Flexible Busbars in a Yard: Sag, Tension and Short Circuit

How sag and tension of a strung cable busbar relate, and what force appears between phases in a short circuit. Worked example of a 24 m span.

By Shadai García, CEO and protection engineer at Tiza Group.

side view: 24 m spansag f = 0.518 mH = 1 500 NH = 1 500 Nplan view: two phases 3 m apartABa = 3 mcables are pushed apart in the short circuitforces on the span (linear scale)static tension at the support: 1,505.6 Nforce between phases in the span, peak value: 8,909 Nwith H = 3,000 N the sag drops to 0.259 mf = w l² / (8 H) = 10.79 × 24² / (8 × 1,500)peak force per meter: 371.2 N/m× 24 m = 8,909 N, 5.9 times the static tensionlasts milliseconds: the cable responds to its impulseChainSpanSag and tensionShort circuitCheck© tizagrp.comside view: 24 m spansag f = 0.518 mH = 1 500 NH = 1 500 Nplan view: two phases 3 m apartABa = 3 mcables are pushed apart in the short circuitforces on the span (linear scale)static tension at the support: 1,505.6 Nforce between phases in the span, peak value: 8,909 Nwith H = 3,000 N the sag drops to 0.259 mf = w l² / (8 H) = 10.79 × 24² / (8 × 1,500)peak force per meter: 371.2 N/m× 24 m = 8,909 N, 5.9 times the static tensionlasts milliseconds: the cable responds to its impulseChainSpanSag and tensionShort circuitCheck© tizagrp.com
24 m flexible busbar: static sag and tension vs peak phase-to-phase force in a 31.5 kA short circuit. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

In a flexible busbar sag and tension depend on each other: more tension means less sag and more load on the gantry. The sag of a level span comes from w·l²/(8·H) and the tension at the support from H + w·f. In a short circuit a force between phases is added, growing with the square of the peak current and falling with phase spacing. The design first fixes tension and sag, and then checks the static fault force; the dynamic movement of the cable is outside this calculation.

Short answer

A flexible busbar is a cable strung between two gantries. Its shape is almost a parabola, and two data come from that shape and are designed together: the sag (how far the cable drops at midspan) and the tension (how hard the cable pulls at each support). With supports at the same level, the sag is f = w·l²/(8·H), with w the weight per metre, l the span and H the horizontal tension. The tension at the support is H + w·f. In a short circuit the force between phases is added, which rises with the square of the peak current and falls with the phase spacing. Only the static case is calculated here; the dynamics are in the guides on pinch and swing and on wind, ice and weight.

If you are still choosing between cable and tube, see bay and busbar conductors, flexible and rigid.

What each datum fixes

  • Span (l): the distance between gantries. A longer span raises the sag with the square of its length.
  • Weight per metre (w): mass of the cable times gravity. In a bundle of several subconductors the mass of all of them is added, plus that of spacers and fittings spread per metre.
  • Horizontal tension (H): the datum that is chosen. The installation is strung at a reference tension, at a given temperature.
  • Temperature: the cable lengthens when hot, the sag grows and the tension drops. In the cold the opposite happens. The design checks both extremes.
  • Ice and wind: add load; they are treated in the guide on mechanical stresses in busbars.

Sag and tension are tied together

For a cable with supports at the same level and a sag that is small against the span, the parabolic shape gives three simple results:

  • Sag: f = w · l² / (8 · H).
  • Tension at the support: T = H + w · f.
  • Cable length: L = l + 8 · f² / (3 · l).

All three come from the parabola. The first shows the design compromise: doubling H halves the sag, but the structure receives twice the horizontal force.

Sag matters for two reasons. It sets the clearance to the ground or to the equipment below, and it sets the swing: a cable with more sag swings more and gets closer to the neighbouring phase when wind or a short circuit moves it.

Worked example: a 24 m span

Example data (assumed): a 24 m span with supports at the same level. Cable of 1.1 kg/m. Reference horizontal tension of 1 500 N. Three-phase short circuit of 31.5 kA with peak factor κ = 1.8. Phase spacing: 3 m.

  1. Weight per metre: w = 1.1 × 9.81 = 10.79 N/m.
  2. Sag: f = 10.79 × 24² / (8 × 1 500) = 6 215 / 12 000 = 0.518 m. It is 2.2 % of the span, so the parabola is a good approximation.
  3. Tension at the support: T = 1 500 + 10.79 × 0.518 = 1 505.6 N.
  4. Cable length: L = 24 + 8 × 0.518² / (3 × 24) = 24.030 m. The cable is 30 mm longer than the span.
  5. With double tension (3 000 N): f = 10.79 × 576 / 24 000 = 0.259 m and T = 3 002.8 N. The sag halves and the load on the support doubles.
  6. Peak current: ip = 1.8 × √2 × 31 500 = 80 186 A.
  7. Peak force per metre between phases: F’ = 2·10⁻⁷ × 0.866 × 80 186² / 3 = 371.2 N/m. It is the same three-phase formula as in the rigid busbars guide.
  8. Effect of the span: with the same 1 500 N tension, a 30 m span would have f = 10.79 × 30² / (8 × 1 500) = 0.809 m, 56 % more sag than the 24 m one, because sag grows with the square of the span.
  9. Over the whole 24 m span: 371.2 × 24 = 8 909 N, which is 5.9 times the static tension of 1 505.6 N.

The last figure is not the tension the support will suffer. It is a peak value that lasts milliseconds, while a cable of 26 kg per span (1.1 × 24) moves slowly. What it indicates is that the cable will move appreciably and that you must calculate how much its tension rises and how close it gets to the neighbouring phase. The methods of the pinch and swing guide are used for that.

How it enters the calculation report

The busbar chapter of the report states the span, the cable, the reference tension and the temperature it is strung at, and delivers three results: the sag in the hottest condition, the tension in the coldest and the maximum horizontal force on each gantry. The first two come from the parabola of this calculation; the third adds the tension from ice and wind loads and from the fault, with the dynamic methods. That way, whoever reviews the gantry finds a single design value with its origin.

What is checked with the result

ResultCompared withWhat is decided
Sag at maximum temperatureMinimum clearanceGantry height or tension
Tension at minimum temperatureWorking load of fittings and insulatorsInsulator string and fittings
Horizontal force at the supportGantry capacityStructure and foundation
Approach in the short circuitMinimum phase-to-phase distanceSpacing or span

Insulators are chosen by their breaking loads. The guide on busbars and insulators of a substation explains how they relate.

What changes the result

  • A bundle of several cables weighs more and has spacers: w rises, and the behaviour in the fault changes.
  • Gantries at different levels make the parabola no longer symmetrical.
  • Hanging droppers (down-leads to the equipment) add weight at points and change the shape.
  • Actual stringing is controlled by measuring the sag at the temperature of the day; a tension different from the design one changes the whole picture.

Frequent mistakes

  • Designing at a single temperature. The sag on a cold day is not that of a hot day at maximum load.
  • Asking for minimum sag without looking at the structure. A clearance is solved by loading the gantry.
  • Taking the peak force as the fault tension. It is an indicator of the order of magnitude, not the result of the dynamic calculation.
  • Forgetting the weight of fittings and spacers in the value of w.
  • Using the parabolic formula on long spans or with large level differences.

Checklist

  • The span, weight per metre and reference tension are written with their temperature.
  • Sag is calculated at maximum temperature and tension at minimum.
  • Weight per metre includes spacers and fittings.
  • The peak current comes from the short-circuit study, not from an assumption.
  • The force between phases is calculated with the real spacing.
  • The approach in the fault is checked with a dynamic method.
  • Fittings and insulators are compared with the maximum tension.
  • Gantries are checked with the maximum horizontal force.

References

  • The parabolic formula and the force between conductors are elementary physics.
  • IEC 60865-1: calculation of the effects of short-circuit currents, method for flexible and rigid busbars.
  • Krieg, T.; Finn, J. (eds.). Substations. CIGRE Green Books. Springer, 2019.

Need this study?

The stringing and stress calculation of your substation busbars, together with the design of gantries and insulator strings, is part of our engineering design and studies service. We do it for projects in any country. Write to us.

Frequently asked questions

Why is the cable not tensioned to the maximum so that it hardly sags?

Because the tension would load the gantry, the insulator strings and the fittings. For the same cable, a tight conductor passes a larger horizontal force to the structure. In the example, doubling the tension from 1 500 to 3 000 N lowers the sag from 0.518 to 0.259 m, but it also doubles the horizontal force at each support.

Does the sag formula hold for any span?

The formula w·l²/(8·H) is the parabolic approximation of the cable. It is adequate when the sag is small compared with the span and the supports are at the same level, as in a yard span. For long line spans or large level differences the full cable curve is used.

What does the force between phases do to a flexible busbar?

In a short circuit the phases push or attract each other and the cable moves, its tension rises and it may approach the neighbouring phase. The peak value per metre only indicates the order of magnitude. The maximum tension and the approach are calculated with the dynamic methods for flexible busbars, as explained in the pinch and swing guide.