NFPA 70E Shock Approach Boundaries Explained

NFPA 70E limited and restricted shock approach boundaries: who may cross them and why they are independent of the arc flash boundary. We do the study.

By Shadai García, CEO and protection engineer at Tiza Group.

energized part 13.2 kVrestrictedlimited0.7 m1.5 marcfrom the studyarcfrom the studyqualifiedunqualifiedWho enters each boundaryUnqualified: stays outside the limitedEnters the limited only with an escortRestricted: qualified, insulated, with a permitArc flash: another distance, from the studyCase 1: arc flash inside the limitedCase 2: arc flash farther, arc-rated clothingShockVoltageTable 130.4(E)(a)LimitedRestricted© tizagrp.comenergized part 13.2 kVrestrictedlimited0.7 m1.5 marcfrom the studyarcfrom the studyqualifiedunqualifiedWho enters each boundaryUnqualified: stays outside the limitedEnters the limited only with an escortRestricted: qualified, insulated, with a permitArc flash: another distance, from the studyCase 1: arc flash inside the limitedCase 2: arc flash farther, arc-rated clothingShockVoltageTable 130.4(E)(a)LimitedRestricted© tizagrp.com
NFPA 70E-2021 approach boundaries at a 13.2 kV cell: restricted at 0.7 m, limited at 1.5 m and the independent arc flash boundary. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

NFPA 70E sets two distances around an exposed energized part to control the shock risk: the limited approach boundary, inside which the risk exists, and the restricted approach boundary, where an unintended movement can cause contact or an arc. An unqualified person does not cross the limited boundary without an escort and never crosses the restricted one. The distances depend on voltage and are independent of the arc flash boundary.

Short answer

Around an exposed energized part, NFPA 70E defines two boundaries for the electric shock risk. The limited approach boundary is the distance inside which there is a shock risk. The restricted approach boundary is closer: inside it, an unintended movement can lead to contact or to an arc-over. Both distances depend on voltage and are read in Table 130.4(E)(a) for AC and Table 130.4(E)(b) for DC of NFPA 70E-2021. An unqualified person does not cross the limited boundary without an escort and never crosses the restricted one. The arc flash boundary is a different distance, calculated separately.

What each boundary means

The terms are defined in Article 100 of the standard. In our words:

  • Limited approach boundary: the line, measured from the exposed energized part, beyond which a person is exposed to a shock hazard.
  • Restricted approach boundary: a closer line, where shock is more likely because an arc-over through the air and an accidental movement of the person add up.
  • Arc flash boundary: the distance from the arc source at which incident energy is 1.2 cal/cm² (5 J/cm²). The note in the standard explains that one second at that exposure is where a second-degree burn on bare skin begins.
  • Qualified person: someone who has shown the skills and knowledge of how the electrical equipment is built and operated, and has had safety training to recognize the hazards and reduce the risk. An unqualified person is anyone who is not.

Each distance is measured from the exposed energized part to the person.

Who may cross each boundary

Who crosses each shock boundary (NFPA 70E-2021, 130.4)
  • Is the person qualified?
    • No: Do they need to enter the limited boundary?
      • No: They stay outside, warned by signs, barricades or an attendant
      • Yes: They enter only with a qualified person escorting them at all times and never cross the restricted boundary
    • Yes: Will they cross the restricted boundary?
      • No: They work as the shock risk assessment says, with the PPE it calls for
      • Yes: They must be insulated or guarded, and hold an energized electrical work permit

The rules behind the tree:

  1. Unqualified person near the limited boundary: the alerting methods of 130.7(E) apply: signs, barricades and, if those are not enough, an attendant, so the person stays outside (130.4(F)(2)). Barricades are placed no closer than the limited boundary, nor closer than the arc flash boundary when that one is larger (130.7(E)(2)).
  2. Unqualified person who must enter: a qualified person explains the hazards and escorts them the whole time they are inside. They never cross the restricted boundary (130.4(F)(3)).
  3. Qualified person at the restricted boundary: they do not move closer or bring a conductive object closer. The exception is when they are insulated or guarded from parts at 50 V or more, or when those parts are insulated from them and from any object at another potential (130.4(G)). Insulating gloves and sleeves count as insulation only for the part being worked on.
  4. Energized electrical work permit: required when work is done inside the restricted boundary (130.2(A)(1)).

The values in two cases

The standard splits the limited boundary into two columns: the exposed movable conductor, when the person does not control the distance, as with an overhead line on poles, and the exposed fixed circuit part, such as the bus of a switchgear cell. For two AC voltage ranges common in industry:

Phase-to-phase voltage rangeLimited, movable conductorLimited, fixed partRestricted
151 V to 750 V3.0 m1.0 m0.3 m
751 V to 15 kV3.0 m1.5 m0.7 m

Values from Table 130.4(E)(a) of NFPA 70E-2021; wording and format by Tiza Group. The table in the standard covers 50 V to 800 kV in AC, and Table 130.4(E)(b) does the same in DC.

In single-phase systems above 250 V, the range is chosen with the maximum phase-to-ground voltage multiplied by 1.732. Below 50 V the standard sets no boundaries.

Annex C explains where the figures come from. The limited boundary for movable conductors comes from the OSHA rule, the US workplace safety authority, which sets a 3.05 m clearance for unqualified persons up to 50 kV to ground, plus 100 mm for each additional 10 kV. The restricted boundary adds an allowance for accidental movement to the flashover distance in air.

Example: a 13.2 kV switchgear cell under maintenance

A plant technician is going to take temperature readings with the door of a 13.2 kV cell open and the energized bus in sight. The voltage falls in the 751 V to 15 kV range. The bus is a fixed part, so the limited boundary is at 1.5 m and the restricted boundary at 0.7 m.

  • The helper, who is not a qualified person, stays more than 1.5 m away, behind a barricade with tape and a sign. If they need to enter to hand over an instrument, they do so escorted and never closer than 0.7 m.
  • The qualified technician works outside the 0.7 m. If the task requires getting closer, it becomes work inside the restricted boundary: it needs an energized work permit and insulation suited to 13.2 kV.
  • The cell label also carries the arc flash boundary calculated in the study. If that boundary is larger than 1.5 m, a person standing between the two distances is outside the shock risk but inside the arc risk, and needs arc-rated clothing.

Arc flash boundary and shock boundaries

The note in 130.4(E) says it plainly: the shock boundaries and the arc flash boundary are independent, and the arc flash boundary can lie farther out than the limited one. The shock boundaries depend only on voltage. The arc flash boundary depends on the fault current, the clearing time of the protection and the type of equipment, and comes from an arc flash study or from the PPE category method. The equipment label must state it, as the guide on arc flash labels explains, and the level of protection is chosen with the arc flash PPE categories. You can estimate the arc flash boundary of a case with our free arc flash tool.

Local regulations may set their own minimum safety distances for work near energized parts, and where they apply they govern the site. Distances and induction risks are covered in working near energized equipment.

Typical mistakes

  • Painting a single line on the floor and calling it «the boundary». There are three different distances, and the arc flash one may be the largest.
  • Using the fixed-part column for an overhead line, where the movable-conductor column applies.
  • Letting an unqualified helper step in to hand over tools without an escort.
  • Believing that insulating gloves protect against a nearby phase. They only count for the part being worked on.
  • Using an old label after the protection settings have changed.

When to call us

The shock boundaries are read from a table; the arc flash boundary and the incident energy of each panel and switchgear come from a study. We do your arc flash study with IEEE 1584 on the real settings of your protection, with the labels of each piece of equipment and proposals to reduce the energy where it is high, as in how to reduce incident energy. Studies are a remote service, available worldwide. See our engineering design and studies service and write to us: we will send you a quote for the study.

References

  • NFPA 70E, Standard for Electrical Safety in the Workplace, 2021 edition: Article 100 (definitions of arc flash boundary, limited and restricted approach boundary, qualified and unqualified person), 130.2(A), 130.4(E) to (G), 130.5(E), 130.7(E), Tables 130.4(E)(a) and 130.4(E)(b) and Informative Annex C, section C.2.
  • NFPA 70E, 2027 edition, current edition.

Frequently asked questions

What is the difference between the limited and the restricted approach boundary?

The limited boundary marks the distance inside which there is a risk of electric shock. The restricted boundary is closer to the energized part and marks where shock becomes more likely, because an unintended movement can cause contact or an arc-over. Both are read in Table 130.4(E)(a) for AC and Table 130.4(E)(b) for DC of NFPA 70E-2021.

Can an unqualified person enter the limited approach boundary?

Only if a qualified person explains the hazards and stays with them the whole time they are inside. They may never cross the restricted boundary, under any circumstance (NFPA 70E-2021, 130.4(F)(3)).

Does the arc flash boundary replace the shock boundaries?

No. They are independent. The arc flash boundary is the distance at which incident energy reaches 1.2 cal/cm² (5 J/cm²) and comes from the arc flash study; the shock boundaries come from the voltage. The arc flash boundary can lie farther out than the limited boundary (NFPA 70E-2021, 130.4(E) and 130.5(E)).