In direct current there is no zero crossing to put the arc out. In a photovoltaic string, the series arc (a loose connector) keeps the operating current and does not make any fuse work, while the parallel arc receives the current of the other strings. With an 800 V, 10.5 A string, the series arc dissipates 367.5 W with no trip, and the parallel arc reaches 4,480 W until the fuse opens.
Short answer
A DC arc does not extinguish by itself because the current does not pass through zero. In a photovoltaic string it appears in two ways: in series, when a conductor or connector separates and the current jumps the gap, and in parallel, when a path closes between poles or between strings. The series arc keeps the normal string current and fuses do not see it. The parallel arc also receives the current that the other strings send back and does make the fuse work, but the string itself may keep feeding it.
IEC 63027:2023 covers the devices that detect the series arc and interrupt the circuit. Fuses and disconnectors do not cover that case on their own.
Why a DC arc does not extinguish by itself
In an alternating-current network the current passes through zero twice per cycle. At that instant the arc loses its energy and can extinguish, and breakers take advantage of that moment. In direct current there is no such instant: the arc holds as long as the source delivers current and there is voltage to sustain it.
A DC switching device has to make the arc voltage exceed the source voltage. That is why the arc is lengthened, split into chambers or blown by a magnetic field. A loose contact or a badly tightened connector does none of that: it opens a small gap with current and voltage available, and the arc stays.
The arc resistance and the forces and heating from short-circuit in DC are covered in separate guides. For incident-energy calculations, IEEE 1584 is made for alternating-current systems; for DC other methods are used, as explained in the arc flash study.
Series arc and parallel arc
- Series arc: the string is interrupted and the current jumps the gap, for example at a loose connector, a fatigued cable or a bad solder joint. The current is what the modules deliver, at the maximum power point or less. It never exceeds the short-circuit current of the string.
- Parallel arc: it forms between conductors of different polarity, or between a conductor and ground. The current is what the modules of that string supply plus whatever the other strings of the combiner send back, limited by the impedance of the path.
The typical faults of the photovoltaic field include both cases with their symptoms.
Example data (assumptions)
All values are assumptions; they do not correspond to a real installation.
- String of 20 modules in series. Maximum-power voltage: 40 V per module, that is, 800 V per string.
- Maximum-power current: 10.5 A. Short-circuit current: 11.2 A.
- String fuse of gPV category, 20 A.
- Combiner with 10 identical strings in parallel.
- Series arc voltage: 35 V. Parallel arc voltage: 40 V.
Case 1: series arc
- Current through the arc: 10.5 A, the operating current.
- Ratio to the fuse: 10.5 / 20 = 0.525. The fuse is at little more than half of its rating: there is nothing to clear.
- Power in the arc: 35 V × 10.5 A = 367.5 W. In 10 s that is 3,675 J concentrated at a point the size of a connector.
- Power loss of the string: 35 V / 800 V = 4.4 %. The inverter sees it as a small drop in output, not as a fault.
A properly assembled connector has a very low contact resistance. A loose one raises it, heats up, degrades and ends up opening the gap across which the arc jumps. As a result, no overcurrent protection acts. The current is normal and the voltage drops only a little. It is the arc that can last longest without anyone noticing, and it is the case covered by the arc detection standard.
Case 2: parallel arc in the cable of a string
A short between the positive and negative poles of a string, in the cable between the modules and the fuse.
- Contribution of the other 9 strings through the fuse: 9 × 11.2 A = 100.8 A.
- Ratio to the fuse: 100.8 / 20 = 5.04. The fuse opens; the time depends on its curve, which is read in the manufacturer’s datasheet.
- Total current in the arc before it opens: 100.8 A + 11.2 A from the string itself = 112 A.
- Power in the arc: 40 V × 112 A = 4,480 W. If the fuse took 0.3 s (assumption), the energy would be 4,480 W × 0.3 s = 1,344 J.
After the fuse opens, the string itself keeps delivering up to 11.2 A. The arc may hold at 40 V × 11.2 A = 448 W. The fuse only removes what the other strings were contributing. That is why the fuse, arc detection and a sound cable are combined, and why it is worth reviewing the system’s rapid shutdown as part of the set.
What each protection sees
| Protection | Series arc | Parallel arc |
|---|---|---|
| String gPV fuse | Does not see it | Removes only the contribution of the other strings; the arc can continue on the current of its own string |
| DC ground fault | No, if there is no ground | Yes, if the arc involves ground (ground fault detection) |
| Arc detector (IEC 63027) | Yes | Outside the scope of the standard |
What to look at in a study
- Maximum string voltage when cold, higher than the maximum-power voltage, because it determines whether the arc is sustained and which switching device can interrupt it.
- Number of strings per combiner. With more strings in parallel the back-feed grows: with 10 strings, 100.8 A; with 20, 212.8 A.
- String fuse and its curve, with the clearing time at the back-feed value.
- Quality of the connectors and their tightening torque.
- Type of arc detection, if the inverter includes it, and what it does when it detects: open the string or stop the equipment.
- Incident energy for labeling, with a method valid for DC. Short-circuit and coordination in solar plants give the framework of currents.
Common mistakes
- Thinking the fuse protects against every type of arc.
- Assuming a DC arc extinguishes by itself.
- Calculating incident energy with an alternating-current method.
- Forgetting the back-feed from the other strings.
- Sizing the fuse only from the operating current.
- Treating a connector as an element that needs no maintenance.
Checklist
- Maximum string voltage when cold and at maximum power.
- Operating and short-circuit current of the string.
- Number of strings per combiner and back-feed calculated.
- String fuse, gPV category, rating and time curve.
- Arc detection: whether it exists, which arc it covers and what action it takes.
- Connectors and their assembly procedure.
- Incident-energy method suitable for DC.
Do you need this study?
We carry out fault-current and protection-coordination studies for solar plants, with the back-feed between strings and the selection of fuses and arc detection. Study work serves projects in any country. See our engineering design and studies service and write to us.
Related guides
- Photovoltaic field faults: ground, arc and connectors
- Arc flash study: IEEE 1584 and NFPA 70E
- Solar cable and MC4 connectors: standard and selection
- Rapid shutdown in solar systems
- Short-circuit and coordination in solar plants
References
- IEC 63027:2023, photovoltaic power systems: DC arc detection and interruption (scope: detection of series arcs).
Frequently asked questions
Why is a DC arc harder to put out than an AC arc?
Because alternating current passes through zero a hundred or a hundred and twenty times per second and the arc has a chance to extinguish each time. Direct current never passes through zero: to interrupt it, the arc voltage has to exceed the source voltage. That is why DC switching devices use arc chutes and magnetic blow-out.
Does a fuse protect against a series arc in a PV string?
No. In a series arc the current is the operating current of the string, equal to or lower than its short-circuit current, and the fuse is sized above it. The fuse sees nothing abnormal. What detects it is an arc detection device, which recognizes the characteristic electrical noise of the arc.
What does IEC 63027 cover?
The 2023 edition deals with the detection of series arcs and the interruption of the PV circuit in systems up to 1,500 V DC, with tests of detection and of response time. It leaves out the detection of parallel arcs and DC sources that are not photovoltaic.