S5.2.5.13 Voltage and Reactive Power Control: NER Guide

What NER clause S5.2.5.13 asks of generator voltage and reactive power control: accuracy, setpoint range and settling times, with a worked setpoint case.

By Shadai García, CEO and protection engineer at Tiza Group.

132 kVCT800/1CVT, 110 Vplant controllerV, Q, PF modescontrol commandsNSP / AEMOSCADA=~inverters150 MW, 707 APowerMeasure / controlCommssetpoint 1.00 pu = 132 kV; 0.5 % = 0.66 kV1 Mvar moves 1 / 1,500 = 0.067 %60 Mvar gives 60 / 1,500 = 4.0 %: 96 to 104 %95 to 105 % needs 0.05 x 1,500 = 75 MvarQ mode: 2 % of 161.6 MVA = 3.2 Mvarrequested 95 to 105 % = 125.4 to 138.6 kVreachable with 60 Mvar: 96 to 104 %95100105 %needed: 0.05 x 1,500 = 75 Mvarplant capability 60 Mvarstiff-network estimateVoltageCVT inputCTPlant controllerInvertersSCADA© tizagrp.com132 kVCT800/1CVT, 110 Vplant controllerV, Q, PF modescontrol commandsNSP / AEMOSCADA=~inverters150 MW, 707 APowerMeasure / controlCommssetpoint 1.00 pu = 132 kV; 0.5 % = 0.66 kV1 Mvar moves 1 / 1,500 = 0.067 %60 Mvar gives 60 / 1,500 = 4.0 %: 96 to 104 %95 to 105 % needs 0.05 x 1,500 = 75 MvarQ mode: 2 % of 161.6 MVA = 3.2 Mvarrequested 95 to 105 % = 125.4 to 138.6 kVreachable with 60 Mvar: 96 to 104 %95100105 %needed: 0.05 x 1,500 = 75 Mvarplant capability 60 Mvarstiff-network estimateVoltageCVT inputCTPlant controllerInvertersSCADA© tizagrp.com
NER S5.2.5.13: a 132 kV connection with the plant controller fed by the CVT and an 800/1 CT on separate cores, the control commands to the inverters and the SCADA link to the network operator, with a 150 MW plant of 60 Mvar that reaches a voltage setpoint range of 96 to 104 percent instead of 95 to 105 percent. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Clause S5.2.5.13 of the National Electricity Rules sets how a generating system controls voltage, reactive power and power factor: voltage control as the main mode plus a power factor or reactive power mode, voltage held to within 0.5 percent of setpoint, defined settling times and damping, and, for synchronous plant, excitation and stabiliser requirements.

Clause S5.2.5.13 of the National Electricity Rules (NER) is titled “Voltage and reactive power control”. It is the longest clause in the series. It covers the plant’s whole voltage control system: modes, accuracy, speed, damping, limiters and, for synchronous plants, excitation and power system stabilisers. The Australian Energy Market Operator (AEMO) assesses it with root-mean-square (RMS) and electromagnetic transient (EMT) models. The plant controller reads current transformers (CTs) and voltage transformers (VTs). It takes setpoints through supervisory control and data acquisition (SCADA).

It is part of the generator performance standards (GPS) in the Australia electrical codes and grid connection guide.

Short answer

S5.2.5.13 requires voltage (droop) control as the main mode, unless the network service provider (NSP) says otherwise, plus a power factor or reactive power mode. Voltage is held to within 0.5 percent of a continuously adjustable setpoint. Responses settle within defined times, with no oscillation or hunting. The setpoint range is subject to the reactive power capability agreed under S5.2.5.1.

What the clause says, in plain words

  • Damping and stability. Oscillations are adequately damped. The plant does not degrade damping of a critical mode. It causes no instability, including tap changer hunting, that would affect other participants.
  • Monitoring and testing. The control systems have permanently installed recording of key variables, and facilities to test the control system dynamics.
  • Modes. Voltage (droop) control is the main mode unless the NSP says otherwise. The plant also offers one additional mode, power factor or reactive power control.
  • Voltage control. Voltage is regulated at the connection point or an agreed location to within 0.5 percent of the setpoint. The setpoint is continuously adjustable, subject to the reactive capability. Limiting devices must not trip the unit at the limits of its capability and must be coordinated with protection.
  • Synchronous plant. The excitation system has its own requirements, such as its ceiling and its response to a voltage step.
  • Settling and rise times. Table S5.2.1 sets the step responses. For a step inside the plant’s limits, the response settles within 5 s, or 7.5 s when a limiter acts. A rise time limit for reactive power also applies.
  • Stabiliser. A power system stabiliser or power oscillation damper with adjustable gain and time constants, washout filters, an output limiter and test facilities.
  • Reactive power or power factor mode. The quantity is held to within 2 percent of the plant’s maximum apparent power (Smax). The setpoint is continuously controllable across the capability range.

What the assessor asks for

AEMO and the NSP ask for a voltage control strategy. It includes the controlled point, with a single line diagram showing the CTs and capacitor voltage transformers (CVTs) the plant controller uses. It also includes the controller’s operating principles and responses, and block diagrams with delays, filters, gains and limiters. Hybrid plants need each control system and the communication delays between them. RMS and EMT models are both needed and benchmarked against each other, and the SCADA signal list that lets the NSP and AEMO change setpoints must be provided.

Voltage control also overlaps with protection. Limiters must be coordinated with the relays so the plant does not trip at the edge of its capability. The guide on the AVR and its testing procedure shows how a tap changer voltage regulator behaves, which matters for the hunting requirement.

Worked example (illustrative)

The numbers are illustrative. A 150 MW solar plant connects at 132 kV. The target voltage is 1.00 per unit, which is 132 kV. The fault level at the connection point is 1 500 MVA. The agreed reactive capability is 60 Mvar leading and lagging.

Step 1. Setpoint range requested. Assume the NSP asks for a setpoint range of 95 to 105 percent. 95 percent of 132 kV = 125.4 kV and 105 percent = 138.6 kV.

Step 2. Regulation accuracy. 0.5 percent of 132 kV = 0.66 kV. The controller must hold the connection point voltage within 0.66 kV of the setpoint in steady state.

Step 3. Voltage change per Mvar. A first estimate for a stiff network: the voltage change in per unit equals the reactive power change divided by the fault level. So 1 Mvar changes the voltage by 1 / 1 500 = 0.067 percent.

Step 4. What the full range needs. A 5 percent change in the setpoint needs 0.05 × 1 500 = 75 Mvar.

Step 5. Compare with capability. The plant has 60 Mvar. Its reachable range is 60 / 1 500 = 4.0 percent each way, so the setpoint range achievable without a tap changer is about 96 to 104 percent. The full 95 to 105 percent would need 75 Mvar.

Step 6. Reactive accuracy. Smax = √(150² + 60²) = 161.6 MVA. Two percent of it is 3.2 Mvar, the tolerance for reactive power mode.

Result. At this fault level, the plant meets the setpoint range only to about 96 to 104 percent. The options are to raise the reactive capability to 75 Mvar, or to agree the narrower range with the NSP. The studies must then show it is as close as practicable to the automatic standard. The estimate ignores the network X/R ratio and the plant’s own transformer, so the studies, not this formula, decide.

For the plant controller’s instrument transformers, the voltage reference comes from a 132 kV CVT with a 110 V line-to-line secondary. The current reference comes from an 800/1 A CT on the line feeder. At 161.6 MVA the line current is 161 600 / (1.732 × 132) = 707 A, inside the 800 A rating. Both go to the plant controller through separate measuring cores from those of the protection.

Checklist for the engineer

  • The controlled point and its measurement chain, with CT and VT or CVT ratios and classes.
  • Block diagrams of every control mode, with delays, filters and limiters.
  • Capability curve and the setpoint range it supports.
  • Step response studies in RMS and EMT for voltage, reactive power and power factor setpoints.
  • Small-signal studies of damping, and a stabiliser design if one is installed.
  • Limiter coordination with protection settings.
  • A SCADA signal list that lets setpoints and modes be set remotely.
  • Test plan for commissioning, including voltage and reactive power step tests.

Figure

Figure: single line of a 132 kV connection with the plant controller, the CVT and CT feeding it, the control commands to the inverters and the SCADA link to the network operator.

Next step

Tiza prepares voltage control studies and the documentation for the controller strategy, working remotely and in English. Tiza does not stamp, sign or certify: it delivers studies and engineering ready for review and certification by your RPEQ in Queensland, or by the registered engineer your state requires. Contact us with the plant data and the network fault levels.

See S5.2.5.12 on network capability, S5.2.5.14 on active power control and the PPC and SCADA cybersecurity guide.

Frequently asked questions

Which control modes must the plant offer?

Since 21 August 2025, the plant operates in voltage (droop) control mode unless the network service provider says otherwise. It must also offer one additional mode: power factor control or reactive power control.

How accurate must voltage control be?

Voltage is regulated at the connection point, or an agreed location, to within 0.5 percent of the setpoint. In reactive power or power factor mode, the tolerance is 2 percent of the plant's maximum apparent power.

Does the voltage setpoint range depend on reactive capability?

Yes. The setpoint must be continuously adjustable, but the range the plant can actually reach depends on the reactive power capability agreed under S5.2.5.1 and on the fault level. A plant with less reactive capability reaches a narrower range.