The burden of a voltage transformer is the sum of what the connected equipment consumes in volt-amperes, and it must stay within the range of its rated output (the example assumes 25% to 100%). The cable adds very little burden, but its voltage drop adds to the measurement error. In the example, 12 VA at 120 m with 2.5 mm² drops 0.63%; with 10 mm² it drops 0.16%.
Short answer
The burden of a voltage transformer (VT) is the sum, in volt-amperes (VA), of what the equipment connected to its secondary consumes plus what the cable consumes. It must stay within the range of the VT’s rated output in which the accuracy class holds; the example assumes 25% to 100%. Apart from the burden, the voltage drop in the cable must be checked, because it adds to the measurement error even though it barely increases the VA. The example below shows that 12 VA at 120 m with 2.5 mm² gives a drop of 0.63%, and that with 10 mm² it falls to 0.16%. General CT and VT selection is covered in CT and VT selection for a substation.
What makes up the burden
The burden of a VT is the sum of what each device takes from the secondary voltage:
- Energy meter or analyzer: its voltage circuit consumes a few VA per phase.
- Protection relays: the voltage inputs of a numerical relay consume a fraction of a VA; old electromechanical relays consume much more.
- Synchro-check, recorders and transducers: each adds its own consumption.
- Connecting cable: its resistance, going and returning, consumes a fraction of a VA and produces a voltage drop.
The consumption data come from each device’s datasheet. The burdens are added arithmetically: a simplification on the safe side, because different power factors make the vector sum somewhat smaller.
Rated output and accuracy range
The rated output of a VT is given in VA; the example assumes a power factor of 0.8 lagging and an accuracy range of 25% to 100% of that output (assumptions of the example). That is why there are two checks: that the burden does not exceed 100%, and that it does not fall below 25%. If it is too low, the VT’s rated output is lowered. Protection windings have their own classes; see 3P and 6P and measuring accuracy classes.
Worked example: 13.2 kV VT with a panel 120 m away
Assumptions of the example (calculation values, not from a real installation):
- 13.2 kV system; single-phase VT 13,200/√3 : 110/√3 V, class 0.5, rated output 25 VA.
- Secondary voltage per phase: 110 / √3 = 63.51 V.
- Consumption per phase: meter 2.5 VA, multifunction relay 1.0 VA, synchro-check 3.5 VA and recorder 5.0 VA.
- 120 m copper cable from the VT to the panel. Go-and-return loop: 240 m. Assumed resistivity: 0.022 Ω·mm²/m.
- Assumed drop limit for the metering circuit: 0.2%.
Step 1. Equipment burden. 2.5 + 1.0 + 3.5 + 5.0 = 12.0 VA.
Step 2. Secondary current. I = 12 / 63.51 = 0.189 A.
Step 3. Loop resistance with 2.5 mm². R = 0.022 × 240 / 2.5 = 2.112 Ω.
Step 4. Cable burden. I² × R = 0.189² × 2.112 = 0.075 VA. Negligible.
Step 5. Voltage drop. ΔV = I × R = 0.189 × 2.112 = 0.399 V. Relative to 63.51 V: 0.399 / 63.51 = 0.63%. It exceeds the 0.2% limit, so the 2.5 mm² cable does not work for this circuit even though the burden is right.
Step 6. Changing the section.
| Section | Loop resistance | Drop |
|---|---|---|
| 2.5 mm² | 2.112 Ω | 0.63% |
| 4 mm² | 1.320 Ω | 0.39% |
| 6 mm² | 0.880 Ω | 0.26% |
| 10 mm² | 0.528 Ω | 0.16% |
With 10 mm² the drop is 0.189 × 0.528 = 0.0998 V, that is, 0.157%, which complies.
Step 7. Total burden against rated output. With 10 mm² the cable adds 0.189² × 0.528 = 0.019 VA. The total burden is 12.02 VA. The range of class 0.5 with 25 VA runs from 6.25 VA (25%) to 25 VA (100%). The burden is at 48% and falls inside.
Reading. The equipment burden was right from the start. What decided the design was the drop in the cable, and it is solved with the section or by placing the equipment closer to the VT. With a 50 VA VT the burden would have been 24%, outside the range (12.02 / 50).
If the check fails
There are four ways out, in this order of preference. First, shorten or thicken the cable: it is the cheapest fix when the drop is what fails, as in the example. Second, split the equipment: revenue-metering devices go on their own circuit with their own cable, and protection and recording devices on another, so that an additional device does not degrade the measurement. Third, change the rated output: if the burden exceeds 100%, move to the next standard rating; if it falls below 25%, move down. Fourth, use an additional core or winding in the VT to separate functions, if the manufacturer offers it.
Each winding is checked separately: the measuring one with its class 0.5 and the protection one with 3P or 6P, each with its own equipment, cable and range. The sum of the burdens of both windings is not the relevant figure; what counts is the burden of each one against its own rated output.
Other checks on the VT
The VT primary is chosen with the system voltage and its insulation with the level that corresponds to that voltage; the medium-voltage inductive VT describes it. The maximum continuous voltage and the voltage factor depend on how the system is earthed, as explained in the rated voltage factor. The secondary is protected against short circuit with a miniature circuit breaker; see the short circuit on the secondary of a VT, because the breaker has its own resistance that also counts in the drop. The equivalent check for a current transformer is in CT selection: burden, ALF and saturation.
Checklist
- Equipment connected to each winding and its consumption in VA per phase.
- Real cable length, going and returning.
- Loop resistance with the chosen section.
- Cable voltage drop against the circuit limit.
- Total burden between 25% and 100% of rated output.
- Class of the measuring winding and of the protection winding.
- Secondary protection and its resistance included in the loop.
- Field check of the real burden with applied voltage.
Need this study?
We check the burden and drop of each voltage circuit using the real data of your equipment and cables and deliver the calculation report and the VT specification. We provide this engineering work for any country. See the engineering design and studies service and contact us.
Related guides
- CT and VT selection for a substation
- Accuracy classes of a measuring voltage transformer
- Classes 3P and 6P of a protection voltage transformer
- CT selection: burden, ALF and saturation with an example
- AC voltage drop in cables
- Short circuit on the secondary of a voltage transformer
References
- IEC 61869-3, instrument transformers: additional requirements for inductive voltage transformers.
Frequently asked questions
What is the burden of a voltage transformer?
It is the apparent power, in volt-amperes, consumed by the equipment connected to its secondary at rated voltage, cable included. It is compared with the VT's rated output: the accuracy of the class is only guaranteed within a range of that output; the example assumes 25% to 100%.
Why does the cable barely count in the burden but does count in accuracy?
Because modern equipment draws little current: the cable's power is the current squared times its resistance and comes out as a fraction of a volt-ampere. But that same current produces a drop in volts along the cable, and that drop adds to the VT's ratio error at the point where the measurement is made.
What happens if the burden is below 25% of the rated output?
The VT falls outside the range in which the class is guaranteed. The fix is to choose a lower rated output that matches the real burden, not to add ballast resistors without analyzing their effect on the circuit.