A power factor correction panel combines capacitors, contactors, protection and a controller that switches steps in and out to hold the plant power factor at the target value. The kvar follow from the active power and the two power factors, initial and target. Before the panel is built you must decide whether harmonics are present, how the steps are switched and where the current transformer goes.
The power factor correction panel supplies the reactive power that inductive loads would otherwise draw from the network, so the plant power factor approaches the target value. It is one variant of the family presented in types of electrical panels.
Short answer
A power factor correction panel is a low-voltage capacitor bank divided into steps, with a controller that switches them according to the load. It is sized with kvar = P × (tan φ1 − tan φ2), protected step by step and verified as a low-voltage assembly. What changes the design most is the presence of harmonics: with them, every step gets a detuning reactor.
What it contains
- Main breaker or fused switch, sized for the total bank current.
- Capacitors in each step, self-healing type, with a discharge device.
- Capacitor-duty contactors, or thyristor switches when the load changes very fast.
- Detuning reactors (in series with each step) when harmonics are present.
- Protection of each step: fuses or a breaker, sometimes an over-temperature relay.
- Power factor controller, which measures the load current with a current transformer and decides which steps switch in.
- Ventilation, because capacitors and reactors dissipate heat; the temperature rise of the assembly is verified under IEC 61439.
IEC 61921:2017 is the standard for low-voltage capacitor banks for power factor correction. It refers to IEC 61439-1 and 61439-2 for the assembly, so the panel is treated like any other low-voltage switchboard. Design verification and routine verification follow those rules.
Worked example
A plant draws 400 kW at a power factor of 0.78 and the target is 0.95.
- tan φ1 = tan(arccos 0.78) = 0.802.
- tan φ2 = tan(arccos 0.95) = 0.329.
- kvar = 400 × (0.802 − 0.329) = 189 kvar.
The next standard bank size is 200 kvar. With 200 kvar the remaining reactive power is 321 − 200 = 121 kvar and the final power factor is 0.957. If 0.98 were specified instead of 0.95, about 240 kvar would be needed. Asking for more than necessary raises the cost and the risk of overcompensation when the load drops; the full sizing criteria are in how to size a capacitor bank.
Selection table
| Decision | Question that settles it | Typical choice |
|---|---|---|
| Fixed or automatic | Does the reactive load change during the day? | Fixed if constant; automatic if it varies. See automatic vs fixed |
| With or without detuning reactor | Are there drives, rectifiers or other non-linear loads? | No harmonics: capacitor only; with harmonics: detuning reactor per step |
| Contactor or thyristor | Does the load change in cycles or in seconds (welding, cranes)? | Contactor for slow loads; thyristor for fast loads |
| Location | One central point or several? | Central at the main switchboard; local next to large motors |
| Steps | What control resolution is needed? | See steps of an automatic capacitor bank |
Where the current transformer goes
The controller must see the load current and the bank current. For that reason the current transformer is installed upstream of the point where the bank connects: at the incomer of the main switchboard or at the feeder being compensated. If it is installed downstream, the controller sees only the load and not the effect of the steps it switches in: it keeps adding steps until the whole bank is in service, and it overcompensates when the load drops. The transformer is selected with the rules in current transformer.
Harmonics and resonance
Capacitors and network inductance form a circuit that can resonate at a harmonic frequency. If it coincides with the frequency of the currents from drives or rectifiers, the capacitor current rises and the capacitors overheat until they fail. The series detuning reactor moves that resonance to a frequency below the harmonics present. How much harmonic content there is must be measured with a power quality analyzer; the harmonic study under IEEE 519 and active and passive filters are the next step if the measurement calls for it.
Checklist before building
- Initial and target power factor, with measured, not estimated, active power.
- 24-hour load profile: minimum, maximum and rate of change.
- Voltage and current harmonic measurement at the connection point.
- Service voltage and its variation; capacitors are sized for the real voltage.
- Available short-circuit current, for the breaking capacity of the protection.
- Ambient temperature and site altitude, which affect temperature rise.
- Current transformer ratio and location.
- Capacitor discharge time before a step is reconnected.
- Enclosure degree of protection (IP) for the environment; see IP rating of a panel.
- Rating plate with the assembly data, as IEC 61439 requires.
How we help
We design the correction panel with you remotely, worldwide: reactive profile, harmonic review, kvar and step arrangement, single-line diagram and bill of materials, adapted to the local code and the utility requirements you give us. See our primary engineering service and write to us with the plant power and the load profile.
Related guides
- Types of electrical panels: which one to choose for your load
- Steps of an automatic capacitor bank
- Semi-direct metering panel
- Automatic or fixed capacitor bank: which one fits
- How to size a capacitor bank in a plant
- Power factor in industry
- Harmonic study under IEEE 519-2022
References
- IEC 61921:2017, Power capacitors – Low-voltage power factor correction banks.
- IEC 61439-1:2020 and IEC 61439-2:2020, low-voltage switchgear and controlgear assemblies: general rules and power switchgear assemblies.
- IEC 60831-1:2014, shunt power capacitors of the self-healing type for low-voltage a.c. systems.
- IEEE 519-2022, harmonic control in electric power systems.
Frequently asked questions
How many kvar does a power factor correction panel need?
They are calculated from the active power and the initial and target power factors: kvar = P × (tan φ1 − tan φ2). For example, 400 kW going from power factor 0.78 to 0.95 needs about 189 kvar. The result is rounded up to the next standard bank size and split into steps.
Which standard applies to a power factor correction panel?
IEC 61921 covers low-voltage capacitor banks for power factor correction; the current edition is from 2017. The bank must also meet IEC 61439-1 and IEC 61439-2 where applicable, because the bank is a low-voltage switchgear and controlgear assembly.
Can a power factor correction panel be installed without measuring harmonics?
It is not advisable. Capacitors and network inductance can resonate with the harmonic currents of drives and rectifiers. With significant non-linear loads the bank gets detuning reactors, and that is decided from a prior measurement.