or access standards, and that acceptance does not mean the models will meet the compliance requirements of a given project.
Who runs the tests?
The proponent or the network service provider, as agreed, does the initial screening of the single machine infinite bus tests, and AEMO does the final assessment and acceptance. AEMO also runs the wide-area network tests.