IEC 61850 to IEC 104 and DNP3 mapping in the gateway

How a gateway translates IEC 61850 to IEC 60870-5-104 and DNP3: logical nodes to addresses, quality, time tags, SBO commands and what gets lost.

By Shadai García, electrical engineer, founder and CEO of Tiza Group. Reviewed by the Tiza Group engineering team · .

IEDgatewaycontrol centerXCBR1.PosstVal · q · truleCA + IOAdouble + time tagPos.stValIOA 1001SBO commandC_DC_TA_1: selectCSWI1.Pos: SBOwC_DC_TA_1: executeCSWI1.Pos: OperIEC 61850IEC 104XCBR1 in its LDCA + IOA 1001Pos.stValDPI (double)Pos.qDIQ qualityPos.tCP56Time2aCSWI1.Pos SBOC_DC_TA_1 S/EM_DP_TB_1: double point with time tagMappingLN/DORuleIOAASDU© tizagrp.comIEDgatewaycontrol centerXCBR1.PosstVal · q · truleCA + IOAdouble + time tagPos.stValIOA 1001SBO commandC_DC_TA_1: selectCSWI1.Pos: SBOwC_DC_TA_1: executeCSWI1.Pos: OperIEC 61850IEC 104XCBR1 in its LDCA + IOA 1001Pos.stValDPI (double)Pos.qDIQ qualityPos.tCP56Time2aCSWI1.Pos SBOC_DC_TA_1 S/EM_DP_TB_1: double point with time tagMappingLN/DORuleIOAASDU© tizagrp.com
IEC 61850 to IEC 104 mapping: from the LN attribute to the IOA, and the command back. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

The substation gateway reads IED data over IEC 61850 and delivers it to the control center over IEC 60870-5-104 or DNP3. Along the way, each data point changes its name (from logical node and attribute to a numeric address), its type, its quality format and its time tag, and select-before-operate commands are translated from one model to the other. IEC TS 61850-80-1 and IEEE 1815.1 give the reference rules.

What the gateway does

Inside the substation, the IEDs speak IEC 61850: each data point has a hierarchical name (logical device, logical node, data object and attribute), detailed quality and a time tag. The control center, on the other hand, usually speaks IEC 60870-5-104 or DNP3 (IEEE 1815), where each data point is a numeric address of a defined type.

The gateway or RTU sits in between. It is an MMS client of the IEDs, receives their reports and publishes them as an IEC 104 server or a DNP3 outstation. For each signal it keeps a mapping rule: where it comes from, which address it goes to, with which type and with what handling of quality and time.

The data point changes its name at each hop

An example with the position of a breaker:

HopWhat the data point is called
IED (IEC 61850)Position of logical node XCBR or CSWI, data object Pos, attribute stVal, with its quality q and time tag t
GatewayInternal rule: MMS source, destination IOA and type
Control center (IEC 104)ASDU common address + information object address (IOA), double-point type with time tag
Control center (DNP3)Double-bit binary input object, with its index and event class

IEC 61850 names are self-describing: an engineer reads the path and knows what it is. IEC 104 and DNP3 addresses say nothing by themselves: their meaning lives in the signal list agreed with the control center.

Data type

  • Single and double points. A breaker position is a double point in both worlds (open, closed, intermediate, invalid). An alarm is a single point.
  • Measurands. In IEC 61850 they are analog values with scale and unit; in IEC 104 you choose between normalized, scaled or floating-point values, and in DNP3 among the analog input variations. The choice affects resolution and deadband.
  • Counters. Energy and operation counts are mapped as integrated totals.
  • With or without a time tag. IEC 104 has types with a time tag (CP56Time2a, seven octets) and without one. Types with a time tag are used for events the operator must put in order.

Quality

IEC 61850 reports quality with validity (good, invalid, questionable), details (overflow, out of range, failure, oscillatory, inconsistent) and source (process or substituted), plus the test and operator-blocked flags. IEC 104 has a shorter quality descriptor (invalid, not topical, substituted, blocked, overflow) and DNP3 has its flags (online, restart, communication lost, local or remote forced, among others).

The gateway decides how each combination is translated. Two decisions matter:

  • What happens if the IED stops communicating. The right behavior is for the gateway to flag that IED’s signals as not topical or communication lost, so the operator does not see an old state as valid.
  • What happens with a data point in test mode. A data point flagged as test in IEC 61850 must not reach the control center as if it were real.

Time tag

The time tag should come from the IED that detected the change, not from the gateway that forwarded it. If the gateway applies its own time, the sequence of events loses accuracy. The time zone also matters, as does the IED, gateway and control center sharing the same time source.

Commands

In IEC 61850, each controllable object has a control model: direct operate or select before operate (SBO), with normal or enhanced security. In IEC 104, the command carries a qualifier that distinguishes select from execute, and the response comes back with the activation confirmation and activation termination causes of transmission. In DNP3, select and operate are function codes 3 and 4, with direct operate as an alternative.

The gateway translates each step:

Select-before-operate command through the gateway
  1. 01Select in IEC 104 or DNP3The control center selects the object
  2. 02Select in IEC 61850The gateway selects the object in the IED
  3. 03ConfirmationThe IED accepts and the gateway confirms to the control center
  4. 04ExecuteThe control center issues the order and the gateway sends Operate
  5. 05TerminationThe IED reports the result and the gateway closes the command

If the IED rejects the command because of an interlock, local mode or the maximum time between select and execute, the gateway must carry that rejection to the control center with the right cause. A command rejected without explanation is one of the most common faults: see command rejected from SCADA.

What is lost in translation

  • The self-describing name: in IEC 104 and DNP3 only an address remains.
  • Part of the quality: IEC 61850 details are summarized in a few bits.
  • The IED mode and behavior (on, blocked, test), unless they are mapped as additional signals.
  • Time resolution, when the time tag moves to a millisecond format.
  • The structure: a logical node with several data objects becomes a flat list of addresses.

Mapping references

  • IEC TS 61850-80-1, Edition 2 of 2016: guidance for exchanging IEC 61850 model information over IEC 60870-5-101 and 104, with a focus on the gateway. A third edition is in development.
  • IEEE 1815.1-2015: information exchange between IEC 61850 and DNP3 networks, in both directions, including the gateway architecture and the description of the mapping in SCL and in the DNP3 device profile.

These standards give the general rules. The actual table for each project is set by the utility or the owner of the control center.

Gateway configuration with Tiza Group

Mapping is where integration succeeds or fails: a badly translated quality or a gateway time tag in place of the relay’s goes unnoticed until the first real event. We configure IEDs, switches and gateways remotely through our remote relay and communications configuration service, with a backup before and after every change. Our team configures and tests gateways and RTUs against the control center’s signal list, with point-to-point tests, as part of our SCADA and gateway integration service, in medium-, high- and extra-high-voltage substations and industry, in Colombia, or elsewhere on request. You can review the reports and datasets in your SCD with our free IEC 61850 SCL viewer tool. Write to us with the protocol and the control center of your project.

References

  • IEC TS 61850-80-1:2016, guideline to exchanging information from a CDC-based data model using IEC 60870-5-101 or IEC 60870-5-104.
  • IEEE 1815.1-2015, Standard for Exchanging Information Between Networks Implementing IEC 61850 and IEEE Std 1815 (DNP3).
  • IEC 60870-5-104, Edition 2 of 2006 with its Amendment 1 of 2016.
  • IEEE 1815 (DNP3).
  • IEC 61850-7-2 and IEC 61850-8-1: services, control model and mapping to MMS.

Frequently asked questions

Is there a standard for mapping IEC 61850 to IEC 104?

Yes. IEC TS 61850-80-1, whose Edition 2 dates from 2016, gives guidance for carrying IEC 61850 model data over IEC 60870-5-101 and 104 links, mainly with the gateway in mind. For DNP3, the reference is IEEE 1815.1-2015. In practice, each utility also sets its own signal list and data types.

Why does the control center receive an event with a different time than the relay?

The usual causes are that the gateway forwards the data point with its own time instead of the IED's, that it uses a type without a time tag, or that the IED, gateway and control center have different time zones or time sources. Check the configured type, the source of the time tag and the synchronization of each device.

Does an IEC 61850 select-before-operate command arrive the same way in IEC 104?

The idea is the same, but the mechanics differ. In IEC 104, select and execute are two command messages with the corresponding qualifier; in IEC 61850, they are the Select and Operate services on the object's control model. The gateway must translate both steps and their responses, including a rejection.