Gas-Insulated Transmission Line (GIL): Ratings and Tests

What a gas-insulated transmission line (GIL) is, its ratings under IEC 62271-204, type and routine tests, and how it is tested on site before energizing.

By Shadai García, CEO and protection engineer at Tiza Group.

section 1section 2section 3AC sourceAC sourceAC sourceAC sourceno cables, transformers orsurge arresters connectedone section energized, the others earthednext sectionlast sectioncomplete line, at lower voltageapplied voltage (AC)time80 % of the routine testpartial discharge: no level prescribedOn siteInstallationGas and moistureCircuit RVoltage and UHFService© tizagrp.comsection 1section 2section 3AC sourceAC sourceAC sourceAC sourceno cables, transformers orsurge arresters connectedone section energized, the others earthednext sectionlast sectioncomplete line, at lower voltageapplied voltage (AC)time80 % of the routine testpartial discharge: no level prescribedOn siteInstallationGas and moistureCircuit RVoltage and UHFService© tizagrp.com
On-site voltage test of a GIL in sections (IEC 62271-204): one section is energized with the others earthed, with partial discharge monitoring, and finally the complete line at lower voltage. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A GIL is a rigid transmission line: a conductor inside an earthed metal tube with a pressurized insulating gas between the two. IEC 62271-204 covers it above 52 kV and defines its ratings, its type and routine tests and the on-site tests, made by sections, before energizing.

Short answer

A gas-insulated transmission line, GIL, is a rigid transmission line. It carries a conductor inside an earthed metal tube, and a pressurized insulating gas fills the space between the two. IEC 62271-204 covers it for rated voltages above 52 kV and frequencies up to 60 Hz (clause 1.1). It sets the ratings, the factory tests and the on-site tests made before energizing.

Edition of the standard. This guide is based on IEC 62271-204:2011, and the clauses cited are those of that edition. The current edition is IEC 62271-204:2022 (edition 2.0), which replaces it. According to the publisher’s summary, the new edition is aligned with IEC 62271-1:2017 and adds material on welds of pressurized parts and on gas tightness.

What a GIL is and when it is used

The standard defines it as a metal-enclosed line, earthed, whose insulation is provided, at least in part, by a gas other than air at atmospheric pressure (clause 3.102).

It is used when the application falls outside IEC 62271-203, the standard for GIS substations. The scope gives three examples: a line buried wholly or partly, a line in an area accessible to the public, and a line so long that its gas compartments exceed usual GIS practice. It can be installed in open air, buried, or in a tunnel or shaft (clauses 2.101 to 2.103).

Ratings

The rating of a GIL includes, besides voltage, frequency and currents, the filling pressure of the gas (clause 4). Three points deserve attention:

  1. Insulation level. It is chosen with the values of IEC 62271-203 and with an insulation coordination study of each installation, covering overvoltages and wave reflections. The standard suggests considering surge arresters at each end (clause 4.2).
  2. Normal current. It is defined for one three-phase circuit above ground at 40 °C ambient. For other conditions it is calculated with Annex A (clause 4.4.1).
  3. Enclosure temperature. In open air, in a tunnel or in a shaft it must not exceed 80 °C, and parts that are touched must not exceed 70 °C. When buried it is limited so the soil does not dry out: a value between 50 °C and 60 °C is considered acceptable (clauses 4.4.2 and 2.102).

How the effect of an internal fault is limited

An internal arc is unlikely, because the gas is not contaminated and is not affected by moisture or animals. Even so, the standard requires its effect to stay inside the compartment where it started and, toward the outside, to be limited to a hole or a tear without fragments (clause 5.101). To achieve this, the design includes:

  • Compartments and sections separated by partitions and disconnecting units (clauses 5.103 and 5.104). The guide to pressures and compartments of a GIS applies the same idea.
  • Gas monitoring with a signal at the alarm pressure and at the minimum functional pressure (clause 5.9).
  • Thermal expansion compensated with sliding contacts between conductor and enclosure (clause 5.106).
  • Earthing. Enclosures are joined with guaranteed continuity, and the usual practice is to earth them at both ends (clause 5.3.102). The currents that flow in them are covered in earthing of a GIS.

Type and routine tests

Type tests are made on representative assemblies with the gas at the rated filling pressure. Routine tests are made on every unit manufactured.

TestWhat it checksClause
Dielectric with partial discharge (type)The insulation level. Partial discharges should not exceed 5 pC at the measuring voltage6.2 and 6.2.9
Temperature rise and resistance (type)That the rated current does not overheat conductor or enclosure6.4 and 6.5
Short-time and peak withstand current (type)That the main and earthing circuits withstand the fault6.6
Enclosures, partitions and tightness (type)Pressure strength and leaks6.101, 6.102 and 6.8
Dielectric and partial discharge (routine)Insulation at minimum functional pressure; discharges in critical parts such as insulators7.1 and 7.101
Main circuit resistance (routine)The value measured on the transport unit does not exceed 1.2 times the sum obtained in the type test7.3
Pressure of each enclosure (routine)1.3 times the design pressure if welded; 2.0 if cast7.102

Own elaboration with values from IEC 62271-204:2011; wording and format by Tiza Group.

An example of our own with assumed data: if the sum measured in the type test is 15 µΩ, the transport unit can measure up to 18 µΩ. With 19 µΩ the joints must be checked. For very long parts that ship dismantled, the routine dielectric test can be limited to the critical parts, and the complete section is tested on site.

On-site tests before energizing

After assembly and before commissioning, the standard requires verifying operation and dielectric strength (clause 10.3). The voltage and the resistance of the main circuit, the gas moisture and tightness, the welds and the corrosion protection are checked. The assembly, the wiring and the earthing are also reviewed (clauses 10.3.101 to 10.3.107).

The voltage test is the most delicate. The standard describes it this way:

  • It is made with the complete line, filled with gas at the rated pressure and, preferably, at the end of the on-site tests. It is also recommended after major parts have been dismantled.
  • A.c. is preferred and d.c. should not be used. 80 % of the a.c. voltage of the routine test is recommended.
  • Partial discharges are monitored. The conventional method of IEC 60270 may not be appropriate, and the standard asks to consider others, such as ultra-high frequency (UHF), without prescribing an acceptance level. The guide to the OMICRON UHF 800 describes that method.
  • The line must not be connected to cables, overhead lines, transformers or surge arresters: their charging current or their voltage-limiting effect prevent the test.
  • If the line is long, it is tested in sections, and the design must provide where to connect the test equipment without dismantling.

The on-site withstand voltage test explains how it is done with a.c. resonant systems.

For welds made on site, the standard accepts a pneumatic test with a factor of 1.1 if 100 % of the weld is inspected by radiography, ultrasound or an equivalent technique. With that inspection no separate tightness test is required (clauses 10.3.104 and 6.8.102). In service, the standard does not recommend mandatory inspections or pressure tests (clause 10.3).

Typical mistakes

  • Treating the GIL as a long GIS, without studying expansion, soil heating or corrosion.
  • Testing the line connected to surge arresters or transformers, or with d.c.
  • Not keeping the commissioning measurements. The standard asks the manufacturer to recommend what to measure and record to decide future maintenance (clause 10.2.5).

When to call us

At Tiza Group we recommend the test and the equipment your case needs, inside the quotation, so you do not pay for tests you do not need. Learn about our testing and commissioning service and our primary engineering service, and contact us for a quotation. To interpret contact resistance, SF6 and the operating mechanism of a GIS, you can use the disconnector and switchgear tests tool.

References

  • IEC 62271-204, High-voltage switchgear and controlgear - Part 204: Rigid gas-insulated transmission lines for rated voltage above 52 kV, edition 1.0 (2011). Clauses: 1.1, 2.101 to 2.103, 3.102, 4.2, 4.4, 5.3.102, 5.9, 5.101 to 5.106. Also 6.2 to 6.8, 6.101, 6.102, 7.1 to 7.3, 7.101, 7.102, 10.2.5 and 10.3. Current edition: 2022.
  • IEC 62271-203 and IEC 60270, to which the standard refers for the insulation level and partial discharge measurement.

Frequently asked questions

How does a GIL differ from a GIS?

A GIS groups the circuit breaker, disconnectors and busbars of a substation in metal enclosures. A GIL only transports energy, like a line. IEC 62271-204 is used when the installation is not covered by IEC 62271-203 (GIS): buried lines, lines in areas accessible to the public, or lines so long that their compartments exceed usual GIS practice (clause 1.1, note 3).

What voltage is applied to a GIL in the on-site test?

The standard sets no mandatory value. It recommends 80 % of the a.c. voltage of the routine test, applied as a.c. and not d.c., with partial discharge monitoring. The on-site test programme is agreed between the manufacturer and the user (clause 10.3.101).

Does a GIL need periodic inspections of the gas and the enclosure?

The standard neither specifies nor recommends mandatory inspections or pressure tests while the line is in service, so that moisture and dust are kept out of the inside (clause 10.3). The enclosure needs no periodic test if the gas is non-corrosive, dry, stable and inert and the anti-corrosion coating is monitored (clause 10.3.105).