A transformer core is earthed at one point only. The core insulation test opens that connection, measures the resistance from the core to the tank with 500 V DC and checks that no second earth exists. ANSI/NETA MTS-2015 asks for a value comparable with earlier ones and not lower than 1 MΩ.
Standard edition. This guide is based on ANSI/NETA MTS-2015. The current edition is ANSI/NETA MTS-2023.
Short answer
The core insulation test checks that the transformer core is insulated from the tank at every point except one: its earth connection. That connection is opened, 500 V DC is applied between the core and the tank, and the resistance is read. ANSI/NETA MTS-2015 asks for a value comparable with earlier ones and not below 1 MΩ (clause 7.2.2, B.8 and D.8). It is a short test that detects a second core earth before it overheats the transformer.
Why the core is earthed at one point only
The core is a stack of electrical steel laminations. It sits inside the oil-filled tank, surrounded by earthed metal parts, and the magnetic flux runs through it. If it were not connected to any point, it would take a floating potential. That is why it is brought to earth with a conductor, normally up to an accessible terminal. The guide núcleo y devanados del transformador describes that connection.
It must be a single one. With two earth connections, the core and the tank form a closed loop that the transformer flux crosses. A voltage is induced in the loop and a current circulates that was not planned. That current heats the contact point and the oil around it, and combustible gases appear.
What the test measures and what the standard says
ANSI/NETA MTS-2015 includes the test in the section on liquid-filled transformers (7.2.2) and in the one on large dry-type transformers (7.2.1.2):
| Item | Liquid-filled transformers | Large dry-type transformers |
|---|---|---|
| Condition | Optional; if the core earth conductor is accessible, it is removed and the measurement is made | If the core is insulated and the earth conductor can be removed |
| Test voltage | 500 V DC | 500 V DC |
| Criterion | Comparable with earlier values and not below 1 MΩ | Comparable with earlier values and not below 1 MΩ |
| Clauses | 7.2.2, B.8 and D.8 | 7.2.1.2, B.8 and D.8 |
Wording and format by Tiza Group with the values of ANSI/NETA MTS-2015.
The criterion has two parts. The 1 MΩ minimum is a floor. The comparison with earlier values is more useful: a core that went from several gigaohms to a value close to the floor is changing even if it does not yet go below it. That is why the commissioning reading is worth keeping as a reference.
How the measurement is organized
With the transformer de-energized and out of service, the conductor that joins the core to the tank is removed from its terminal or link. The insulation resistance instrument is connected between that conductor and the tank, and 500 V DC is applied. The voltage and the time used by each manufacturer can differ; if the manual or the nameplate gives another value, the manufacturer’s is followed. Before applying the voltage, confirm in the manufacturer’s drawings whether there is a single core earth conductor or several. Each one is measured separately.
Example with our own data
A 138/13.8 kV power transformer has an accessible core earth conductor. At commissioning, 5,000 MΩ was measured. Three years later there are three assumed cases:
| Case | Reading | Interpretation |
|---|---|---|
| A | 4,200 MΩ | Comparable with the reference. The core is still insulated |
| B | 0.6 MΩ | Below 1 MΩ. It must be investigated: the core insulation is degraded or there is a partial contact |
| C | Close to zero | Direct contact of the core with the tank: there is a second earth |
In cases B and C, the reading alone does not say where the defect is. The oil and the gases are reviewed, compared with the dissolved gas analysis, and the manufacturer defines whether the contact point can be reached. A second earth can be a metal object left inside the tank or a deteriorated core insulation.
What to do with the result
- Comparable reading above 1 MΩ. The core is insulated. File the reading with the date, the voltage and the oil temperature.
- Low or falling reading. Investigate. Compare with the dissolved gas analysis and with the core temperature, which the manufacturer limits.
- Overheating gases without a clear electrical cause. Measure the core insulation as part of the diagnosis. This agrees with what the guide on elevated dissolved gases recommends.
Some transformers have a core ground alarm. IEC 61850-7-4 defines the data object CGAlm in the logical node YPTR (power transformer): its true value indicates that the core insulation has broken down. The alarm flags the problem but does not measure it; the insulation test gives the value.
Typical mistakes
- Leaving the core without an earth connection. It is the most important mistake. After the test, the conductor must go back to its point and a continuity check with an ohmmeter confirms that the core is connected again.
- Measuring with the conductor connected. The instrument reads the resistance to earth through the normal connection and gives a value close to zero that says nothing about the insulation.
- Measuring a single conductor when there are several. Each insulated connection is tested separately.
- Comparing with a reference from another unit. The reference value is that of the same transformer.
- Changing the test voltage between one measurement and the next. Always record the voltage used.
What we recommend
If your transformer has an accessible core earth conductor, ask for the test to be in the commissioning protocol and in every major maintenance. The insulation resistance test of windings does not replace it: it measures another insulation. With the free transformer insulation and polarization index tool you can check the temperature correction of the other readings.
When to call us
We test the core insulation and the other field tests as part of the commissioning of power transformers. For your case we recommend which tests and which equipment to use, and that goes inside the quote, so that you do not pay for tests your transformer does not need. Write to us and we will quote.
Related guides
- Core and windings of the transformer: losses and tests
- Three-limb and five-limb core: what changes
- Elevated dissolved gases in the transformer: what to do
- Transformer insulation resistance: IR, PI and DAR
- Maximum core temperature of the transformer
- Transformer maintenance: dry-type and oil-filled
References
- ANSI/NETA MTS-2015, Standard for Maintenance Testing Specifications for Electrical Power Equipment and Systems, clause 7.2.1.2 (B.8 and D.8) and clause 7.2.2 (B.8 and D.8). The current edition is 2023.
- IEC 61850-7-4, Communication networks and systems for power utility automation - Part 7-4: Basic communication structure - Compatible logical node classes and data classes, edition 2.0, logical node class YPTR, data object CGAlm.
Frequently asked questions
Why is the transformer core earthed at one point only?
A single point fixes the core potential without closing a loop. If a second earth connection appeared, the loop formed would be linked by the transformer flux and a current would circulate in it. That current heats the core and can generate gases that show up in the dissolved gas analysis.
What minimum value does the standard require for the core insulation?
ANSI/NETA MTS-2015 asks for a value comparable with those obtained before and not lower than 1 MΩ at 500 V DC (clause 7.2.2, test value D.8). If the manufacturer states another voltage or its own value, the manufacturer's is used.
Can the test be done if the core connection is not accessible?
No. The test requires opening the core earth connection, which is why the standard makes it conditional on the core earth conductor being accessible (clause 7.2.2, B.8). Without access to the conductor there is no field test; the manufacturer says what alternative exists.