A negotiated access standard is a level of performance between the automatic and the minimum access standard for one technical requirement of a generating system in the National Electricity Market. The connection applicant proposes it, the network service provider assesses it, AEMO advises where the Rules call it an AEMO advisory matter, and the agreed level becomes a registered performance standard. It cannot be weaker than the minimum access standard and cannot harm system security or other network users.
A negotiated access standard is the middle path that the National Electricity Rules (NER) give a generating system. It applies when the plant cannot reach the best level of performance for a technical requirement. It is agreed case by case, and it becomes a legally enforceable performance standard once registered. Clauses S5.2.6 (monitoring and control) and S5.2.7 (auxiliary supplies) of Schedule 5.2 show how the same model applies outside the electrical performance clauses. The wider framework is in the Australian electrical codes and grid connection guide.
Short answer
Every technical requirement of a generating system in Schedule 5.2 of the NER has up to three levels of performance:
- Automatic access standard: the highest level. A plant that meets it is accepted for that requirement without argument.
- Minimum access standard: the weakest level the Rules accept.
- Negotiated access standard: any level in between that the applicant proposes and the network service provider (NSP) and the Australian Energy Market Operator (AEMO) accept.
The applicant proposes a negotiated standard in the connection application under clause 5.3.4. The NSP assesses it. AEMO advises on the requirements the Rules call AEMO advisory matters. The accepted levels are written into the connection agreement and registered by AEMO as performance standards under rule 4.14.
Clause 5.3.4A sets the limits. A negotiated standard must be no less onerous than the minimum access standard. It must not adversely affect power system security or the system standards. It must not adversely affect the quality of supply of other network users. It must also meet the requirements for a negotiated standard in the schedule clause it relates to.
Which Rules apply
The Improving the NEM access standards – Package 1 Rule 2025 No. 6 rewrote parts of Chapter 5 and took effect on 21 August 2025. The new standards apply by default to connection enquiries that had no NSP response by that date. Projects that already had a response but no connection offer can elect to apply some or all of them. Clause numbers here follow the Rules as amended.
AEMO explains how it assesses proposals in its Access Standard Assessment Guide of January 2019. The applicant must show that the proposed level is as close as practicable to the automatic standard. The strongest case is a physical or technical limit of the plant, backed by studies.
What the three levels look like
Reactive power capability in clause S5.2.5.1 shows the pattern clearly.
- Automatic: the plant can supply and absorb reactive power at the connection point of at least 0.395 times its maximum active power. This holds across a voltage band of 5% above and below the mid-point voltage.
- Minimum: no reactive power capability is required at the connection point.
- Negotiated: a range of reactive power, or of power factor, at the connection point, set at or above the level the system needs to meet the system standards. It can also vary with active power if the plant design requires it.
If the plant cannot reach the level the system needs, the Rules list what the applicant must then do, as reasonable in the circumstances:
- pay the NSP compensation for the shortfall;
- install extra equipment;
- reach a commercial arrangement with another registered participant;
- agree operating arrangements for the conditions where the shortfall occurs.
Where S5.2.6 and S5.2.7 fit
Clause S5.2.6 deals with monitoring and control. S5.2.6.1 covers remote monitoring and remote control between the plant and the AEMO control centres. S5.2.6.2 covers communications equipment: the voice and data links to the control centres, their redundancy and the back-up supply that keeps them working after a loss of supply at the connection point. Both clauses are part of the performance standards. The plant proposes its level for each, and the NSP and AEMO assess it like any electrical requirement. The automatic and minimum levels of each clause are in the current Rules; check them against the communications design before the application.
Clause S5.2.7 covers auxiliary supplies. Sometimes a production system takes its auxiliary load through a connection point that does not carry its generation. The access standards for that point are then set under clause S5.3.5, as if the plant were a load customer.
Figure: the three access standard levels for reactive power at the connection point, with the negotiated level between automatic and minimum.
Worked example: reactive capability
These numbers are illustrative. A solar plant has a maximum active power of 80 MW at the connection point.
- Automatic standard: 0.395 × 80 = 31.6 Mvar, both supplied and absorbed. That is a power factor of 80 ÷ √(80² + 31.6²) = 80 ÷ 86.0 = 0.930 at full output.
- The design, after the reactive losses of the transformer and cables, delivers 26.0 Mvar each way at the connection point. That is 0.325 per unit and a power factor of 0.951.
- The gap to the automatic standard is 31.6 − 26.0 = 5.6 Mvar, or about 18% of the automatic level.
- The NSP’s studies then show what the system needs. Suppose absorption must reach 29.0 Mvar. The negotiated standard cannot be set below that, so the gap is 29.0 − 26.0 = 3.0 Mvar.
- The applicant closes the gap with one of the routes in the Rules, for example a reactive compensation unit sized above 3.0 Mvar. The agreed range is recorded in the performance standard.
The proposal is not “26 Mvar because that is what we have”. It is “26 Mvar from the inverters, plus compensation to reach the level the studies require”.
Checklist for the engineer
- List each Schedule 5.2 requirement the plant cannot meet at the automatic level, and the physical limit behind each one.
- Confirm which of them are AEMO advisory matters, because AEMO will review those.
- Run the studies that show the system effect of the proposed level, using the NSP’s network data.
- Write the proposal as the closest level the plant can reach, and show why it is no closer.
- Check each schedule clause for extra conditions on a negotiated level.
- Decide the route for any shortfall: compensation, extra equipment, commercial arrangement or operating arrangement.
- Plan how each agreed level will be demonstrated during commissioning, as described in GPS compliance testing and hold points.
Who certifies
Engineer registration is a state matter in Australia. In Queensland, professional engineering services must be provided by, or under the direct supervision of, a Registered Professional Engineer of Queensland (RPEQ). The engineer of record in your state reviews and certifies the design and the studies behind the proposal. Tiza does not stamp, sign or certify.
Related guides
The data AEMO asks for with the application is covered in AEMO model guidelines: data and models. For the studies behind a proposal, see the short-circuit study, load flow bus types and power plant controller testing.
How Tiza can help
If your project needs the power-system studies that support a negotiated access standard proposal, Tiza prepares them remotely and in English. Tiza delivers engineering and studies ready for your RPEQ (in Queensland) or chartered engineer to review and certify, and does not stamp, sign or certify itself. Contact us with the plant data and the NSP’s network information.
Frequently asked questions
What is a negotiated access standard?
It is a performance level agreed between the connection applicant, the network service provider and, for AEMO advisory matters, AEMO. It sits between the automatic access standard, which is the best level, and the minimum access standard, which is the weakest level the Rules accept. Once agreed, it is recorded in the connection agreement and registered as a performance standard.
Can a project negotiate any requirement down to the minimum?
No. Clause 5.3.4A requires a negotiated standard to be no less onerous than the minimum access standard, to protect power system security and the quality of supply of other network users. Some schedule clauses add conditions of their own, which the proposal must also meet.
Which clauses of Schedule 5.2 can have a negotiated access standard?
Most technical requirements in Schedule 5.2 define an automatic, a minimum and a negotiated standard, including reactive power capability in S5.2.5.1 and the communications equipment in S5.2.6.2. Clause S5.2.7 does not carry its own levels. It sends the auxiliary supply connection point to the load schedule, S5.3.5.