IEC 61850 test tools: simulators and analyzers

Tools for IEC 61850 testing: MMS client, IED and GOOSE simulator, network analyzer, SCL validator and test set with GOOSE and Sampled Values.

By Shadai García, electrical engineer, founder and CEO of Tiza Group. Reviewed by the Tiza Group engineering team · .

publishersubscriberTAPmirror portanalyzercaptured GOOSE framessqNum + 1stNum + 1burstgap > TALstNum 4 · sqNum 7stNum 5 · sqNum 0stNum 5 · sqNum 5no frames: lossstNum 5 · sqNum 6the analyzer sees what reaches that portGridpublisherswitchmirroranalyzer© tizagrp.compublishersubscriberTAPmirror portanalyzercaptured GOOSE framessqNum + 1stNum + 1burstgap > TALstNum 4 · sqNum 7stNum 5 · sqNum 0stNum 5 · sqNum 5no frames: lossstNum 5 · sqNum 6the analyzer sees what reaches that portGridpublisherswitchmirroranalyzer© tizagrp.com
IEC 61850 traffic capture: mirror port, TAP and reading stNum, sqNum and TAL. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

Testing an IEC 61850 system takes several kinds of tool: an MMS client that browses the model of each IED and receives its reports, a simulator that publishes GOOSE or emulates a complete IED, a network analyzer that shows what really travels, an SCL file validator and a test set that publishes and subscribes to GOOSE and sampled values while it tests the protection.

Why dedicated tools are needed

In a substation with conventional wiring, a multimeter and a test set are enough to follow a signal from one end to the other. In an IEC 61850 substation the signal is a message: it cannot be measured with a multimeter, it cannot be seen on a terminal block, and it may be present on the network yet be discarded by the device receiving it. Testing it takes tools that speak the protocol, read the system configuration and show what happens on the network.

What has to be observed depends on the service: a GOOSE is checked differently from an MMS report, as explained in GOOSE vs MMS in IEC 61850. No tool does it all. The brands named here are examples; what matters is the type of tool and what it lets you verify.

Types of tool

TypeWhat it doesWhat it lets you verifyExamples
MMS clientConnects to an IED, browses its data model, reserves reports and sends commandsThat the IED exposes the expected data, that reports arrive and that commands are accepted or rejected correctlyOMICRON IEDScout; client of Triangle MicroWorks 61850 Test Suite Pro
IED or GOOSE simulatorPublishes GOOSE or emulates the complete communication of an IED from its SCL fileThe subscriber’s reaction without the real publisher; HMI and gateway integration before all devices are availableIEDScout; simulator of 61850 Test Suite Pro
Network analyzerCaptures and decodes trafficWhether the message exists, with which parameters and timingWireshark; manufacturers’ own analyzers
SCL validatorChecks the syntax and consistency of the filesErrors in ICD, SCD or CID before loading themValidators of the engineering tools; SCL viewers
Test set with IEC 61850Injects currents and voltages, subscribes to the trip GOOSE, publishes GOOSE and, in a digital substation, sampled valuesProtection operating times when inputs or outputs are messagesTest sets of the main brands with the IEC 61850 option
IEC 61850 network supervisionContinuously compares what is circulating with what the SCD says should circulateLost messages, changed configurations, devices that stop publishingManufacturers’ diagnostic tools, such as Hitachi Energy ITT600

MMS client

It is the most used tool when commissioning the station bus. It shows the model of an IED as loaded, without depending on the HMI, so it can be compared with the specification. With it you reserve a report control block to check which events the device sends, test a select-before-operate command and read the quality of each data item. It also downloads fault records. How MMS works is covered in IEC 61850 MMS.

One precaution: the test client takes up a report control block of the IED. If the HMI or the gateway needs that same block, they will stop receiving data while the test client stays connected.

GOOSE and IED simulator

A simulator reads the SCD and publishes the messages of an IED that is not present, or emulates the MMS response of a complete device. It is useful in three situations: the FAT of an HMI or gateway without all the IEDs, testing a subscriber without its publisher, and extensions, where the part in service cannot be touched. The simulated message must carry the same parameters as the real one; otherwise the subscriber will discard it.

In IEC 61850 Edition 2, simulated messages are flagged with their own bit, and the subscriber only accepts them if it is in simulation mode. That mechanism, and the test mode of the IEDs, are covered in IEC 61850 test and simulation mode.

Network analyzer

The analyzer does not intervene: it only shows. That is why it is the reference when two devices contradict each other. A capture tells whether the GOOSE exists, with which VLAN, APPID, configuration revision and time allowed to live, and whether stNum changes when it should. For MMS it shows associations, reports and retransmissions. Capturing requires a switch mirror port or a TAP, and the clock of the capturing device should be synchronized. All of that is in IEC 61850 traffic in Wireshark.

SCL validator and viewer

Many problems can be caught before going to the field by reviewing the SCD: IEDs without an address, GOOSE without subscribers, subscriptions to data that do not exist, mixed editions. That file is produced by the system configurator, and it is the starting point when there is GOOSE between relays of different brands. You can open an SCD and review its IEDs, subnetworks, GOOSE and SV streams with our free IEC 61850 SCL viewer, with no installation.

Test set with IEC 61850

When the relay trips over GOOSE, as described in protection testing with GOOSE, the test set subscribes to that message and treats it as a binary input: that way it measures the operating time just as with a contact. When the relay expects GOOSE from other devices, the same test set publishes them. In a digital substation it also publishes the sampled values that replace the CT and VT secondaries. Secondary injection remains the basis; what changes is where the signals enter and leave.

Which tool at each stage

IEC 61850 tools by project stage
  1. 01EngineeringSCL validator and viewer on the SCD before loading it
  2. 02FATMMS client and simulator for the HMI and the gateway; test set for the protection
  3. 03SAT and commissioningMMS client signal by signal, network analyzer and test set with GOOSE
  4. 04OperationNetwork supervision and analyzer for communication failures

Common mistakes when testing

  • Testing with an SCD different from the one loaded. The tool shows what the file says, not what the IED has.
  • Forgetting to remove simulation. An IED left in simulation or test mode does not behave as in service.
  • Capturing without a mirror port and concluding that the message does not exist.
  • Testing only the normal case. Loss of the GOOSE, the rejected command and the link going down must be tested too.

We help you test your IEC 61850 system

At Tiza Group we test IEC 61850 systems at FAT, SAT and commissioning, with test sets, MMS clients and network analyzers, in substations and industry, in Colombia, or elsewhere on request. If the problem is in a relay’s configuration, remote relay configuration corrects it remotely. For testing of the complete system, see FAT and SAT testing.

References

  • IEC 61850-10, conformance testing.
  • IEC 61850-7-4, logical nodes LPHD and LLN0 (mode and simulation).
  • CIGRE, Technical Brochure 401, Functional Testing of IEC 61850 Based Systems, 2009.
  • CIGRE, Technical Brochure 760, Test strategy for Protection, Automation and Control (PAC) functions in a fully digital substation based on IEC 61850 applications, 2019.
  • OMICRON, IEDScout product information (omicronenergy.com and T&D World articles).
  • Triangle MicroWorks, 61850 Test Suite Pro documentation (trianglemicroworks.com).

Frequently asked questions

Is Wireshark enough to test IEC 61850?

To see what travels on the network, yes: it decodes GOOSE, SV and MMS. But it does not publish messages, reserve reports or send commands, and it does not automatically compare what it sees with the SCD. It is complemented by an MMS client and a simulator or test set.

Which tool is needed to test a relay that trips over GOOSE?

A secondary injection test set that subscribes to the relay's trip GOOSE and treats it as one more binary input, to measure the operating time. If the relay also receives GOOSE, the same test set or a simulator publishes the messages the relay expects.

Can the integration be tested without all the IEDs?

Yes. With the SCD file, a simulator can emulate the communication of the missing IEDs, publish their GOOSE and respond as an MMS server. It is useful at the FAT and in extensions, but it does not replace the final test with the real devices.