Tiza Group

Home / Guides / Testing, commissioning and faults

Transformer Energization: Inrush Current and Monitoring

How a transformer is energized during commissioning: what inrush to expect, how long it lasts, what is recorded and when the result is accepted.

By Shadai García, CEO and protection engineer at Tiza Group.

34.5 kV grid20 MVAopen, no load87T50inrush current is not a faultthe second harmonic restrains the differentialtime (s)I / In012128rated current0.69 s1.04 speak: 8 × 334.7 = 2,678 A; 2 × In at 0.69 sreturns to rated in 1.04 s2nd harmonic 25 % > 15 %: no tripChainHV breakerTransformer87T differentialI record© tizagrp.com34.5 kV grid20 MVAopen, no load87T50inrush current is not a faultthe second harmonic restrains the differentialtime (s)I / In012128rated current0.69 s1.04 speak: 8 × 334.7 = 2,678 A; 2 × In at 0.69 sreturns to rated in 1.04 s2nd harmonic 25 % > 15 %: no tripChainHV breakerTransformer87T differentialI record© tizagrp.com
Energization of a 20 MVA transformer on no load: inrush current decaying with time and differential that does not trip. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

When a transformer is energized, the inrush current can be several times the rated current and decays over tenths of a second or seconds. The test closes the breaker with protection ready, records the current, confirms nothing trips and keeps watching the equipment during the first hour. A worked example with assumptions (20 MVA, 34.5 kV, 8-times peak) gives 334.7 A rated, a 2,678 A peak and 1.04 s to fall back to rated.

Short answer

When the breaker closes onto an unloaded transformer, the core saturates for a few cycles and the inrush current can reach several times the rated value, then decay over tenths of a second or seconds. The energization test closes with protection ready and verified, records that current with a recorder, checks that no protection trips and keeps watching the equipment while it takes load. Inrush current is explained in its own guide; this one covers how the test is run.

Before closing

Energization is the end of a sequence, not its start. Before giving the order:

  • Pre-energization review complete. See the transformer pre-energization review: oil, accessories, tap changer, earthing.
  • Protection with approved settings, tested, with its trips wired to the breakers on both sides, as described in the trip and close tests.
  • Recorder ready, with manual trigger to capture the instant of closing, and clocks synchronized.
  • Tap-changer position known and noted.
  • Energization plan stating who gives each order, who watches each device and who is informed. The substation sequence is described in staged energization.
  • Safety conditions: personnel clear of the area, earths removed, no work permits open.

What happens during closing

Inrush depends on the instant of closing on the voltage wave, the residual flux in the core, the source impedance and the transformer design. That is why it changes from one energization to the next and from phase to phase. Its shape is characteristic: single-polarity pulses with almost no current between them and a high second-harmonic content. Differential protection uses that characteristic so as not to confuse it with a fault (second-harmonic restraint or blocking). Energization is also, at once, a proof that this setting is suitable.

What is recorded

  • Current in each phase on the energized side, over the first seconds, until it reaches the no-load value.
  • The first-peak value and the time it takes to fall to defined levels.
  • Second harmonic against the fundamental, if the relay shows it.
  • Busbar voltage before and after closing.
  • Any pickup or trip of a protection, even if it had no effect.
  • The time and the tap-changer position.

The record goes into the project dossier, together with the result of the monitoring.

Worked example: what to expect and for how long

Assumptions. A 20 MVA transformer, 34.5 kV on the high side, energized from that side at no load. First-crest peak of 8 times rated current (illustrative assumption), with exponential decay and a time constant of 0.5 s. The differential relay measures a second harmonic of 480 A against a fundamental of 1,920 A at a given instant, and its restraint threshold is 15 % (assumption).

  1. Rated current at 34.5 kV: In = 20,000 / (√3 × 34.5) = 334.7 A.
  2. Inrush peak: 8 × 334.7 = 2,677.6 A, about 2,678 A.
  3. Evolution: I(t) = 2,677.6 × e^(−t/0.5).
  4. Time to fall to 2 times In (669.4 A): t = 0.5 × ln(4) = 0.69 s.
  5. Time to fall to rated (334.7 A): t = 0.5 × ln(8) = 1.04 s.
  6. Time to fall to 1/16 of the first peak: t = 0.5 × ln(16) = 1.39 s.
  7. Second-harmonic ratio: 480 / 1,920 = 25 %, above the 15 % threshold: restraint acts and the differential relay does not trip.
  8. With a 400/5 CT: the first peak is 2,677.6 / 80 = 33.5 A on the secondary.

With these assumptions the current returns close to rated in a little over one second. In a real transformer the time depends on the design and the network, which is why it is measured and not assumed. If the record shows a much slower decay than expected, or if the settled no-load value is high, it is reviewed before loading.

Monitoring during the first hour

After the inrush, with the transformer at no load, the following are watched: no-load current and voltage, noise (an abnormal hum or vibration), oil and winding temperature, oil level and leaks, indications from the gas relay and the pressure device, and the state of the alarms in the control system. Readings are taken at agreed intervals and logged. Only then is the transformer loaded in steps, following the plan. If there is a trip, the breaker is not closed again until the cause is understood; the guide on transformer trip on energizing helps with diagnosis.

What to do if protection trips

A trip at energization is not solved by closing again. The order is: leave the equipment as it is, download the record from the relay and the recorder, and look at three things. First, which function tripped and at what current. Second, whether the current has the shape of an inrush (single-polarity pulses, high second harmonic) or that of a fault. Third, whether the loaded setting is the approved one. If it is an inrush the protection failed to recognize, the restraint setting is reviewed with whoever owns the study; if it looks like a fault, the electrical tests of the transformer are done before any new attempt. Everything goes in the report, with the time and the state of each device.

It is also worth noting the ambient temperature and the system load at the moment of closing: they help interpret any difference between two energizations of the same equipment.

Common mistakes

  • Energizing without a recorder, and having no evidence if something trips.
  • Closing with a setting that is not the approved one.
  • Not noting the tap-changer position.
  • Mistaking an inrush trip for a transformer fault, and taking it out of service without reviewing the setting.
  • Loading the transformer before the no-load monitoring is finished.
  • Not coordinating the time with the grid operator.

Checklist

  • Transformer pre-energization review closed.
  • Protection with approved settings, tested, trips wired.
  • Recorder ready and clocks synchronized.
  • Tap-changer position noted.
  • Energization plan with responsible persons.
  • Inrush current recorded and first peak noted.
  • No unexpected trips or alarms after closing.
  • No-load monitoring with readings at intervals.
  • Loading in steps only after monitoring.
  • Records filed in the dossier.

References

  • IEEE C37.91, guide for protecting power transformers.

Need these tests?

We prepare the energization plan, the protection settings that support it and the acceptance criteria for transformers as part of our engineering design and studies service, for projects in any country. Contact us.

Frequently asked questions

Is inrush current a fault?

No. It is a normal energization phenomenon: the core saturates for a short time and the transformer draws a high current rich in second harmonic. Protection must tell it apart from a fault; if it trips, the setting needs review, not necessarily the transformer.

How many times in a row can it be energized?

The manufacturer and the installation study set the procedure. In commissioning, the plan must state how many attempts are allowed and how long to wait between them, and after a trip the breaker is not closed again without reviewing the cause.

What is monitored after energizing at no load?

No-load current, voltages, noise, oil and winding temperature, leaks, indications from the gas and pressure relays, and the stability of signals to the control system. Readings are taken at agreed intervals and logged before the transformer is loaded.

WhatsApp