IEC 61850 Edition 1 was published between 2002 and 2005; Edition 2, from 2009 onward, extended the scope to all power utility automation and added simulation mode, GOOSE and SV subscription supervision, new logical nodes and SCL files. The so-called Edition 2.1 is Edition 2 with Amendment 1 of 2020. IEDs of different editions can coexist, but their conformance, SCL files and test-mode behavior must be checked.
The three editions over time
IEC 61850 is not one document: it is a series of parts that are published and amended separately. Speaking of an «edition» is therefore a useful simplification.
- 01Edition 1, 2002 to 2005Substation communication: MMS, GOOSE, SV and SCL
- 02Edition 2, from 2009All power utility automation; simulation, LGOS and LSVS
- 03Amendment 1, 2020Known as Edition 2.1: corrections and model extensions
- 04New parts and parts under revisionTechnical reports of the 90 series and new editions of individual parts
The table of parts with their current editions is in standards for substation communications and time synchronization.
What Edition 1 brought
The first edition defined what is taken for granted today: the data model with logical nodes, the abstract services, their mapping to MMS and GOOSE messages, sampled values, and the SCL configuration language. Its title referred to communication networks and systems in substations.
In the field, Edition 1 left gray areas: quality handling, test mode and some SCL details were open to interpretation, and each manufacturer resolved them its own way.
What changed in Edition 2
- Scope. The title went from «substations» to «power utility automation». Power plants, distributed energy resources and communication outside the substation were included.
- Test mode and simulation. The logical device modes were organized (on, blocked, test, test/blocked) and simulation was added: an IED can accept GOOSE and SV messages flagged as simulated instead of the real ones, to test with logical isolation. The simulated message is identical to the real one except for the simulation flag in its header.
- Subscription supervision. The logical nodes LGOS (GOOSE subscription) and LSVS (SV subscription) let the IED itself supervise whether each expected message arrives.
- Quality. Mandatory handling of data quality in GOOSE was clarified.
- New logical nodes and data classes, for example for power quality and equipment condition monitoring.
- SCL. New file types and rules were added for exchange between tools from different manufacturers. See SCL files.
The test modes are explained in more detail in the IEC 61850 digital substation guide.
What Edition 2.1 is
In 2020, Amendment 1 to several parts of Edition 2 was published: 7-1 to 7-4, 8-1 and 9-2, among others. IEC sells each part as a consolidated version of Edition 2 with its amendment, and the market calls it Edition 2.1. It fixes errata, clarifies behaviors and extends the model. Recent relays from the main manufacturers offer it, sometimes as an ordering option.
Problems when mixing editions in an expansion
The typical situation is a substation with Edition 1 IEDs to which bays with Edition 2 or 2.1 IEDs are added. What usually fails:
- Configuration tools. One manufacturer’s tool may not import the SCL file of another edition, or may not convert an IED’s configuration file between editions.
- New logical nodes and data that the older IED does not understand when it subscribes.
- Test mode. An Edition 2 IED in test mode publishes with the test flag; an Edition 1 IED may interpret it differently and accept or reject the message unexpectedly.
- Quality. An IED that flags questionable quality can make a subscriber of another edition discard the data, or use it when it should not.
- Names and lengths of objects and references that changed from one edition to the next.
None of this prevents coexistence. It takes engineering: checking the conformance of each IED, preparing the system configuration with a tool that supports both editions, and testing every real exchange.
- Do the new IEDs exchange GOOSE or SV with the existing ones?
- YesDoes the system tool import the SCL files of both editions without manual conversion?
- YesReview PICS and PIXIT of both, and test each subscription and the test mode
- NoDefine the engineering workflow and the tool before buying
- No, they only report to the control system over MMSCheck that the MMS client and the gateway support the new edition
How to specify the edition in a new project
In a new project it is sensible to require a single edition for all IEDs, normally the most recent one offered by the selected manufacturers, and to require that the system configuration tool supports it. In an expansion, the specification should state which existing IEDs the new ones will exchange messages with, and ask the vendor to demonstrate that interoperability before delivery.
What to check in the conformance documents
- Conformance certificate: IEC 61850 edition tested, version of the UCA International Users Group test procedure, laboratory and certificate level.
- PICS: which services the IED supports (reports, GOOSE, SV, files, control).
- MICS: which logical nodes and data it implements.
- TICS: which technical issues of the standard it implements.
- PIXIT: additional information needed for testing, such as limits, timings and vendor-specific behaviors.
IEC 61850 Part 10 defines conformance testing, and these documents are its basis.
IEC 61850 integration with Tiza Group
Expansions with IEDs of different editions and manufacturers are part of the daily work of our IEC 61850 engineering team: we check conformance, prepare the SCD and test each subscription, in medium-, high- and extra-high-voltage substations and industry, in Colombia, or elsewhere on request. Before starting, you can see which IED publishes and who subscribes in your SCD with our free IEC 61850 SCL viewer tool. If the change is in a relay’s configuration, we make it worldwide through remote relay configuration. Write to us.
Related guides
- IEC 61850 test mode: Mod, Beh, Sim and the test bit
- Configuration management: settings and SCD versions
- Migrating from 103, 101 or Modbus to IEC 61850
- Top-down and bottom-up IEC 61850 engineering: SSD to CID
- Substation communications by voltage level: MV, HV, EHV
References
- IEC 61850 (series), Editions 1 and 2, and the 2020 amendments to Parts 7-1, 7-2, 7-3, 7-4, 8-1 and 9-2.
- IEC 61850-7-4: logical node classes, including LGOS and LSVS.
- IEC 61850-6: SCL configuration language.
- IEC 61850-10: conformance testing.
- UCA International Users Group: IEC 61850 conformance test procedures.
Frequently asked questions
Can an Edition 1 IED exchange GOOSE with an Edition 2 IED?
Generally yes, because the basic format of the GOOSE message was kept. Problems appear in the details: quality handling, test mode, the names of new logical nodes and the configuration tool, which may not import the SCL file of the other edition. It is verified with the conformance documents and with real tests.
What is IEC 61850 Edition 2.1?
Strictly speaking, it is not a new edition. In 2020, Amendment 1 to several parts of Edition 2 was published (among them 7-1 to 7-4, 8-1 and 9-2), and IEC sells them as consolidated versions; in the industry it is known as Edition 2.1. It corrects and clarifies points of Edition 2 and adds elements to the model.
Which document states the edition an IED supports?
The conformance certificate and the documents that accompany it: PICS (supported services), MICS (data model), TICS (implemented technical issues) and PIXIT (extra information for testing). The certificate states the edition and the version of the UCA International Users Group test procedure used.