Tiza Group

Home / Guides / Studies and design

Feeder Hosting Capacity: How to Calculate It

What hosting capacity is, which criteria limit it, and a deterministic calculation with a voltage limit on a 13.2 kV feeder.

By Shadai García, CEO and protection engineer at Tiza Group.

substation, 1.01 pu5213.2 kV feeder, 8 kmR = 3.2 Ω, X = 2.8 Ω=~52load 0.4 MWwithout generation: voltage dropswith generation, voltage risesvoltage along the feeder (pu)1.001.050 km8 kmlimit 1.05 puwithout generation: 1.003power that can be connected at the end (MW)2.58 MWpf 1, setpoint 1.01 pu3.12 MWpf 1, setpoint 1.00 pu3.46 MWpf 0.95 absorbing, 1.01 puChainSubstationFeederGenerationVoltage criterion© tizagrp.comsubstation, 1.01 pu5213.2 kV feeder, 8 kmR = 3.2 Ω, X = 2.8 Ω=~52load 0.4 MWwithout generation: voltage dropswith generation, voltage risesvoltage along the feeder (pu)1.001.050 km8 kmlimit 1.05 puwithout generation: 1.003power that can be connected at the end (MW)2.58 MWpf 1, setpoint 1.01 pu3.12 MWpf 1, setpoint 1.00 pu3.46 MWpf 0.95 absorbing, 1.01 puChainSubstationFeederGenerationVoltage criterion© tizagrp.com
13.2 kV feeder: voltage rises toward the end when generation is connected and reaches the 1.05 pu limit at 2.58 MW; control measures raise the capacity. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

The hosting capacity of a feeder is the largest amount of distributed generation it can receive without breaching any criterion: voltage, conductor loading, protection or power quality. The deterministic method evaluates the worst case, minimum load and maximum generation; the probabilistic method simulates many cases and returns a risk. On long medium-voltage feeders, voltage rise is usually the limit.

Short answer

The hosting capacity of a feeder is the largest amount of distributed generation that can be connected without breaching any operating criterion. There are four criteria: voltage, loading of conductors and transformers, protection and power quality. The capacity is the lowest of the four powers.

On long medium-voltage feeders the criterion that limits most is voltage: generation pushes power into the network and raises the voltage at the connection point. The study can be deterministic, with one extreme scenario, or probabilistic, with many scenarios and a risk of breach. The worked example solves the deterministic calculation with a voltage limit. The complete connection study is part of the studies the CNO requires to connect generation.

The limiting criteria

  • Voltage. Generation reduces the current flowing from the substation, and can even reverse it; the voltage rises toward the end of the feeder. The opposite case is also checked, maximum load without generation, which sets the minimum voltage. See voltage regulation in the distribution network.
  • Thermal loading. The current in the most loaded section cannot exceed the conductor capacity or that of the substation transformer. It is checked with maximum generation and with minimum load, because reverse flow also heats the equipment.
  • Protection. Generation changes the fault current the relays see, can leave the head-end protection blind to a remote fault, and forces a review of reclosing and islanding behavior. See the protection requirements for distributed generation.
  • Power quality. Inverter harmonics and fast voltage variations. They are checked against the limits in IEEE 519 with inverter-based resources.

Deterministic and probabilistic method

The deterministic method takes the extremes: the minimum feeder load together with maximum generation, which is the most demanding case for voltage, and the generation connected at the least favorable point, normally the end of the feeder. The result is a single value, quick to calculate and conservative: the limit is reached in a case that in real operation may occur a few hours a year.

The probabilistic method repeats the calculation thousands of times with loads, generation and locations that vary according to probability distributions, and returns, for each generation size, the probability of breaching a limit. It lets you define an acceptable risk and gets a larger capacity than the deterministic method. In exchange it needs more data (load and generation profiles) and more calculation time.

Worked example: voltage limit

Example data (assumed values, not measured): 8 km, 13.2 kV feeder with a 0.40 + j0.35 Ω/km conductor. Substation voltage: 1.01 pu. Maximum voltage limit in the example: 1.05 pu (the real limit is set by the network operator). Minimum feeder load: 0.4 MW, concentrated at the end. The generation is connected at the end. Conductor thermal capacity: 250 A.

1. Feeder impedance. R = 0.40 × 8 = 3.2 Ω. X = 0.35 × 8 = 2.8 Ω.

2. Voltage margin. The substation is at 1.01 × 13 200 = 13 332 V and the limit is 1.05 × 13 200 = 13 860 V. The margin is 13 860 − 13 332 = 528 V.

3. Voltage rise. For a net power P flowing up the feeder at unity power factor, the approximate rise between ends is ΔV = P · R / V, with V = 13 200 V. Setting it equal to the margin: P = 528 × 13 200 / 3.2 = 2.178 MW net.

4. Capacity with minimum load. The load at the end consumes part of the generation: 2.178 + 0.4 = 2.578 MW. The hosting capacity by voltage, at unity power factor, is 2.58 MW.

5. Thermal check. The current at the head is 2.178 MW / (√3 × 13.2 kV) = 95 A, below 250 A: voltage governs.

6. Control measures. If the inverters absorb reactive power at 0.95 power factor, the Q/P ratio is 0.329 and the rise becomes ΔV = P · (R − 0.329 · X) / V: P = 528 × 13 200 / (3.2 − 0.329 × 2.8) = 3.057 MW net, that is, 3.057 + 0.4 = 3.46 MW. If the substation setpoint drops from 1.01 to 1.00 pu, the margin rises to 660 V and the capacity becomes 660 × 13 200 / 3.2 = 2.723 MW net, 3.12 MW. The current in the 0.95 case is 141 A, also below the thermal limit.

The formula is a first-order approximation; the real study calculates a full load flow with the network model. The results compare as follows:

CaseCapacity by voltage
Power factor 1, setpoint 1.01 pu2.58 MW
Power factor 1, setpoint 1.00 pu3.12 MW
Power factor 0.95 absorbing, setpoint 1.01 pu3.46 MW

How the study continues

The 2.58 MW figure is not yet the hosting capacity: protection and power quality still have to be checked, and the lowest value kept. The minimum voltage at maximum load without generation is also checked, along with operation with generation spread over several points, which usually allows more total power than a single generator at the end. In the probabilistic version the fixed minimum load is replaced by hourly profiles and the probability of exceeding 1.05 pu is calculated for 1, 2, 3 MW and more.

Mistakes to avoid

  • Calculating the voltage with maximum load and concluding that the feeder can host more: the critical case is minimum load.
  • Checking only voltage and forgetting protection.
  • Placing the generation in the middle of the feeder: the end is the least favorable case.
  • Presenting the deterministic result as the real capacity, when it is a conservative limit.
  • Using the substation voltage setpoint without confirming its operating band.

Checklist

  • Feeder impedance and conductor data confirmed.
  • Substation voltage and its operating band defined.
  • Voltage and loading limits set with the network operator.
  • Minimum and maximum load taken from measurements.
  • Generation placed at the least favorable point and at other points.
  • Protection and power quality checked.
  • Control measures (power factor, setpoint) evaluated separately.
  • Final result confirmed with a full load flow.

References

  • Calculations and data: our own, with assumed data for the example. The voltage limits in the example are illustrative: the applicable value is set by the network operator of each project.

Need this study?

Calculating the hosting capacity of your feeders, with voltage, thermal loading and protection cases, is part of our engineering design and studies service. We do it for projects in any country. Write to us.

Frequently asked questions

Which criteria limit the hosting capacity of a feeder?

Four groups: voltage (the rise caused by generation can push the voltage out of the allowed range), loading of conductors and transformers, protection (the fault current changes and selectivity or detection can be lost) and power quality (harmonics and fast variations). The hosting capacity is the lowest of the powers that each criterion allows.

What is the difference between the deterministic and the probabilistic method?

The deterministic method evaluates one or a few extreme scenarios, such as minimum load with maximum generation, and returns a single conservative value. The probabilistic method repeats the calculation with many randomly generated combinations of load, generation and location, and returns the probability of breaching a limit for each generation size. It lets you accept a small risk in exchange for a larger capacity.

How can hosting capacity be increased without changing the feeder?

With control measures: lowering the voltage setpoint at the substation, making the inverters absorb reactive power, or limiting the exported power in the critical hours. Each measure has an effect that is evaluated in the study. It also increases by reinforcing the conductor or shortening the electrical distance to the substation, which are construction works.

WhatsApp