Generator Transfer Switchboard: How to Size It

How to size an automatic transfer switchboard with a generator: current, short-circuit rating, poles, start signals and checks, with a worked example.

By Shadai García, CEO and protection engineer at Tiza Group.

grid2752NGgroup52GATSpickupbusessential loadsno gridnormal: loads on the gridgrid is lost27 confirms: 52N opens, generator startsgenerator at voltage, frequency52G closes: loads on generatorgrid back: return delay52G opens, 52N closesgenerator cools down, stopsgrid52Ngroup52Gloadsclosed or runningenergizedopen transition: never both closedControl27 on grid and generatorATS logicGenerator start52N / 52G© tizagrp.comgrid2752NGgroup52GATSpickupbusessential loadsno gridnormal: loads on the gridgrid is lost27 confirms: 52N opens, generator startsgenerator at voltage, frequency52G closes: loads on generatorgrid back: return delay52G opens, 52N closesgenerator cools down, stopsgrid52Ngroup52Gloadsclosed or runningenergizedopen transition: never both closedControl27 on grid and generatorATS logicGenerator start52N / 52G© tizagrp.com
Automatic source transfer: grid, generator set and return. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A generator transfer switchboard connects the utility and a generator set to one load without letting the two sources meet. It is sized by the generator current, by the short-circuit current of the stronger source (usually the utility), by the number of poles switched and by the signals that tie it to the generator controls.

Short answer

A generator transfer switchboard is sized with four data: the generator current, the short-circuit current of the stronger source, the number of poles switched and the start signals between the controller and the generator. With those four, the transfer equipment is selected, the assembly is checked to withstand it and the signal list is defined.

The transfer logic and timing are in automatic transfer of sources; the difference between open and closed transition is in open or closed transfer. Its place among the other switchboards is in types of electrical switchboards.

What a generator transfer switchboard contains

  • Two incomers with interlocking, one per source, or a single transfer switch. The mechanical interlock prevents both sources from being closed at once; the electrical one adds to it and does not replace it.
  • Controller that measures voltage and frequency of both sources, times the delays and commands the operations.
  • Output to the generator: a dry start contact and, sometimes, a stop contact with cool-down.
  • Input from the generator: a generator-ready or generator-voltage-present signal.
  • Controller supply taken from both sources, with backup, so it does not go dead exactly when it is needed.
  • Selector for automatic, manual and test, with position indication for each source.
  • Load bus feeding the essential loads, kept separate from the loads that are not backed up.
  • Metering and protection on each incomer, to meet the utility and the installation design.

Built into a switchboard, the assembly is not verified by the transfer equipment alone: IEC 61439-1 and -2 require verification of temperature rise, short-circuit withstand and clearances for the complete assembly. See IEC 61439-1.

Worked example: building with a 250 kVA generator

Assumed data, not from a real project: 400 V three-phase, a 250 kVA standby generator with 12 % subtransient reactance, a 630 kVA utility transformer with 5 % impedance, and a backed-up load of 180 kW at 0.85 power factor.

CalculationFormulaResult
Generator current250,000 / (√3 × 400)361 A
Backed-up load current180 / 0.85 = 211.8 kVA; 211,800 / (√3 × 400)306 A
Generator short-circuit contribution361 / 0.123.0 kA
Utility short circuit (infinite bus)909 A / 0.05, with 909 A = 630,000 / (√3 × 400)18.2 kA

Reading the result:

  1. Rated current. The load draws 306 A and the generator can deliver 361 A. The equipment is sized by the generator: it is the largest load the backed-up system can reach, so the equipment does not limit an expansion: the next standard rating above 361 A is chosen, for example 400 A, and the enclosure temperature rise is checked.
  2. Short circuit. The equipment must withstand 18.2 kA, not the 3.0 kA of the generator. This is a mistake worth avoiding: sizing by the standby source, which is the weak one, when the strongest fault arrives from the utility.
  3. Generator protection. With a 3.0 kA fault and a 361 A rating, the fault is only 8.3 times the rated current, so the generator incomer protection must see a modest fault. It is coordinated with the breaker trip unit.
  4. Poles. If the generator neutral is bonded to earth at the generator, the neutral is switched and the equipment has four poles, so that two neutral-to-earth bonds are never in parallel. If the neutral is bonded to earth only at the service entrance and runs unbroken to the generator, three poles with a solid neutral are enough. The decision is made in the design, with the earthing scheme.

Selection table

DecisionOptionsWhat defines it
Equipment typeWith circuit breakers or with switch-disconnectorsWhether the equipment must protect or only switch
TransitionOpen, delayed or closedMotor loads and what the utility allows
Poles3 or 4Neutral earthing scheme
Rated currentStandard rating above the generator currentGenerator rated output
Short circuitWithstand to the higher fault current of the two sourcesUtility transformer and its impedance
Generator startDry contact or communicationGenerator control installed
OperationAutomatic only or with local manual operationMaintenance procedure

Standards

IEC 60947-6-1 covers low-voltage transfer switching equipment up to 1,000 V AC. Edition 3 is from 2021 and a fourth edition was published in 2026; check which one your specification cites. IEC 61439-2 covers the power assembly, in its 2020 edition. NFPA 110 classifies emergency and standby systems by type, class and level; Type 10, for example, limits to 10 seconds the time without acceptable power at the transfer equipment load terminals. In installations that follow the US code, Articles 700, 701 and 702 of NFPA 70 define when a system is emergency, legally required standby or optional standby.

Design review checklist

  • The rated current covers the generator rated output, not only the present load.
  • The short-circuit withstand covers the utility fault current.
  • The mechanical interlock prevents accidental paralleling.
  • The controller is powered from both sources and has backup.
  • The start signal is defined, with what happens if the generator does not respond.
  • It is defined which loads are backed up and which are shed.
  • Voltage and frequency settings for each source match what the loads tolerate.
  • There is a documented transfer test, with and without load.

What not to do

  • Do not size the equipment by the present load if the generator can deliver more.
  • Do not install two motorized breakers without a mechanical interlock, relying only on the controller program.
  • Do not start the generator with a signal that is never verified; no response must raise an alarm.
  • Do not mix essential loads with non-backed-up loads on the same load bus.

How we help

We design the switchboard and its transfer logic: sizing, single-line and control diagrams, signal lists and verification criteria, delivered remotely. See engineering design and studies.

References

  • IEC 60947-6-1, Transfer switching equipment, edition 3 (2021); fourth edition published 2026.
  • IEC 61439-1 and IEC 61439-2, Low-voltage switchgear and controlgear assemblies, 2020 edition.
  • NFPA 110, Standard for Emergency and Standby Power Systems, 2025 edition.
  • NFPA 70, National Electrical Code, Articles 700, 701 and 702.
  • UL 1008, Transfer Switch Equipment.

Frequently asked questions

What current is a generator transfer switchboard sized for?

For the generator current at its rated output, even if the present load is smaller, rounded up to the next standard rating of the equipment; that way the equipment does not limit a load that grows up to what the generator delivers. It must also withstand the short-circuit current of the stronger source, normally the utility.

Does automatic transfer need a dry-contact start signal to the generator?

Not always, but it is the most common arrangement: the controller closes a voltage-free contact that orders the start, and the generator returns a ready signal. Some systems use digital communication; either way the design must define who commands and what happens if the signal is lost.

Which standard covers the transfer equipment?

IEC 60947-6-1 covers low-voltage transfer switching equipment up to 1,000 V AC, including the automatic version with its controller. Built into a switchboard, the assembly is verified under IEC 61439. Projects that follow US standards use UL 1008, NFPA 110 and Articles 700, 701 and 702 of NFPA 70.