IEC 81346-2 classifies each object by the task it performs in the system, not by the product that performs it, and gives it a class letter and, when needed, a second subclass letter. In a substation the circuit breaker is QA, the disconnector QB, the earthing switch QC, instrument transformers belong to class B, the power transformer is TA and high-voltage busbars are WA.
This guide is based on the 2009 edition of IEC 81346-2. The current edition is edition 2.0 of 2019. According to the publisher, that edition defines the entry classes by the inherent function of the object, adds a three-level scheme and a separate scheme for spaces. Before fixing the codes of a new project, compare them with the current edition.
Short answer
IEC 81346-2:2009 gives each object a letter according to the task it performs in the system: switching, measuring, protecting, converting, conducting or connecting. When more detail is needed, a second letter gives the subclass. In a substation, the circuit breaker is QA, the disconnector QB, the earthing switch QC, the CT is BC, the voltage transformer BA, the surge arrester FA, the power transformer TA and the high-voltage busbar WA. Those letters are the ones used in the reference designation of IEC 81346-1.
The underlying rule: the task is classified, not the product
The standard asks you to view each object as a component of the system that performs a task, without thinking about how it is built (clause 4.2, rule 2). The same product can fall into different classes depending on its use.
Our example: the substation battery bank. Its task is to store energy for the DC services, so it goes in class C, storage, subclass CC, chemical storage of electrical energy. A battery whose task is to initiate the flow of energy, such as a dry cell feeding a portable device, goes instead in class G, subclass GB.
If an object has several tasks, it is classified by the main one (rule 3). Class A is kept only for objects in which no main task can be identified (rule 4); it is not a class for whatever you do not know where to put.
The classes used in a substation
This is our selection of the objects found in a substation and their class. It is not the table of the standard: it is only what a typical bay needs.
| Bay equipment | Code | How to read it on the drawing |
|---|---|---|
| Circuit-breaker | QA | The device that opens under load or fault; wherever you see QA, that is where the trip arrives |
| Disconnector | QB | Opens off-load to leave a visible gap before work starts |
| Earthing switch | QC | Closed only once the section is open and dead |
| Current transformer | BC | Feeds relays and meters with the primary current scaled down |
| Voltage transformer | BA | Does the same with the bus or line voltage |
| Surge arrester | FA | Diverts lightning and switching overvoltages to earth |
| Power transformer | TA | Changes the voltage level between two networks |
| High-voltage busbar | WA | The node every bay connects to |
| Control cable | WG | The wiring between yard, panel and relays |
| Panel terminal blocks | XD | Where field wiring meets panel wiring |
| Auxiliary relay | KF | Repeats or combines control signals inside the scheme |
| Local/remote selector | SF | What the operator turns to choose where commands come from |
Codes from Tables 1 and 2 of IEC 81346-2:2009; selection, explanation and format by Tiza Group (the standard’s definitions are not reproduced). The full list of classes and subclasses is in the standard.
Two facts help to read the table. First, the split between high and low voltage in class W is set by the standard itself: above 1 000 V AC or above 1 500 V DC. Second, the second letter follows a fixed grouping (clause 5.2). Letters A to E are subclasses for electrical energy, and F to K for information and signals. L to Y are for process, mechanical and civil engineering, and Z is for combined tasks. Class B is the exception: its subclasses follow the measurement codes of ISO 14617-6.
The case of the protective relay
The 2009 edition leaves one decision to the project. Measuring relays appear in class B, which turns a quantity into a signal. Class F groups direct protection and includes systems and equipment for protective purposes. Class K, signal processing, explicitly excludes protective objects and points to class F.
A numerical relay measures, decides and trips. Depending on which task is taken as the main one, the project will classify it as B or as F. What cannot be done is to use both in the same project for identical devices. The choice is written in the supporting documentation, next to the numbering rule.
Our example: the coded line bay
With those letters, line bay 3 of our 115 kV example reads as follows, in the product aspect:
-QB1 busbar disconnector
-QA1 circuit breaker
-BC1 current transformers
-QB9 line disconnector
-QC9 line earthing switch
-BA1 line voltage transformer
-FA1 line surge arrester
The numbers tell apart objects of the same class within the bay. Here the project decided that 9 marks the devices on the line side, so it writes that down in its rules document: a number with a meaning must be explained (IEC 81346-1:2009, rule 10).
Typical mistakes
- Classifying by the trade name. Calling everything named «relay» K ignores the task. A measuring relay and an auxiliary relay do not perform the same task.
- Using A as a catch-all. Class A is only for objects with no main task.
- Using reserved letters. In the 2009 edition, the letters D, J, L, N, Y and Z of Table 1 are reserved for future standardization, and I and O are not applied.
- Coding attributes in the subclass. The standard asks not to use subclasses to code technical data (note 2 of clause 4.1). Rated voltage or brand go in the specification and the parts list, not in the code.
- Inventing subclasses without writing them down. They may be created if none in Table 2 applies, following its grouping and explaining them in the documentation (rule 6).
- Mixing editions. A project with 2009 codes and an extension with 2019 codes, without a correspondence table, creates two names for the same kind of equipment.
Where it is used
The letters appear in the single-line diagram, in the protection and control drawings and on the yard labels. Each device in the table has its own guide; start with the power circuit breaker and the current transformer. For power supply plants and systems, the series also has ISO 81346-10:2022, which defines its own classes of systems and spaces in that field.
When to call us
At Tiza Group we define the equipment coding of your substation or plant and apply it in the single-line diagram, the drawings and the lists, with the supporting documentation that audits ask for. Engineering is a remote service, available worldwide. See our primary engineering and secondary engineering services. Write to us and we will send you a quote.
Related guides
- IEC 81346-1 reference designation: aspects =, - and +
- Single-line diagram of a plant
- Secondary design: protection and control drawings
- Power circuit breaker
- Current transformer
- Substation disconnector
- Industrial electrical diagrams: IEC and NEMA symbols
References
- IEC 81346-2, Industrial systems, installations and equipment and industrial products – Structuring principles and reference designations – Part 2: Classification of objects and codes for classes, edition 1.0 (2009), clauses 4.1, 4.2, 5.1 and 5.2, Tables 1 and 2.
- IEC 81346-2, edition 2.0 (2019), current edition.
- IEC 81346-1, edition 1.0 (2009), clause 6.2, rule 10.
- ISO 81346-10, Part 10: Power supply plants, edition 1.0 (2022).
Frequently asked questions
Which letter does a power circuit breaker take under IEC 81346-2?
Class Q groups the controlled switching of a flow of energy. Within it, the circuit breaker and the contactor take QA, because they are the devices that open and close the power circuit. The disconnector goes in QB and the earthing switch in QC (IEC 81346-2:2009, Table 2).
Why is a current transformer not in class T?
Because the standard classifies by the task within the system. The CT turns a primary quantity into a signal for another device to process, and that task belongs to class B. Subclass BC is for electric current and BA for electrical potential, where the voltage transformer goes (Tables 1 and 2).
Which class does a protective relay take?
It depends on which task is taken as its main one. The 2009 edition places measuring relays in class B, keeps class F for equipment with a protective purpose and excludes that equipment from class K. The project must choose one option and write it in its supporting documentation.