Tiza Group

Home / Guides / Communications and control / Interlocking and control logic

Substation switching: opening, closing and safety

What substation switching is, in what order breakers, disconnect switches and grounds are operated, the golden rules and what interlocks prevent.

By Shadai García, electrical engineer, founder and CEO of Tiza Group. Reviewed by the Tiza Group engineering team · .

89BL157-15257-289L57LVTline L1remote end123BCULR43SCADAClose 57L of L1189L of L1 open2dead (detector or 27)CILO.EnaClstruefalsefalseClose 89L of L13L1: 52, 57-2 and 57L openCILO.EnaClstruefalsefalsecommand: open 52 of L1 · executedcommand: open 89L of L1 · executedcommand: open L1 89B · executedrequest: open the remote end · lock and tagvoltage detector: 0 V on the linecommand: close 57L of L1 · executedrejected: ground closedIEC 61850CSWICILOXCBRXSWI© tizagrp.com89BL157-15257-289L57LVTline L1remote end123BCULR43SCADAClose 57L of L1189L of L1 open2dead (detector or 27)CILO.EnaClstruefalsefalseClose 89L of L13L1: 52, 57-2 and 57L openCILO.EnaClstruefalsefalsecommand: open 52 of L1 · executedcommand: open 89L of L1 · executedcommand: open L1 89B · executedrequest: open the remote end · lock and tagvoltage detector: 0 V on the linecommand: close 57L of L1 · executedrejected: ground closedIEC 61850CSWICILOXCBRXSWI© tizagrp.com
Substation switching: de-energizing a line bay and CILO interlocking. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

Switching is the set of operations used to change the state of the grid safely: taking equipment out for maintenance, transferring a load or restoring service. The principle is always the same: the breaker makes and breaks the current; disconnect switches only isolate, without load; and grounding is applied only after absence of voltage has been verified. To de-energize, the breaker opens first and then the disconnect switches; to energize, the order is reversed. Interlocks block the wrong operation, but they do not replace the golden rules.

What switching is

Switching is the set of operations used to run an electrical network safely. In a substation, switching means changing the state of breakers, disconnect switches and grounding switches to:

  • take equipment out of service for maintenance or testing and return it afterwards;
  • transfer circuits between buses or between sources;
  • energize a line, a transformer or a new expansion;
  • restore service after a trip.

Each switching operation is planned on the up-to-date single-line diagram, coordinated with whoever operates the grid, and carried out in an order that never forces a device to do something it was not designed for.

What each device can do

DeviceLoad currentFault currentRole in switching
Circuit breakerMakes and breaksMakes and breaksInterrupts and restores current
Disconnect switchNoNoIsolates with a visible gap, with negligible current
Medium-voltage load-break switchMakes and breaksDoes not interrupt itBreaks load in medium-voltage networks, often with fuses
Grounding switchNoWithstands short-circuit current for a short timeGrounds a section already isolated

IEC 62271-102 defines the disconnector as the device that opens or closes a circuit when the current is negligible or when there is no significant change in the voltage across its terminals; IEEE C37.30.1 covers the same equipment in North America. Hence the central rule: the breaker opens first and closes last.

General order to de-energize

Taking a bay out of service (general order)
  1. 01Open the breakerInterrupts the current; its open position is confirmed at the control point and at the equipment
  2. 02Open the disconnect switchesOn both sides of the breaker, now without current
  3. 03Lock and tagControls locked against closing and a tag at each isolation point
  4. 04Verify absence of voltageWith a detector rated for the voltage level, at the work location
  5. 05Ground and short-circuitClose the grounding switches and, if needed, apply temporary grounds at the work site

To energize, the order is reversed (the first time it is done in a new installation has its own checks, described in first energization of a new substation): temporary grounds are removed and grounding switches opened, the disconnect switches are closed with the breaker open, and finally the breaker is closed. If both sides are live, the closing is supervised by the synchronism check 25; if one side is dead, by the dead-line and live-bus mode.

That is the general principle. Each installation has its own switching procedures, approved by the utility or the substation owner, and in substations of the interconnected system switching is coordinated with their control center. When the substation configuration comes into play, the order adapts to it: a double-bus arrangement, for example, allows a circuit to be transferred between buses without interrupting it.

Golden rules

Opening the breaker and the disconnect switches does not make equipment safe. De-energized work is the work done after following the golden rules of electrical safety:

  1. Visible isolation.
  2. Lock to prevent re-energization.
  3. Verification of absence of voltage.
  4. Grounding and short-circuiting.
  5. Covering adjacent live parts.
  6. Marking out the work area.

In Europe, EN 50110-1 groups them into the well-known five rules: disconnect, secure against reconnection, verify absence of voltage, ground and short-circuit, and protect against adjacent live parts. In North America, NFPA 70E and OSHA 29 CFR 1910.269 set the lockout/tagout steps for an electrically safe work condition, and IEEE 1048 covers temporary protective grounding.

What interlocks prevent

Substation interlocking consists of conditions that block a command when the operation would be dangerous. The three basic ones:

  • Do not move a disconnect switch with its bay breaker closed (except the parallel transfer cases the logic allows).
  • Do not close a grounding switch onto a section that may be live.
  • Do not close a disconnect switch onto a grounded section.

They are implemented mechanically, electrically, with keys or as logic in the bay controller (in IEC 61850, the CILO logical node), and they are resolved at equipment, bay or station level; see bay and station interlocking. You can build the condition matrix of a bay with our free interlocking table tool.

Where each operation can be commanded from (control center, substation HMI, panel or equipment) is defined by the control levels and the local/remote selector. Repetitive operations, such as moving a bay to the other bus, can be automated with automatic switching sequences.

Switching at medium voltage

At medium voltage, most switching is done in metal-enclosed switchgear: the breaker sits on a withdrawable truck or has a three-position switch (closed, open, grounded), and the mechanical interlocks of the switchgear prevent racking out the truck with the breaker closed or opening the door without grounding.

Common mistakes

  • Operating from an outdated drawing that does not show a tie, a generator or a backup source.
  • Trusting position indication alone without checking at the equipment.
  • Releasing interlocks to “save time”: every release must be authorized and logged; see interlock bypass.
  • Energizing with forgotten temporary grounds, one of the classic causes of a fault on closing.
  • Closing a transformer breaker without considering inrush current, which can operate poorly set protection.

We can help with your switching logic

Interlocks, control levels and automatic sequences live in the bay controllers and relays. Our team configures and modifies them remotely, worldwide: see remote relay configuration. On site, we test the complete logic, in Colombia, or elsewhere on request. Contact us with your substation configuration.

References

  • IEC 62271-102: AC disconnectors and earthing switches.
  • IEEE C37.30.1: requirements for high-voltage air switches.
  • IEC 61936-1: power installations exceeding 1 kV AC.
  • EN 50110-1: operation of electrical installations, general requirements (five rules).
  • NFPA 70E, Standard for Electrical Safety in the Workplace.
  • IEEE 1048, IEEE Guide for Protective Grounding of Power Lines.
  • IEC 61850-7-4: logical nodes CILO, CSWI, XCBR and XSWI.

Frequently asked questions

Why can a disconnect switch not be opened under load?

Because a disconnect switch is built to isolate, not to interrupt current. If it is opened under load, an arc forms between its contacts with no means of extinction: it can damage the equipment, cause a phase-to-phase or ground fault and injure anyone nearby. That is why the breaker opens first and the interlock prevents moving the disconnect switch while the breaker is closed.

What is the order to energize a bay?

In general terms, temporary grounds are removed and grounding switches opened, the disconnect switches are closed with the breaker open, and finally the breaker is closed, with synchronism check if both sides are live. The exact sequence is set by the switching procedure of each installation.

Is the interlock enough to work safely on equipment?

No. Interlocks prevent wrong switching, but personnel safety depends on following the golden rules: visible isolation, lock against re-energization, verification of absence of voltage, grounding and short-circuiting, protection against adjacent live parts and marking out the work area.

WhatsApp